    Gestin de Costos en la Construccin

    GESTIN DE COSTOS EN

    CONSTRUCCIN

  • 7/25/2019 PPT Costos-Clase2

    2/19

    Gestin de Costos en la Construccin

    TIPOS DE CONTRATOS DECONSTRUCCIN

  • 7/25/2019 PPT Costos-Clase2

    3/19

    Gestin de Costos en la Construccin

    Contratos de Construccin

    Hay 2 clasificaciones:

    Tipos de contrato por el alcance de trabajo

    Tipos de contrato por forma de pago

    Clasificaciones

    Fuente: Libro Modern Construction Lean Project Delivery and Integrated Practices, Lincoln H Forbes, Syed M. Ahmed

  • 7/25/2019 PPT Costos-Clase2

    4/19

    Gestin de Costos en la Construccin

    CONTRATOS DE CONSTRUCCIN

    Tipos de contrato segn alcance de trabajo

    Oferta de Construccin

    La forma ms frecuente de contratacin, en la que el dueo conceptualiza elproyecto y contrata por separado el diseo y la construccin, siendo esta ltimael nico alcance del contratista.

    Oferta EPC (Engineering, Procurement and Construction)

    El contratista recibe la ingeniera bsica del cliente y tiene por alcancedesarrollar la ingeniera de detalle y la procura y la construccin.

    Concesiones

    El contratista es el responsable del diseo, construccin y operacin de lainfraestructura por el periodo de tiempo de la concesin

    Fuente: Libro Modern Construction Lean Project Delivery and Integrated Practices, Lincoln H Forbes, Syed M. Ahmed

  • 7/25/2019 PPT Costos-Clase2

    5/19

    Gestin de Costos en la Construccin

    CONTRATOS DE CONSTRUCCIN

    Tipos de contrato segn la forma de pago

    Contrato a Precios Unitarios

    El precio de Obra se determina por los precios unitarios y los metrados. El pago serealiza con base en el precio unitario del contrato y los metrados ejecutados para lo cual,cliente aprueba los metrados presentados en la valorizacin.

    Contrato a suma alzada

    Se fija un precio relacionado a un alcance. Los precios se mantienen fijos aunque hayavariacin de metrados, tarifas, rendimientos durante la ejecucin del proyecto. El nicocaso en el que se puede ajustar el precio es si existe algn cambio de alcance. El pagose realiza con base en el % de avance que se tiene por partida.

    Fuente: Libro Modern Construction Lean Project Delivery and Integrated Practices, Lincoln H Forbes, Syed M. Ahmed

  • 7/25/2019 PPT Costos-Clase2

    6/19

    Gestin de Costos en la Construccin

    CONTRATOS DE CONSTRUCCIN

    Tipos de contrato segn la forma de pago

    Contrato de margen sobre el costo o Por administracin

    Este contrato fija un fee sobre los costos del contratista. El pago consiste en elreembolso de los costos en los que el contratista incurre para la ejecucin del proyectoms un margen sobre el mismo. El contratista debe presentar sustentos de los

    materiales, mano de obra, subcontratas y gastos generales consumidos.

    Contrato Colaborativo (Integrated Project Delivery)

    Se firma en la etapa de anteproyecto y se tiene como involucrados al dueo, contratista ydiseador. Comienza con la fijacin del costo objetivo (Target Cost) acordado por todos,

    siendo transparentes los costes directos e indirectos y pactando como se gestiona elriesgo; es decir, las desviaciones positivas respecto al costo objetivo esperado delproyecto. Se comparten los riesgos y las sobreutilidades en los porcentajes que seconvenga en cada caso.

    Fuente: Libro Modern Construction Lean Project Delivery and Integrated Practices, Lincoln H Forbes, Syed M. Ahmed

  • 7/25/2019 PPT Costos-Clase2

    7/19Gestin de Costos en la Construccin

    PRESUPUESTO OFERTA DECONSTRUCCIN

  • 7/25/2019 PPT Costos-Clase2

    8/19Gestin de Costos en la Construccin

    Presupuesto Oferta:

    Etapas en un estudio de un presupuesto

    Preparacin

    presupuesto

    Planificacin

    propuesta

    Preguntas y

    respuestas

    Visita a terreno

    Metodologa constructiva

    Estrategia de propuesta

    Revisin bases

    Invitacin

    Compra de bases

    Lista de partidas

    Metrados

    Planificacin

    de la obra

    Fuente: Libro Procesos y Tcnicas de Construccin 2da Edicin, Hernan de Solminihac, Guillermo Thenoux

    Contin

    ua

  • 7/25/2019 PPT Costos-Clase2

    9/19Gestin de Costos en la Construccin

    Presupuesto Oferta:

