    Old Oak Common overview

  • 8/17/2019 2016-05 OOC presentation 100516-1

    2/26

    2

    Overview

    Construction Programme

    Phase 1 – enabling works

    Phase 2 – Tunneling prep, conveyors and Victoria Road widening

    Phase 3 – Civil engineering works & compoundsPhase 4 – CrossrailTurnback, flyover and tunneling

    Phase 5 – Tunneling and GWML works

    Phase 6 – Fit out and commissioning

    Operational Phase – OSD, location

  • 8/17/2019 2016-05 OOC presentation 100516-1

    3/26

    3

    Indication of current construction programme

  • 8/17/2019 2016-05 OOC presentation 100516-1

    4/26

    4

    • Environmental surveys

    • Ground investigation

    • Utility protection and diversion works

    • Demolition and site compound

    preparation

    • Old Oak Common Station

    • Victoria Road tunnel drive

    • Victoria Road crossover

    • Atlas Road

    • Euroterminal

    Phase 1 – Enabling works

  • 8/17/2019 2016-05 OOC presentation 100516-1

    5/26

    5

    • Retaining wall/diaphragm wall construction

    •Bulk excavation of eastern end of station box

    • Bulk excavation of western end of crossover box

    • Conveyor system to Atlas Road and

    Euroterminal

    • Establish precast segment factory

    • Convert Willesden Euroterminal railhead

    • Victoria road widening

    • Ready for tunnelling

    Phase 2 –Tunnelling preparation

  • 8/17/2019 2016-05 OOC presentation 100516-1

    6/26

    6

    OOC conveyors

    Old Oak Common Laneconveyor

    • 2020-2023

    • 0800-1800 Mon-Fri

    0800-1300 Sat

    Victoria Road conveyor• 2019-2023

    24/7 (potentially)

  • 8/17/2019 2016-05 OOC presentation 100516-1

    7/267

    Victoria Road conveyor

  • 8/17/2019 2016-05 OOC presentation 100516-1

    8/268

    Excavated materials (EM) conveyor

    • A specialist system of EM conveyors will be used to handle excavated material

    from tunnelling and box excavation to a surface disposal point

    • The assessment of the construction noise in the Environmental Statement took

    into account noise from the proposed conveyors

    • Typical mitigation could include in line with draft Code of Construction Practice:

    • Maintenance including lubrication of the rollers

    • Limiting drop heights for loading and unloading

    • Locating motor units away from sensitive receptors

    • Partial or full enclosure of drive units and belt near sensitive receptors

    • Damping down material to avoid dust creation

  • 8/17/2019 2016-05 OOC presentation 100516-1

    9/269

    Insert conveyor slideMitigation examples

  • 8/17/2019 2016-05 OOC presentation 100516-1

    10/2610

    Potential widening of Victoria Road

    • LB Ealing have put forward a proposal not to widen Victoria Road for HGV

    movements, instead their proposal is to widen the road to include a cycle lane.

    HS2 is reviewing the proposal and will report back to LB Ealing on its outcomes in

    May 2016.

  • 8/17/2019 2016-05 OOC presentation 100516-1

    11/2611

    • Logistics tunnel to Atlas Road compound (24-

    hour working)

    • Bulk excavation of station and crossover boxes

    • Construction of Old Oak Common tunnels (24-

    hour working)

    • Demolition of Heathrow Express depot

    Phase 3 –Civil engineering works

  • 8/17/2019 2016-05 OOC presentation 100516-1

    12/2612

    Willesden Euroterminal Main Compound – indicative site layout

  • 8/17/2019 2016-05 OOC presentation 100516-1

    13/26

    13

    Victoria Road tunnel main drive and crossover box

    Offices and staff welfare

    Storage

    Site workshops

    Circulation

  • 8/17/2019 2016-05 OOC presentation 100516-1

    14/2614

    • Complete box excavation of station box

    • Crossrail turnback tracks

    • Flyover/viaduct construction

    • Construct Euston and Northolt tunnels (24-hour

    working)

    Phase 4 –Civil engineering works and tunnelling

  • 8/17/2019 2016-05 OOC presentation 100516-1

    15/26

    15

    Requirement for GWML Up-Relief Flyover

    • Under additional provision 2 (AP2) to the bill, HS2 Ltd promotes turnback sidingsalong the Wycombe rail corridor which also provides passive provision for a WestCoast Main Line to Crossrail link if promoted in the future.

