CURVA DE AVANCE DE OBRA OBRA : CONSTRUCCION DEL RESERVORIO APOYADO DE 1500 M3 - BUENA VISTA - BARRANCA PROPIETARIO : GOBIERNO REGIONAL DE LIMA CONTRATISTA : CONSORCIO PORVENIR REGION : LIMA DEPART. : LIMA PROV. : BARRANCA DISTR. : BARRANCA LOCALIDAD : BUENA VISTA : ING. ALEXANDER P. HUERTAS JARA RESIDENTE DE OBRA : ING. VICTOR HUGO CARBAJAL ALZAMORA PRESUPUESTO : 708,655.46 S/IGV - Inc. Expediente Tecnico AVAN VALORI S/ # # # # # # # # # # # Set # # # AVANCES AVANCE PROGRAMADO AVANCE REAL VALORIZACION MENSUAL ACUMULADO MENSUAL ACUMULADO S/. % S/. % S/. % S/. % Jun-08 55,339.93 7.81% 55,339.93 7.81% 94,637.40 13.60% 94,637.40 13.60% Jul-08 252,892.63 35.69% 308,232.56 43.50% 94,249.47 13.54% 188,886.87 27.14% Aug-08 317,181.45 44.76% 625,414.01 88.25% 127,321.69 18.30% 316,208.56 45.44% Sep-08 83,241.44 11.75% 708,655.46 100.00% TOTAL (*) 708,655.46 100.00% 316,208.56 45.44% (*) SUB TOTALES S/I.G.V. ATRASO -42.81% NOTA : La Supervision ha elaborado la Curva de Avance de Obra, en base al Calendario de Obra Valorizado Actualizado vigente. SUPERVISOR DE OBRA junio-08 julio-08 agosto-08 septiembre-08 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 13.60% 27.14% 45.44% 7.81% 43.50% 88.25% 100.00% AVANCE REAL AVANCE PROGRAMADO

Upload: ebertdcordova

Post on 18-Dec-2015

6 views

Category:

Documents


3 download

DESCRIPTION

INGENIERIA

TRANSCRIPT

CURVA DE AVANCE CURVA DE AVANCE DE OBRAOBRA: CONSTRUCCION DEL RESERVORIO APOYADO DE 1500 M3 - BUENA VISTA - BARRANCAPROPIETARIO: GOBIERNO REGIONAL DE LIMACONTRATISTA: CONSORCIO PORVENIRREGION: LIMADEPART.: LIMAPROV.: BARRANCADISTR.: BARRANCALOCALIDAD: BUENA VISTASUPERVISOR DE OBRA: ING. ALEXANDER P. HUERTAS JARARESIDENTE DE OBRA: ING. VICTOR HUGO CARBAJAL ALZAMORAPRESUPUESTO :708,655.46S/IGV - Inc. Expediente TecnicoAVANCESAVANCE PROGRAMADOAVANCE REALVALORIZACIONMENSUALACUMULADOMENSUALACUMULADOS/.%S/.%S/.%S/.%Oct-0443,404.646.12%43,404.646.12%87,286.0512.32%87,286.0512.32%Nov-04267,149.3737.70%310,554.0143.82%577,566.9181.50%664,852.9693.82%Dec-040.000.00%310,554.0143.82%0.000.00%664,852.9693.82%Jan-051,159,497.96163.62%1,470,051.96207.44%1,686,926.99238.05%2,351,779.95331.87%Feb-053,607,427.71509.05%5,077,479.67716.49%2,371,031.51334.58%4,722,811.46666.45%Mar-054,447,485.82627.59%9,524,965.491344.09%2,887,038.13407.40%7,609,849.591073.84%Apr-055,545,306.55782.51%15,070,272.032126.60%3,705,539.48522.90%11,315,389.071596.74%May-055,669,634.90800.06%20,739,906.932926.66%3,924,821.81553.84%15,240,210.882150.58%Jun-056,082,523.37858.32%26,822,430.303784.97%Jul-054,528,960.35639.09%31,351,390.654424.07%Aug-054,180,671.31589.94%35,532,061.965014.01%Set-054,115,985.71580.82%39,648,047.685594.83%Oct-054,726,144.97666.92%44,374,192.656261.74%Nov-054,547,166.69641.66%48,921,359.336903.41%Dec-05534,351.3275.40%49,455,710.656978.81%TOTAL (*)49,455,710.656978.81%15,240,210.882150.58%141731.091063866119886.2584.5871213579AVANCESAVANCE PROGRAMADOAVANCE REALVALORIZACIONMENSUALACUMULADOMENSUALACUMULADO8,979,130.72S/.%S/.%S/.%S/.%1263832.12Jun-0855,339.937.81%55,339.937.81%94,637.4013.60%94,637.4013.60%1961408.5Jul-08252,892.6335.69%308,232.5643.50%94,249.4713.54%188,886.8727.14%Aug-08317,181.4544.76%625,414.0188.25%127,321.6918.30%316,208.5645.44%Sep-0883,241.4411.75%708,655.46100.00%NOTA : CORREGIR PROXIMO MESTOTAL (*)708,655.46100.00%316,208.5645.44%(*) SUB TOTALES S/I.G.V.ATRASO-42.81%2,165,277.63NOTA : La Supervision ha elaborado la Curva de Avance de Obra, en base al Calendario de Obra Valorizado Actualizado vigente.406438.8733,356.21381328.285131.72381,328.2833356.215098.18414,684.49414684.49416668.772,887,038.13234220.68324675.989248.9617191.78585337.4345807.3421295.6613484.8830530.5411118.38411118.38166289.3658472.8527367.3120184.33272313.85272313.85

CURVA DE AVANCE

AVANCE REALAVANCE PROGRAMADO

Avance Mensual ProgramadoAvance Real ProgramadoAVANCE PROGRAMADO MENSUAL VS AVANCE REAL MENSUAL