G CRONOGRAMA VALORIZADO DE ADQUISICION DE MATERIALES PROYECTO : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO" DISTRITO SANDIA PLAZO DE EJECUCION 180 dias Calendario PROVINCIA SANDIA REALIZADO POR: DEPARTAMENTO PUNO DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PRESUPUESTADO DESEMBOLSO 1ER MES 2DO MES 3ER MES 4TO MES 5TO MES CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO 1 OPERADOR DE EQUIPO LIVIANO hh 12.35 7.5 92.655 92.65 92.65 2 TOPOGRAFO hh 159.18 8.13 1294.143156 1294.45 94.73 770.30 5.02 40.79 58.96 479.48 0.48 3.87 3 OPERARIO hh 20081.18 5 100405.907 100418.54 243.14 1,215.83 9,127.87 45,645.07 8,537.33 42,692.01 443.61 2,218.34 1,716.49 8,583.53 4 OFICIAL hh 6422.76 6.88 44188.567472 44225.81 77.59 534.27 3,161.78 21,771.37 2,885.61 19,869.73 178.14 1,226.65 119.64 823.78 5 PEON hh 27864.1 3.75 104490.3795 104495.31 6,026.84 22,601.73 10,130.25 37,990.23 3,570.78 13,391.05 3,499.64 13,124.28 4,544.32 17,042.02 6 LUBRICANTE PARA TUBERIA gln 0.05 32 1.6 1.6 0.05 1.60 7 CLAVOS PARA MADERA C/C 2" kg 1.96 5 9.78 9.79 1.96 9.79 8 CLAVOS PARA MADERA C/C 3" kg 1.96 5 9.78 9.79 1.96 9.79 9 CLAVOS 4" kg 213.55 5 1067.742 1067.76 10.09 50.45 203.46 1,017.31 10 CLAVOS 3" kg 7.13 5 35.635 38.01 1.51 8.04 5.62 29.97 11 CLAVOS DE 5" kg 2 5 10 10 2.00 10.00 12 CLAVOS 2 1/2" kg 21.93 5 109.641 109.65 0.25 1.23 21.68 108.42 13 ALAMBRE NEGRO N°16 kg 217.46 5 1087.314 1087.32 9.43 47.13 190.51 952.59 2.75 13.75 14.77 73.85 14 ALAMBRE NEGRO N°8 kg 153.9 5 769.479 769.49 6.90 34.51 126.02 630.08 17.07 85.34 3.91 19.56 15 CLAVOS kg 20.22 5 101.11 101.11 16.98 84.91 3.24 16.20 16 PERNO HEXAG. C/ROSCA CORRIENTE 2.1/2"x3/8" cto 0.86 35.5 30.672 30.67 0.86 30.67 17 CONO DE REBOSE PVC SAP 4"X2" und 1 15 15 15 1.00 15.00 18 CONO DE REBOSE PVC SAP 4"X4" und 1 25 25 25 1.00 25.00 19 PUERTA METALICA 0.90MX1.70M (INC. ACCESORIOS Y GLB 116 381 44196 44196 116.00 44,196.00 20 VENTANA METALICA 0.40MX0.40M (03 UND) (INC. ACC GLB 216 55 11880 11880 216.00 11,880.00 21 ROTURAS DE TESTIGOS DE CONCRETO und 40 15 600 600 40.00 600.00 22 REJILLA DE FIERRO DE 1/4" und 106 3 318 318 106.00 318.00 23 ACERO DE REFUERZO FY=4200 GRADO 60 kg 2367.16 3.8 8995.20192 9004.01 2,356.27 8,962.59 10.89 41.42 24 FIERRO CORRUGADO 3/8" var 12.28 15 184.26 184.26 12.28 184.26 25 FIERRO CORRUGADO 1/2" var 39.6 25 990 990 39.60 990.00 26 ARENA FINA m3 47.82 35 1673.763 1684.61 3.57 125.85 19.69 693.67 24.56 865.09 27 ARENA m3 162.27 35 5679.4535 5729.58 141.57 4,998.80 20.70 730.78 28 PIEDRA MEDIANA DE 4" m3 7.78 40 311.304 311.3 7.78 311.30 29 PIEDRA GRANDE m3 27.39 30 821.73 821.73 27.39 821.73 30 ARENA GRUESA m3 0.18 35 6.3 6.3 0.18 6.30 31 MATERIAL PARA CAMA DE APOYO m3 74.79 15 1121.904 1121.9 74.79 1,121.90 32 PIEDRA MEDIANA 3" m3 15.89 25 397.25 397.25 15.89 397.25 33 GRAVA DE 1" A 2" m3 3 55 165 165 3.00 165.00 34 MATERIAL DE CAMA DE APOYO m3 122.84 15 1842.6 1842.6 122.84 1,842.60 35 PIEDRA m3 0.3 25 7.5 7.5 0.30 7.50 36 GRAVA m3 113.3 25 2832.5 2832.5 113.30 2,832.50 37 TANQUE BAJO W.C. C/TAPA COLOR BLANCO pza 112 55.7 6238.4 6238.4 112.00 6,238.40 38 INODORO und 112 88.3 9889.6 9889.6 112.00 9,889.60 39 DUCHA C/ACCESORIOS. und 100 35 3500 3500 100.00 3,500.00 40 REGISTRO DE BRONCE DE 2" und 100 12 1200 1200 100.00 1,200.00 41 SUMIDERO CROMADO DE 2" und 196 9 1764 1764 196.00 1,764.00 42 SUMIDERO BRONCE 1/2" und 100 4 400 400 100.00 400.00 43 GRIFO DE ESFERA DE 1/2" TIPO JARDIN und 110 25 2750 2750 110.00 2,750.00 44 LADRILLO K.K. DE CONCRETO und 90 0.85 76.5 76.5 90.00 76.50 45 ENSAYO DE CAPACIDAD PORTANTE und 3 200 600 600 3.00 600.00 46 CEMENTO PORTLAND TIPO I (42.5KG) BOL 2607.69 21.9 57108.411 57105.53 113.58 2,487.37 1,750.12 38,325.65 169.90 3,720.54 42.44 929.37 531.65 11,642.59 47 CAJA DE CONCRETO SIMPLE CON FONDO und 106 15 1590 1590 106.00 1,590.00 48 CAJA DE CONCRETO SIMPLE SIN FONDO und 106 12 1272 1272 106.00 1,272.00 49 GIGANTOGRAFIA 4.80M X 2.40M und 1 380 380 380 1.00 380.00 50 LACA DESMOLDANTE gln 1.96 75 146.7 146.71 1.96 146.71 51 YESO EN BOLSAS DE 25 KG. BOL 88.74 8 709.8912 701.5 43.19 341.39 10.45 82.61 18.05 142.71 17.05 134.79