    • Three turnback sidings are provided to enable up to 12 Crossrail trains per hour

    (tph) to turn back at Old Oak Common station.

    • In addition AP2 promotes a flyover on the Great Western Main Line Up-Relief toprovide a grade-separation junction to avoid conflicting movements betweenCrossrail train turning back and other services.

    Network Rail supports HS2 Ltd’s assessment that a grade separated junction isnecessary. The intensity of use of this junctions in both directions is likely topresent a significant risk to train operations due to conflicting train movements.

  • 8/17/2019 2016-05 OOC presentation 100516-1

    16/26

    16

    Turnback/viaduct/sub-station plan

  • 8/17/2019 2016-05 OOC presentation 100516-1

    17/26

    17

    Turnback/viaduct/sub-station section 1 & 2

  • 8/17/2019 2016-05 OOC presentation 100516-1

    18/26

    18

    Turnback/viaduct/sub-station section 3

  • 8/17/2019 2016-05 OOC presentation 100516-1

    19/26

    19

    Great Western Main Line Up-Relief Line

    Flyover - visualisation

    Wells House Road

    The Flyover structure is a maximum of 18m above Old Oak Common

    Lane and approximately 10m above the existing GWML rail level

    Ph T lli d GWML k

  • 8/17/2019 2016-05 OOC presentation 100516-1

    20/26

    21

    • Construct Northolt tunnel• Construct Euston tunnel• Old Oak Common Great Western Main Line

    station• trackwork

    • bridge works

    Phase 5 –Tunnelling and GWML works

    Ph 6 Fit t d i i i

  • 8/17/2019 2016-05 OOC presentation 100516-1

    21/26

    22

    • Fit-out Old Oak Common station andVictoria Road crossover

    • Fit-out railway• Close and lower Old Oak Common Lane for

    up to one year starting last quarter of 2025

    Phase 6 – Fit-out and commissioning

  • 8/17/2019 2016-05 OOC presentation 100516-1

    22/26

    23

    Old Oak Common Lane lowering

    • Lowering of Old Oak Common Lane under GWML bridges required to provided

    improved headroom and enable access for double-decker buses via Old Oak

    Common Lane south of the station

    • Construction works will start in last quarter of 2025 (post peak of construction

    activity) and are expected to last 12 months with a 2m walkway maintained

    • Indicative cross section of the works provided below

  • 8/17/2019 2016-05 OOC presentation 100516-1

    23/26

    24

    Old Oak Common Lane lowering

    • The works will involve the strengthening of the existing

    boundary wall between Wells House road and Old Oak

    Common Lane.

    • Infrequent temporary access to the back garden of

    approximately 25 properties is required for baseline

    surveys. The majority of the construction works will be

    undertaken from Old Oak Common Lane.

  • 8/17/2019 2016-05 OOC presentation 100516-1

    24/26

    25

    Potential Over-site development at Old Oak Common

    • Oversite development (OSD) is potential development, not included in the

    scheme being proposed by HS2 Ltd that may be promoted by others, either over

    the high speed railway or on the land returned after construction. This will require

    separate planning permissions, supported by a separate environmental

    assessment.

    • HS2 Ltd is in discussion with the Old Oak and Park Royal Development

    Corporation on the potential of amending the design of the station so as not to

    preclude future OSD development .

  • 8/17/2019 2016-05 OOC presentation 100516-1

    25/26

    26

    Old Oak Common station – location & entrance

    • As set out in paragraph 66 of the Promoter’s Response to the Select Committee’s

    Second Special Report of Session 2015-16:

    ‘In developing its detailed design and construction plans, and as part of its efforts to

    mitigate, as far as reasonably practicable, the impact of the Proposed Scheme onresidents of Wells House Road, the Promoter will consider a range of options for thelocation of the vehicular entrance to the Old Oak Common Station main compound

     from Old Oak Common Lane.’ 

    Other mitigation measures will reduce construction effects such as noise, light and

    air pollution so far as reasonably practicable, in accordance with the Code ofConstruction Practice.’ 

    Operational phase

  • 8/17/2019 2016-05 OOC presentation 100516-1

    26/26

    Operational phase