Hello my group members...I would like to know the Difference between : 1) Activity % complete 2)
Performance % complete 3) Schedule % complete 4) Duration % complete ....Thanks alot
5 days ago
Like CommentFollow Flag More
abdul raqheeb likes this
5 comments
Follow Dave
Dave Caldwell http://www.planningengineer.net/oracle-primavera-p6-different-between-activity-
percent-complete/
4 days ago Like
Follow WILLIAM
WILLIAM WEDDENDORF Since you have been "endorsed" for Primavera 6, deploy the HINTS
feature and it will give you the answer.
4 days ago Like
Follow Cherie
Cherie Chance Activity % Complete is calculated based on your Activity % Complete Type and can
be based on Duration % Complete, Physcial % Complete or Units % Complete values
Performance % Complete is based on the Earned Value Technique selected for the WBS. It can be
tied to Activity % Complete, 0/100, 0/50, WBS Milestones or WBS custom % complete.
Schedule % Complete is calculates how much of baseline duration has been completed using the
data date and the baseline dates. It does not take into account actual progress.
Duration % Complete represents the % complete based on the planned duration compared to the
remaining duration of the activity.
-
7/27/2019 Primavera 5 % Complete
2/5
1- Duration % complete:Duration % of Original (or Planned) threshold value is expressed as a percentage. An issue is generated
if the ratio of the activitys actual duration to its original or planned duration (actual duration / original or
planned duration * 100) falls beyond the threshold values.
How it is calculated in primavera p6 : Duration percent Complete(P6) = ( [Original Duration]
[Remaining Duration] ) / [Original Duration]
Example of calculating Duration % Complete : Original Duration: 20d , Actual Duration: 15d and
Remaining Duration: 18d [Duration % Complete] = (20-18)/20 = 10%
to use the Duration % complete for an activity you should select the Duration % complete type from the
activity details general tap as shown in the photo below
Duration percent complete primavera p6
Duration percent Complete for WBS Elements
The previous explanation was focused on Duration % Complete for Activities. Duration % Complete is
also calculated for WBS Elements, but I strongly recommend you not to use Duration % Complete to
track a WBS Elements progress. Thus I have not included an explanation of the calculations here.
2- Units % complete:Each assigned resource and assigned expense creates units in Primavera P6. The number of units
depend on duration of the activity and your current settings the Units % is calculated from the actual
and remaining units, Units % Complete = [Actual Units / At Completion Units] x 100. see the figure
below for more understanding
http://www.planningengineer.net/oracle-primavera-p6-different-between-activity-percent-complete/duration-percent-complete-primavera-p6/ -
7/27/2019 Primavera 5 % Complete
3/5
unitspercent complete primavera p6
Units % Complete for WBS Elements
The previous explanations were for activities Units % Complete. This field is calculated in the same way
for WBS Elements. However, I recommend you to use Earned Value and Performance % Complete for
the WBS Elements instead of Units % Complete and Duration % Complete.
Different between Duration % complete and Units %Complete:
- When units are not distributed uniformly, the Units % Complete will not be uniform relative to the timeand will not equal to duration percentage complete.
- Even if the units are distributed uniformly and the original duration not equal to at completion duration
the units percentage complete will not equal to duration percentage complete.
- Only when units are distributed uniformly and the original duration equal to at completion duration the
units percentage complete will equal to duration percentage complete.
3- Physical % complete:Physical percentage complete is a calculated field, which displays the percent complete based on the
relative weights of the completed steps versus the incomplete steps. The physical progress of an activity
is a manually-entered value determined by the user. The Physical % Complete is not rolled-up to
WBS level, because its based on an external parameters, unknown to the software.
to use the Physical % complete for an activity you should select the Physical % complete type from the
activity details general tap as shown in the photo below
http://www.planningengineer.net/oracle-primavera-p6-different-between-activity-percent-complete/units-percent-complete-primavera-p6/ -
7/27/2019 Primavera 5 % Complete
4/5
Physical percent complete primavera p6
4- Schedule % complete:schedule percent complete for an activity based on a straight forward calculation in primavera p6,
schedule percent complete = ( [Data Date] [Baseline Start] ) / ( [Baseline Finish] [Baseline Start] )
When the Data Date is earlier than the Baseline Start date, Schedule % Complete is zero, when its after
the Baseline Finish data, Schedule % Complete is 100%. Otherwise, Schedule % Complete show what
percentage of the Baseline duration is passed by the Data Date. see the figure below for better
understanding.
Schedule percent complete primavera p6
Schedule % Complete for WBS Elements:
The Schedule % Complete of the WBS Element will be the ratio of the Baseline Costs before the Data
Date to the Total Baseline Cost.
The costs before the Data Date are called the Planned Value, or PV for short (Also called BCWS
Budgeted Cost of Work Scheduled). The total baseline cost is called Budget At Completion or BAC for
http://www.planningengineer.net/oracle-primavera-p6-different-between-activity-percent-complete/schedule-percent-complete-primavera-p6/http://www.planningengineer.net/oracle-primavera-p6-different-between-activity-percent-complete/physical-percent-complete-primavera-p6/http://www.planningengineer.net/oracle-primavera-p6-different-between-activity-percent-complete/schedule-percent-complete-primavera-p6/http://www.planningengineer.net/oracle-primavera-p6-different-between-activity-percent-complete/physical-percent-complete-primavera-p6/ -
7/27/2019 Primavera 5 % Complete
5/5
short. We can now formulate the calculation of Schedule % Complete for WBS Elements as: Schedule %
Completed (WBS) = PV / BAC
5-Performance % Complete:The percentage presentation of EV is usually called Performance % Complete. Performance % Complete
of the Activities under the same WBS Element is calculated by one of these six options:
1. By Activity % Complete and without resource curves
2. By Activity % Complete and with resource curves
3. By WBS Milestones
4. By 0/100 method
5. By 50/50 method
6. By x/(100-x) custom method
(1) and (2) are continuous and the rest of them are milestone progresses. (1) and (2) are dependent on
the Activity
progress, (3) is completely independent from the Activity progress, and the rest of them are only
influenced by Actual Start
and Actual Finish of the Activities.