Upload: mikyroe

Post on 05-Jan-2016

232 views

Category:

Documents


0 download

DESCRIPTION

Cronograma

TRANSCRIPT

Page 1: Cronograma

G

CRONOGRAMA VALORIZADO DE ADQUISICION DE MATERIALESPROYECTO : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO

INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"

DISTRITO SANDIA PLAZO DE EJECUCION 180 dias Calendario

PROVINCIA SANDIA REALIZADO POR:

DEPARTAMENTO PUNO

Nº DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PRESUPUESTADO

DESEMBOLSO

1ER MES 2DO MES 3ER MES 4TO MES 5TO MES 6TO MES

CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO

1 OPERADOR DE EQUIPO LIVIANO hh 12.35 7.5 92.655 92.65 92.65 92.652 TOPOGRAFO hh 159.18 8.13 1294.143156 1294.45 94.73 770.30 5.02 40.79 58.96 479.48 0.48 3.87 1,294.453 OPERARIO hh 20081.18 5 100405.907 100418.54 243.14 1,215.83 9,127.87 45,645.07 8,537.33 42,692.01 443.61 2,218.34 1,716.49 8,583.53 12.75 63.76 100,418.544 OFICIAL hh 6422.76 6.88 44188.567472 44225.81 77.59 534.27 3,161.78 21,771.37 2,885.61 19,869.73 178.14 1,226.65 119.64 823.78 44,225.815 PEON hh 27864.1 3.75 104490.3795 104495.31 6,026.84 22,601.73 10,130.25 37,990.23 3,570.78 13,391.05 3,499.64 13,124.28 4,544.32 17,042.02 92.26 346.01 104,495.316 LUBRICANTE PARA TUBERIA gln 0.05 32 1.6 1.6 0.05 1.60 1.607 CLAVOS PARA MADERA C/C 2" kg 1.96 5 9.78 9.79 1.96 9.79 9.798 CLAVOS PARA MADERA C/C 3" kg 1.96 5 9.78 9.79 1.96 9.79 9.799 CLAVOS 4" kg 213.55 5 1067.742 1067.76 10.09 50.45 203.46 1,017.31 1,067.76