    Etapas en un estudio de un presupuesto

    Analisis de P.U

    costo directo por

    partida

    Planificacin de recursos

    Organizacin de la obra

    Estrategia de propuesta

    Cuantificacion de riesgo

    Organizacin de empresa

    Garantias

    Materiales

    Mano de Obra

    Equipos

    Curva ocupacional

    Programa de uso de equip

    Flujo de caja

    Precio unitario

    Personal, Instalacin,

    Equipamiento

    Imprevistos

    GG oficina principal

    Costo garanta

    Costo financiero

    Costo directo

    Utilidad

    Gastos generales

    indirectos

    Gastos generales

    Presupuesto

    final

    Fuente: Libro Procesos y Tcnicas de Construccin 2da Edicin, Hernan de Solminihac, Guillermo Thenoux

    Sigue

  • 7/25/2019 PPT Costos-Clase2

    10/19Gestin de Costos en la Construccin

    Presupuesto Oferta:

    Entregables de un presupuesto oferta

    1. Resumen de presupuesto

    2. Presupuesto detallado: Anlisis de precios unitarios + presupuesto

    descompuesto

    3. Gastos generales

    4. Cronograma valorizado / Flujo de caja

    5. Consideraciones y Exclusiones

  • 7/25/2019 PPT Costos-Clase2

    11/19Gestin de Costos en la Construccin

    Presupuesto Oferta:Ejercicio de Anlisis: Revisin Presupuestos Histricos

    Razones para que los ratios del 2do proyecto sean menores?

    Dpto: LIMA

    Fecha may-13

    AC: 49,128.03 AC: 4,074.84

    PRECIO (S/.)RATIO (S/.

    / m2)% PRECIO (S/.)

    RATIO

    (S/. / m2)%

    1.00 Obras prel iminares y provis ionales 2,604,465S/. 53.0S/. 7.5% 283,629S/. 69.6S/. 10.7%2.00 Estructuras 12,861,404S/. 261.8S/. 37.0% 925,780S/. 227.2S/. 34.8%3.00 Arquitectura 13,181,332S/. 268.3S/. 37.9% 963,861S/. 236.5S/. 36.2%4.00 Instalaciones Elct ricas 2,937,776S/. 59.8S/. 8.4% 154,106S/. 37.8S/. 5.8%5.00 Instalaciones Sani tar ias 3,192,607S/. 65.0S/. 9.2% 252,925S/. 62.1S/. 9.5%6.00 Instalaciones Mecanicas -S/. -S/. 0.0% 0.0%7.00 Par tidas Complementar ias -S/. 0.0% 78,891S/. 19.4S/. 3.0%

    34,777,584S/. 707.9S/. 100.0% 2,659,191S/. 652.6S/. 100.0%

    4,105,326S/. 83.6S/. 11.8% 352,019S/. 86.4S/. 13.2%

    1,972,507S/. 40.2S/. 5.7% 226,031S/. 55.5S/. 8.5%

    40,855,417S/. 831.6S/. 117.5% 3,237,241S/. 794.4S/.

    7,353,975S/. 149.7S/. 582,703S/. 143.0S/.48,209,393S/. 981.3S/. 3,819,944S/. 937.4S/.

    PROYECTO 02

    Costo Directo

    Gastos Generales

    Utilidades

    SUB - TOTAL (sin IGV)

    IGV

    TOTAL

    ITEM DESCRIPCION

    PROYECTO 01

    CONSIDERACIONES:

    1. Ambas estructuras son de ductilidad limitada.

    2. El nivel socio econmico al cual esta orientado el producto es el mismo.

    3. Edificio Proyecto 01 (4 dptos x planta) Edificio Proyecto 02 (6 dptos x planta)

  • 7/25/2019 PPT Costos-Clase2

    12/19Gestin de Costos en la Construccin

    Presupuesto Oferta:

    PRECIO (S/.)RATIO (S/.

    / m2)% PRECIO (S/.)

    RATIO (S/.

    / m2)% PRECIO (S/.)

    RATIO (S/.

    / m2)%

    1.00 Obras preliminares y provisionales 2,163,300S/. 44.0S/. 5.5% 2,251,753S/. 45.8S/. 5.9% 2,324,553S/. 47.3S/. 5.9%2.00 Estructuras 13,100,222S/. 266.7S/. 33.2% 13,337,671S/. 271.5S/. 35.0% 13,951,274S/. 284.0S/. 35.6%

    3.00 Arquitectura 13,864,552S/. 282.2S/. 35.1% 15,754,660S/. 320.7S/. 41.3% 14,015,650S/. 285.3S/. 35.7%4.00 Instalaciones Elctricas 3,555,287S/. 72.4S/. 9.0% 3,311,468S/. 67.4S/. 8.7% 3,915,293S/. 79.7S/. 10.0%5.00 Instalaciones Sanitarias 3,608,710S/. 73.5S/. 9.1% 3,500,000S/. 71.2S/. 9.2% 2,520,569S/. 51.3S/. 6.4%6.00 Instalaciones Mecanicas -S/. -S/. 0.0% -S/. -S/. 0.0% -S/. -S/. 0.0%7.00 Partidas Complementarias 3,158,073S/. 64.3S/. 8.0% -S/. -S/. 0.0% 2,502,921S/. 50.9S/. 6.4%

