CRONOGRAMA DE EJECUCION FISICA DEL PIPALTERNATIVA 01: CIRCULACION CON ADOQUINES DE CONCRETO
PROYECTO: “CREACIÓN DE PLATAFORMA DEPORTIVA EN EL A.H. NUEVO TALARITA Y SUS JAZMINES, DISTRITO DE CASTILLA - PIURA”
UBICACIÓN: A.H. NUEVO TALARITA Y SUS JAZMINES, CASTILLA - PIURA - PIURA
ITEM COMPONENTE UNIDAD CANTIDADAVANCE FISICO MES A MES (%)
Costo Directo Sub Total IGV (18%) MES 1 MES 2 MES 3 MES 4 MES 5
I EXPEDIENTE TECNICO Und 1.00 15,200.00 1,520.00 1,520.00 18,240.00 3,283.20 21,523.20 100.00% 0.00% 0.00% 0.00% 0.00%
II LOSA DEPORTIVA Und 1.00 139,456.58 13,945.66 13,945.66 167,347.90 30,122.62 197,470.52 0.00% 40.00% 60.00% 0.00% 0.00%
III GRADERIAS Y MURO DE ALBAÑILERIA Und 1.00 97,916.61 9,791.66 9,791.66 117,499.93 21,149.99 138,649.92 0.00% 10.00% 40.00% 50.00% 0.00%
IV CERCO METALICO Und 1.00 67,298.99 6,729.90 6,729.90 80,758.79 14,536.58 95,295.37 0.00% 20.00% 30.00% 50.00% 0.00%
V Und 1.00 48,339.97 4,834.00 4,834.00 58,007.96 10,441.44 68,449.40 0.00% 10.00% 20.00% 70.00% 0.00%
VI GRASS SINTÉTICO E INST. ELECTRICAS Und 1.00 24,599.83 2,459.98 2,459.98 29,519.80 5,313.56 34,833.36 0.00% 0.00% 30.00% 70.00% 0.00%
VII EQUIPAMIENTO Und 1.00 20,760.00 2,076.00 2,076.00 24,912.00 4,484.16 29,396.16 0.00% 0.00% 20.00% 80.00% 0.00%
VIII MEDIDAS DE MITIGACIÓN Und 1.00 7,918.13 791.81 791.81 9,501.76 1,710.32 11,212.07 0.00% 30.00% 40.00% 30.00% 0.00%
IX Und 1.00 24,200.00 2,420.00 2,420.00 29,040.00 5,227.20 34,267.20 0.00% 28.00% 31.00% 37.00% 4.00%
TOTAL 631,097.20 3.41% 20.87% 39.24% 36.26% 0.22%
Gastos Generales (10%)
Utilidad (10%)
Costo por Componente
SARDINELES Y CIRCULACION CON ADOQUINES DE CONCRETO
SUPERVISION Y REVISION DE LIQUIDACION
CRONOGRAMA DE EJECUCION FINANCIERA DEL PIPALTERNATIVA 01: CIRCULACION CON ADOQUINES DE CONCRETO
PROYECTO: “CREACIÓN DE PLATAFORMA DEPORTIVA EN EL A.H. NUEVO TALARITA Y SUS JAZMINES, DISTRITO DE CASTILLA - PIURA”
UBICACIÓN: A.H. NUEVO TALARITA Y SUS JAZMINES, CASTILLA - PIURA - PIURA
ITEM COMPONENTE UNIDAD CANTIDADAVANCE FINANCIERO MES A MES (%)
Costo Directo Sub Total IGV (18%) MES 1 MES 2 MES 3 MES 4 MES 5
I EXPEDIENTE TECNICO Und 1.00 15,200.00 1,520.00 1,520.00 18,240.00 3,283.20 21,523.20 21,523.20 0.00 0.00 0.00 0.00
II LOSA DEPORTIVA Und 1.00 139,456.58 13,945.66 13,945.66 167,347.90 30,122.62 197,470.52 0.00 78,988.21 118,482.31 0.00 0.00
III GRADERIAS Y MURO DE ALBAÑILERIA Und 1.00 97,916.61 9,791.66 9,791.66 117,499.93 21,149.99 138,649.92 0.00 13,864.99 55,459.97 69,324.96 0.00
IV CERCO METALICO Und 1.00 67,298.99 6,729.90 6,729.90 80,758.79 14,536.58 95,295.37 0.00 19,059.07 28,588.61 47,647.68 0.00
V Und 1.00 48,339.97 4,834.00 4,834.00 58,007.96 10,441.44 68,449.40 0.00 6,844.94 13,689.88 47,914.58 0.00
VI GRASS SINTÉTICO E INST. ELECTRICAS Und 1.00 24,599.83 2,459.98 2,459.98 29,519.80 5,313.56 34,833.36 0.00 0.00 10,450.01 24,383.35 0.00
VII EQUIPAMIENTO Und 1.00 20,760.00 2,076.00 2,076.00 24,912.00 4,484.16 29,396.16 0.00 0.00 5,879.23 23,516.93 0.00
VIII MEDIDAS DE MITIGACIÓN Und 1.00 7,918.13 791.81 791.81 9,501.76 1,710.32 11,212.07 0.00 3,363.62 4,484.83 3,363.62 0.00
IX Und 1.00 24,200.00 2,420.00 2,420.00 29,040.00 5,227.20 34,267.20 0.00 9,594.82 10,622.83 12,678.86 1,370.69
TOTAL 631,097.20 21,523.20 131,715.65 247,657.67 228,829.99 1,370.69
Gastos Generales (10%)
Utilidad (10%)
Costo por Componente
SARDINELES Y CIRCULACION CON ADOQUINES DE CONCRETO
SUPERVISION Y REVISION DE LIQUIDACION