10 CLAVOS 3" kg 7.13 5 35.635 38.01 1.51 8.04 5.62 29.97 38.0111 CLAVOS DE 5" kg 2 5 10 10 2.00 10.00 10.0012 CLAVOS 2 1/2" kg 21.93 5 109.641 109.65 0.25 1.23 21.68 108.42 109.6513 ALAMBRE NEGRO N°16 kg 217.46 5 1087.314 1087.32 9.43 47.13 190.51 952.59 2.75 13.75 14.77 73.85 1,087.3214 ALAMBRE NEGRO N°8 kg 153.9 5 769.479 769.49 6.90 34.51 126.02 630.08 17.07 85.34 3.91 19.56 769.4915 CLAVOS kg 20.22 5 101.11 101.11 16.98 84.91 3.24 16.20 101.1116 PERNO HEXAG. C/ROSCA CORRIENTE 2.1/2"x3/8" cto 0.86 35.5 30.672 30.67 0.86 30.67 30.6717 CONO DE REBOSE PVC SAP 4"X2" und 1 15 15 15 1.00 15.00 15.0018 CONO DE REBOSE PVC SAP 4"X4" und 1 25 25 25 1.00 25.00 25.0019 PUERTA METALICA 0.90MX1.70M (INC. ACCESOR GLB 116 381 44196 44196 116.00 44,196.00 44,196.0020 VENTANA METALICA 0.40MX0.40M (03 UND) (INC GLB 216 55 11880 11880 216.00 11,880.00 11,880.0021 ROTURAS DE TESTIGOS DE CONCRETO und 40 15 600 600 40.00 600.00 600.0022 REJILLA DE FIERRO DE 1/4" und 106 3 318 318 106.00 318.00 318.0023 ACERO DE REFUERZO FY=4200 GRADO 60 kg 2367.16 3.8 8995.20192 9004.01 2,356.27 8,962.59 10.89 41.42 9,004.0124 FIERRO CORRUGADO 3/8" var 12.28 15 184.26 184.26 12.28 184.26 184.2625 FIERRO CORRUGADO 1/2" var 39.6 25 990 990 39.60 990.00 990.0026 ARENA FINA m3 47.82 35 1673.763 1684.61 3.57 125.85 19.69 693.67 24.56 865.09 1,684.6127 ARENA m3 162.27 35 5679.4535 5729.58 141.57 4,998.80 20.70 730.78 5,729.5828 PIEDRA MEDIANA DE 4" m3 7.78 40 311.304 311.3 7.78 311.30 311.3029 PIEDRA GRANDE m3 27.39 30 821.73 821.73 27.39 821.73 821.7330 ARENA GRUESA m3 0.18 35 6.3 6.3 0.18 6.30 6.3031 MATERIAL PARA CAMA DE APOYO m3 74.79 15 1121.904 1121.9 74.79 1,121.90 1,121.9032 PIEDRA MEDIANA 3" m3 15.89 25 397.25 397.25 15.89 397.25 397.2533 GRAVA DE 1" A 2" m3 3 55 165 165 3.00 165.00 165.0034 MATERIAL DE CAMA DE APOYO m3 122.84 15 1842.6 1842.6 122.84 1,842.60 1,842.6035 PIEDRA m3 0.3 25 7.5 7.5 0.30 7.50 7.5036 GRAVA m3 113.3 25 2832.5 2832.5 113.30 2,832.50 2,832.5037 TANQUE BAJO W.C. C/TAPA COLOR BLANCO pza 112 55.7 6238.4 6238.4 112.00 6,238.40 6,238.4038 INODORO und 112 88.3 9889.6 9889.6 112.00 9,889.60 9,889.6039 DUCHA C/ACCESORIOS. und 100 35 3500 3500 100.00 3,500.00 3,500.0040 REGISTRO DE BRONCE DE 2" und 100 12 1200 1200 100.00 1,200.00 1,200.0041 SUMIDERO CROMADO DE 2" und 196 9 1764 1764 196.00 1,764.00 1,764.0042 SUMIDERO BRONCE 1/2" und 100 4 400 400 100.00 400.00 400.0043 GRIFO DE ESFERA DE 1/2" TIPO JARDIN und 110 25 2750 2750 110.00 2,750.00 2,750.0044 LADRILLO K.K. DE CONCRETO und 90 0.85 76.5 76.5 90.00 76.50 76.5045 ENSAYO DE CAPACIDAD PORTANTE und 3 200 600 600 3.00 600.00 600.0046 CEMENTO PORTLAND TIPO I (42.5KG) BOL 2607.69 21.9 57108.411 57105.53 113.58 2,487.37 1,750.12 38,325.65 169.90 3,720.54 42.44 929.37 531.65 11,642.59 57,105.5347 CAJA DE CONCRETO SIMPLE CON FONDO und 106 15 1590 1590 106.00 1,590.00 1,590.0048 CAJA DE CONCRETO SIMPLE SIN FONDO und 106 12 1272 1272 106.00 1,272.00 1,272.0049 GIGANTOGRAFIA 4.80M X 2.40M und 1 380 380 380 1.00 380.00 380.0050 LACA DESMOLDANTE gln 1.96 75 146.7 146.71 1.96 146.71 146.7151 YESO EN BOLSAS DE 25 KG. BOL 88.74 8 709.8912 701.5 43.19 341.39 10.45 82.61 18.05 142.71 17.05 134.79 701.50