    39,450,145S/. 803.0S/. 100.0% 38,155,552S/. 776.7S/. 100.0% 39,230,260S/. 798.5S/. 100.0%

    4,105,326S/. 83.6S/. 10.4% 4,768,137S/. 97.1S/. 12.5% 5,065,811S/. 103.1S/. 12.9%

    1,972,507S/. 40.2S/. 5.0% 2,715,767S/. 55.3S/. 7.1% 2,353,816S/. 47.9S/. 6.0%45,527,978S/. 926.7S/. 115.4% 45,639,456S/. 929.0S/. 119.6% 46,649,887S/. 949.6S/. 118.9%

    8,195,036S/. 166.8S/. 8,215,102S/. 167.2S/. 8,396,980S/. 170.9S/.53,723,014S/. 1,093.5S/. 53,854,558S/. 1,096.2S/. 55,046,866S/. 1,120.5S/.

    CONST 3CONST 1

    TOTAL

    ITEM DESCRIPCION

    CONSTR 2

    Costo Directo

    Gastos Generales

    Utilidades

    SUB - TOTAL (sin IGV)

    IGV

    Ejercicio de Anlisis:

    Consideraciones: Tres ofertas distintas (3 postores) para el mismo proyecto

    Pregunta: Qu razones hay para que sean distintas?

  • 7/25/2019 PPT Costos-Clase2

    13/19Gestin de Costos en la Construccin

    PRESUPUESTO LNEA BASE PARACONSTRUCCIN

  • 7/25/2019 PPT Costos-Clase2

    14/19Gestin de Costos en la Construccin

    PRESUPUESTO LNEA BASE DE CONSTRUCCIN

    Estudio depresupuesto

    Oferta

    Planeamientode Obra

    Anlisis deRiesgos

    Anlisis deBrechas

    PresupuestoLnea Base

    Adjudicacin del

    Proyecto

    Inicio deProyecto

  • 7/25/2019 PPT Costos-Clase2

    15/19Gestin de Costos en la Construccin

    LNEA BASE DE CONSTRUCCIN

    REVISIN DE BRECHAS

    Tarifas o precios de insumos: Materiales, incluyendo fletes. Jornales, sueldos, salarios, leyes sociales, incrementos retroactivos. Tarifas de alquiler de equipos y subcontratas (alcances).

    Cantidades: Metrados

    Productividad: Mano de Obra y Equipos

    Velocidad de Produccin: Plazo Costo Indirecto

  • 7/25/2019 PPT Costos-Clase2

    16/19Gestin de Costos en la Construccin

    Taller: Simulacin de Lnea Base de Construccin

    PROYECTO REUBICACIN DE POZO SEPTICO

  • 7/25/2019 PPT Costos-Clase2

    17/19Gestin de Costos en la Construccin

    Consideracin de riesgos en el Presupuesto

    Gestin del Riesgo

    Identificacin delos Riesgos

    AnlisisCualitativo

    AnlisisCuantitativo

    Calificaciones al

    Presupuesto

    AdicionamientodeContingencias

    Fuente: Adaptado del PMBOK: Gestin de los Riesgos del Proyecto

  • 7/25/2019 PPT Costos-Clase2

    18/19Gestin de Costos en la Construccin

    Consideracin de riesgos en el Presupuesto

    Gestin del Riesgo

    Proyecto: Reubicacin de Pozo Septico

    Presupuesto: 63,300.00

    Plazo (das) 60.00

    % Cind Costo % Plazo Plazo (das)

    01

    Desconocimiento del

    volumen real de solidos asuccionar

    Mayor volumen de solidos a

    succionar

    Elevar los costos de S/C del

    proyecto - M A A 20.00% 6.32% 4,000 6.67% 4

    02Variacin precio de tuberias Mayor precio de mercado Elevar los costos de

    materiales- B B B 10.00% 0.47% 300 0.00%

    03Variacion de precios de la

    MO

    Mayor precio que el

    considerado en e l ppto.

    Elevan los costos de la MO- M B B 20.00% 0.56% 357 0.00%

    Impacto 901.40 Soles

    Anlisis Cualitativo y Cuantitavivo de Riesgos

    Item CausaTipo

    (+/-)

    Probabili

    dadRiesgo Impacto Impacto

    Calificaci

    n

    Impacto en costo

    % de Probab.

    Identificacin de riesgos Cal. cualitativa Cal. cuantitativa

    Anlisis de riesgos

    Impacto plazo de ruta

  • 7/25/2019 PPT Costos-Clase2

    19/19