TOTAL PRESUPUESTO

Page 2: Cronograma

Nº DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PRESUPUESTADO

DESEMBOLSO

1ER MES 2DO MES 3ER MES 4TO MES 5TO MES 6TO MES

CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO

TOTAL PRESUPUESTO

52 CINTA SEÑALADORA AMARILLA pza 307.1 1.2 368.52 368.52 307.10 368.52 368.5253 CINTA TEFLON rll 525 1 525 525 16.80 16.80 295.80 295.80 176.00 176.00 36.40 36.40 525.0054 CIERRE AUTOMATICO ARTESANAL jgo 100 12 1200 1200 100.00 1,200.00 1,200.0055 GEOMEMBRANA HDPE 10 mm m2 777.15 11.5 8937.1905 8940.89 777.15 8,940.89 8,940.8956 GEOTEXTIL NO TEJIDO DE 200 gr/m2 m2 777.15 4 3108.588 3108.59 777.15 3,108.59 3,108.5957 SOLDADURA CELLOCORD 1/8" kg 5 14 70 70 5.00 70.00 70.0058 DISCO DE DESBASTE 4 1/4" pza 2.5 9 22.5 22.5 2.50 22.50 22.5059 SISTEMA DE CLORACION POR GOTEO GLB 1 4000 4000 4000 1.00 4,000.00 4,000.0060 VALVULA H. DUCTIL DE COMPUERTA ELASTOMERIund 2 649 1298 1298 2.00 1,298.00 1,298.0061 PEGAMENTO PARA PVC 1/4 GLN und 0.4 95 38 38 0.40 38.00 38.0062 PEGAMENTO PLASTICO PVC gln 33.67 95 3198.6785 3220.72 0.88 84.18 27.21 2,602.79 3.08 294.62 2.50 239.14 3,220.7263 ANILLO DE JEBE Ø 6" und 233.4 2.5 583.49 589.63 233.40 589.63 589.6364 ANILLO DE JEBE D=38.00mm P/AGUA und 16 4 64 64 16.00 64.00 64.0065 FILTRO DE GRAVA O CASCAJO m3 0.08 40 3.296 3.3 0.08 3.30 3.3066 SIKA 1 kg 10.44 23 240.028 240.03 10.44 240.03 240.0367 IMPRIMANTE gln 1.69 25 42.2825 42.28 1.69 42.28 42.2868 ACCES UNIR TUB HDPE PE80 PN6 (87 PSI) DE DIA und 12.22 75 916.2 920.27 12.22 920.27 920.2769 WINCHA DE 50 MTS und 37.23 40 1489.072 1491.15 37.20 1,490.08 0.03 1.07 1,491.1570 FLETE TERRESTRE GLB 1 47156.99 47156.99 47156.99 1.00 47,156.99 47,156.9971 PRESUPUESTO SOCIAL GLB 1 31472.75 31472.75 31472.75 1.00 31,472.75 31,472.7572 FLETE EN ZONA RURAL GLB 1 24454.47 24454.47 24454.47 1.00 24,454.47 24,454.4773 TRANSPORTE DE EQUIPOS Y MATERIALES A OBRGLB 1 8593.76 8593.76 8593.76 1.00 8,593.76 8,593.7674 GASOLINA gln 392.85 15 5892.7695 5884.42 245.85 3,682.47 111.62 1,671.94 35.38 530.01 5,884.4275 HORMIGON m3 212.98 35 7454.1425 7448.77 10.54 368.70 143.59 5,021.97 6.83 238.88 52.02 1,819.22 7,448.7776 LIJA pza 23.42 2 46.848 46.85 23.42 46.85 46.8577 HOJA DE SIERRA und 6.48 5 32.39 32.39 6.48 32.39 32.3978 LIJA PARA MADERA und 1.8 1.5 2.7 2.7 1.80 2.70 2.7079 CORDEL N° 42 (50 M) m 53 0.2 10.6 10.6 53.00 10.60 10.6080 AGUA m3 1149.81 1.3 1494.74767 1485.28 1.83 2.36 110.72 143.02 70.28 90.78 468.97 605.79 94.62 122.22 403.40 521.10 1,485.2881 HIPOCLORITO DE CALCIO AL 70% kg 3.21 20 64.174 64.17 3.21 64.17 64.1782 TRAPO INDUSTRIAL kg 0.1 0.7 0.07 0.07 0.10 0.07 0.0783 PRUEBAS DE CALIDAD DE CONCRETO ROTURA und 17 25 425 425 17.00 425.00 425.0084 LIMPIEZA DE ESCOMBROS EN FORMA GLOBAL GLB 1 6000 6000 6000 1.00 6,000.00 6,000.0085 TAPA METALICA SANITARIA 0.60*0.60M INC. AC und 2 125 250 250 2.00 250.00 250.0086 TAPA METALICA SANITARIA 0.40*0.40M INC. AC und 1 90 90 90 1.00 90.00 90.0087 MADERA TORNILLO p2 435.54 4.6 2003.46192 2000.09 189.54 870.39 246.00 1,129.70 2,000.0988 MADERA PARA ENCOFRADO p2 8753.92 4.6 40268.03016 40270.32 196.41 903.52 8,497.01 39,088.48 60.50 278.32 40,270.3289 REGLA DE MADERA p2 1.08 4.6 4.96616 4.87 1.08 4.87 4.8790 ESTACA p2 56.86 1.5 85.2882 90.96 56.68 90.67 0.18 0.29 90.9691 ROLLIZO DE EUCALIPTO DE 4" X 2.50 M pza 22 40 880 880 22.00 880.00 880.0092 ROLLIZO DE EUCALIPTO DE D=6" X 3.5M und 40.64 50 2031.75 2031.75 40.64 2,031.75 2,031.7593 ROLLIZO DE EUCALIPTO DE D=4" X 1.5M und 40.64 25 1015.875 1016.42 40.64 1,016.42 1,016.4294 TABLONES DE MADERA DE 8" X 1" X 1m p2 264.66 4.6 1217.436 1217.48 264.66 1,217.48 1,217.4895 MADERA CORRIENTE p2 89.47 3.8 339.99284 357.89 85.29 341.17 4.18 16.72 357.8996 TRIPLAY LUPUNA DE 4 X 8 X 4 MM pln 24 49 1176 1176 24.00 1,176.00 1,176.0097 TRIPLAY DE 18 MM. 2.44x1.22M pln 4.89 69 337.41 337.41 4.89 337.41 337.4198 MARCO Y TAPA F°F° P/REG. VALVULA und 2 22 44 44 2.00 44.00 44.0099 MARCO Y TAPA F°F° DE 125 kg. pza 18 495 8910 8910 18.00 8,910.00 8,910.00

100 MARCO Y TAPA FºFº (DESAGUE) und 106 25 2650 2650 106.00 2,650.00 2,650.00101 FIERRO FY=4200 KG/CM2 kg 1209.38 3.8 4595.63716 4600.16 168.11 639.44 1,041.27 3,960.72 4,600.16102 PLATINA FN 1/2"x1" m 62 7 434 434 62.00 434.00 434.00103 PETROLEO gln 547.14 15 8207.061 8207.06 547.14 8,207.06 8,207.06104 PINTURA LATEX gln 0.52 24 12.4896 12.49 0.52 12.49 12.49105 PINTURA ESMALTE SINTETICO gln 2.27 45 102.357 105.43 2.27 105.43 105.43106 PINTURA ANTICORROSIVA gln 13.13 45 590.976 590.98 13.13 590.98 590.98107 PINTURA ESMALTE gln 83.4 45 3753.216 3753.22 83.40 3,753.22 3,753.22108 PLANCHA ACERO LAC. 6mm 1.2x2.4m pln 0.65 428.5 278.525 278.53 0.65 278.53 278.53109 CALAMINA GALVANIZADA 1.83m x 0.83m x O.3mm pza 400 23 9200 9200 400.00 9,200.00 9,200.00

Page 3: Cronograma

Nº DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PRESUPUESTADO

DESEMBOLSO

1ER MES 2DO MES 3ER MES 4TO MES 5TO MES 6TO MES

CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO

TOTAL PRESUPUESTO

110 PLANCHA GALVANIZADA LISA 0.30X920X1830 MM pza 22.98 61.2 1406.4066 1406.32 22.98 1,406.32 1,406.32111 REDUCCION DE PVC SAP DE 1" x 1/2" und 110 1 110 110 110.00 110.00 110.00112 NIPLE DE Fo Go DE 1/2" x 3" und 440 1.5 660 660 440.00 660.00 660.00113 UNION UNIVERSAL F° GALVANIZADO 1/2" pza 110 4 440 440 110.00 440.00 440.00114 SUMIDERO F°G° 4" pza 1 21 21 21 1.00 21.00 21.00115 SUMIDERO DE BRONCE DE 2" und 110 5 550 550 110.00 550.00 550.00116 CANASTILLA PVC SAP 1" und 1 20 20 20 1.00 20.00 20.00117 CANASTILLA PVC SAP 4" und 1 60 60 60 1.00 60.00 60.00118 TUBERIA CACHIMBA D=6" C.S.N. und 106 12 1272 1272 106.00 1,272.00 1,272.00119 CODO FO GO 1/2"X90º und 110 1.8 198 198 110.00 198.00 198.00120 ABRAZADERA FO GO Ø 2" pza 1 8 8 8 1.00 8.00 8.00121 ABRAZADERA FO GO Ø 1" pza 2 6 12 12 2.00 12.00 12.00122 ABRAZADERA FO GO Ø 4" pza 1 14 14 14 1.00 14.00 14.00123 TUBERIA PVC SAP CLASE 7.5 2" m 3 5 15 15 3.00 15.00 15.00124 TUBERIA PVC SAP CLASE 10, 1/2" m 3757.05 2 7514.094 7514.09 1,744.05 3,488.09 2,013.00 4,026.00 7,514.09125 TUBERIA PVC SAP CLASE 7.5 1" m 5 2.8 14 14 5.00 14.00 14.00126 TUBERIA PVC SAP CLASE 10, 2" m 1979.95 28 55438.656 55438.66 1,979.95 55,438.66 55,438.66127 TUBERIA HDPE PE80 PN6 (87 PSI) POLITUBO Nac, m 838.83 18 15098.976 15098.98 838.83 15,098.98 15,098.98128 TUBERIA PVC SAP CLASE 7.5 1 1/2" m 5 21.5 107.5 107.5 5.00 107.50 107.50129 TUBERIA PVC SAP CLASE 7.5, 4" m 10 14 140 140 10.00 140.00 140.00130 UNION UNIVERSAL PVC SAP 1" und 2 6 12 12 2.00 12.00 12.00131 UNION UNIVERSAL PVC SAP 4" und 2 45 90 90 2.00 90.00 90.00132 CURVA DE 450 SP PVC SAP P/AGUA DE 1/2" und 120.25 0.8 96.196 96.2 65.25 52.20 55.00 44.00 96.20

CODO DE 45° PVC SAL DE 4" und 4 4.5 18 18 18.00 18.00TUBERIA PVC 6" SERIE 25 PARA DESAGUE m 2137.82 16.5 35274.03 35280.17 35,280.17 35,280.17TUB. PVC SAL P/DESAGUE DE 2" m 196 4.9 960.4 960.4 960.40 960.40TEE PVC SAP 1/2" und 210 1 210 210 100.00 110.00 210.00CODO DE 90 PVC SAL DE 2" und 196 3 588 588 588.00 588.00CODO DE 45° PVC SAL DE 2" und 192 2 384 384 384.00 384.00CODO DE 90° PVC SAL DE 4" und 104 4.5 468 468 432.00 36.00 468.00CODO DE 90° PVC SAL DE 2" und 320 3 960 960 864.00 96.00 960.00REDUCCION PVC SAP 3/4" A 1/2" pza 100 1.5 150 150 150.00 150.00REDUCCION PVC SAP 2" A 1 1/2" pza 100 10 1000 1000 1,000.00 1,000.00REDUCCION PVC SAP 1" X 3/4" und 100 2 200 200 200.00 200.00REDUCCION PVC SAP C 10, 1 1/2" A 1" und 100 8 800 800 800.00 800.00REDUCCION PVC SAP C 10, 3" A 2" und 100 16 1600 1600 1,600.00 1,600.00TEE SANITARIA SIMP C/REDUC PVC SAL 4"A2" und 100 8 800 800 800.00 800.00CODO 90° H. DUCTILDN 38 mm UF, PN-10 und 1 135 135 135 135.00 135.00YEE PVC SAL 4" und 104 6 624 624 576.00 48.00 624.00YEE PVC SAL 2" und 200 2 400 400 384.00 16.00 400.00CODO PVC SAP 1/2" X 90° und 520 0.5 260 260 150.00 110.00 260.00CODO PVC SAL 2" X 90° und 220 1.5 330 330 330.00 330.00CODO SIMPLE PRESION PVC SAP 2"X90º und 2 7 14 14 7.00 7.00 14.00CODO SIMPLE PRESION PVC SAP 1"X90º und 10 5 50 50 20.00 30.00 50.00CODO SIMPLE PRESION PVC SAP 1"X45º und 93 5 465 465 465.00 465.00CODO SIMPLE PRESION PVC SAP 2"X45º und 8 7 56 56 56.00 56.00CODO SIMPLE PRESION PVC SAP 4"X90º und 1 25 25 25 25.00 25.00UNION DE REPARACION PVC ISO D=38mm UF, C-7pza 4 35 140 140 140.00 140.00TUBERIA PVC SAL 2" m 1135.06 7 7945.42 7945.42 807.52 7,137.90 7,945.42TUBERIA PVC SAL 4" m 128.75 7 901.25 901.25 901.25 901.25TEE PVC SAL 4" X 2" pza 4 5 20 20 20.00 20.00TEE SIMPLE PRESION PVC SAP 2" und 5 8 40 40 40.00 40.00TEE SIMPLE PRESION PVC SAP 1" und 100 2.5 250 250 250.00 250.00TEE SIMPLE PRESION PVC SAP 1/2" und 5 0.8 4 4 4.00 4.00TEE SIMPLE PRESION PVC SAP 4" und 1 25 25 25 25.00 25.00TEE PVC SAL 4" und 4 5 20 20 20.00 20.00UNION PRESION ROSCA PVC SAP 2" und 1 25 25 25 25.00 25.00VALVULA ESFERICA PVC SAP 1" und 1 18 18 18 18.00 18.00UNION PRESION ROSCA PVC SAP 4" und 2 38 76 76 76.00 76.00VALVULA ESFERICA PVC SAP 4" und 1 97 97 97 97.00 97.00VALVULA ESFERICA PVC SAP 1/2" und 110 18 1980 1980 1,980.00 1,980.00LLAVE DE PASO PVC 1/2" und 100 6 600 600 600.00 600.00VALVULA PURGA DE SEDIMENTOS 2" jgo 1 190 190 190 190.00 190.00VALVULA PURGA DE SEDIMENTOS 1" jgo 5 150 750 750 750.00 750.00

Page 4: Cronograma

Nº DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PRESUPUESTADO

DESEMBOLSO

1ER MES 2DO MES 3ER MES 4TO MES 5TO MES 6TO MES

CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO

TOTAL PRESUPUESTO

VALVULA DE AIRE DE 1 1/2" jgo 1 250 250 250 250.00 250.00DISEÑO DE MEZCLAS und 1 300 300 300 300.00 300.00VALVULA COMPUERTA BRONCE 2" (INC. ACCESORGLB 46 160 7360 7360 7,360.00 7,360.00PISON DE MANO und 282.67 10 2826.702 2827.02 2,827.02 2,827.02MIRAS Y JALONES hm 120.3 3 360.9117 359.46 175.79 7.49 176.18 359.46CAMION VOLQUETE 12 M3. hm 30.97 150 4645.68 4645.68 4,645.68 4,645.68MOTOBOMBA 10 HP 4" hm 102 20 2040 2040 2,040.00 2,040.00CAMION CISTERNA 4X2 (AGUA) 1,500 GAL. hm 320.89 95 30484.36 30484.36 30,484.36 30,484.36EQUIPO DE SOLDADURA POR EXTRUCCION hm 39.45 11.5 453.66925 451.49 451.49 451.49PISTOLA DE TEMPERATURA hm 19.76 5 98.8085 96.22 96.22 96.22BOMBA MANUAL PARA PRUEBA DE TUBERIA hm 42.68 20 853.514 866.35 866.35 866.35FORMA METALICA H=1.20 M. PARA BUZON hm 216 9 1944 1944 1,944.00 1,944.00COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP hm 779.12 12.5 9738.9475 9747.03 3,702.05 6,044.98 9,747.03CARGADOR S/LLANTAS 125 HP 2.5 YD3. hm 5.65 170 960.381 960.38 960.38 960.38RETROEXCAVADOR S/LLANTAS 58 HP 1 YD3. hm 52.58 190 9990.58 9995.32 9,995.32 9,995.32VIBRADOR DE CONCRETO 4 HP 2.40" hm 38.1 9 342.9324 343 180.97 162.03 343.00MOTOSOLDADORA DE 250 AMP. hm 1.6 20 32 32 32.00 32.00MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 hm 16.56 21 347.76 347.76 347.76 347.76MEZCLADORA DE CONCRETO TROMPO 8 HP 9 P3hm 30.24 21 635.082 635.07 635.07 635.07PANEL METALICO DE 2.40 x 1.20 HE 281.74 8 2253.888 2253.89 2,253.89 2,253.89GRUPO ELECTROGENO 220 V hm 41.05 11.5 472.06925 469.89 469.89 469.89TEODOLITO hm 64.46 7 451.2249 455.49 416.68 35.44 3.37 455.49NIVEL hm 123.42 5 617.1195 618.1 295.31 25.12 295.29 2.38 618.10

133 HERRAMIENTAS MANUALES %MO 844.66 844.66 844.66 844.66 844.66 844.66 5,067.9354,897.95 367,296.99 124,971.89 166,279.74 139,076.10 43,423.65 895,946.32

TOTAL COSTO DIRECTO S/. 895,946.32Obra Meses Porcentaje % 895,946.32

Mensual Coeficiente Meses TotalS/. S/.

GASTOS GENERALES S/. 99,253.99 11.08%01.01.00 Remuneraciones y Beneficios 95,221.99

01.01.01 Residente de Obra 4,500.00 1.00 6.00 27,000.0001.01.02 Maestro de Obra 2,600.10 1.00 6.00 15,600.6001.01.03 Asistente Tecnico de Obra 1,800.00 1.00 6.00 10,800.0001.01.04 Almacenero 1,650.00 1.00 6.00 9,900.0001.01.05 Residente Social (Antes de la Ejecucion de 2,500.00 1.00 6.00 15,000.0001.01.06 Papeleria, Utiles de Escritorio. 700.00 1.00 1.00 700.0001.01.07 Combustible para movilizarse (02 und) 1,200.00 1.00 6.00 7,200.0001.01.08 Alquiler de computadora (02 und) 120.00 1.00 6.00 720.0001.01.09 Alquiler de habitacion (02 und) 240.00 1.00 6.00 1,440.0001.01.10 Fotocopias (02 und) 200.00 1.00 6.00 1,200.0001.01.11 Servicio por diagnostico comunitario (Exped 2,000.00 1.00 1.00 2,000.0001.01.12 Otros 3,661.39 1.00 1.00 3,661.39

Cantidad Precio S/. 4,032.0001.01.12 Cascos de Seguridad 72.00 14.00 1,008.0001.01.13 Chalecos de seguridad 72.00 12.00 864.0001.01.14 Guantes de cuero 72.00 10.00 720.0001.01.15 Guantes de jebe 72.00 12.00 864.0001.01.16 Lentes de seguridad 72.00 8.00 576.00

GASTOS DE SUPERVISION S/. 49,850.99 5.56%01.01.00 Remuneraciones y Beneficios 27,000.0001.01.01 Supervisor de Obra 4,500.00 1.00 6.00 27,000.0001.02.00 Movilidad de Personal y Servicios. 22,850.9901.02.01 Papeleria, Utiles de Escritorio. 4,837.44 1.00 1.00 4,837.4401.02.02 Combustible para movilizarse 695.00 2.00 6.00 8,340.0001.02.03 Alquiler de computadora 60.00 1.00 6.00 360.0001.02.04 Alquiler de habitacion 120.00 1.00 6.00 720.0001.02.05 Fotocopias 100.00 1.00 6.00 600.0001.02.06 Otros 7,993.55 1.00 1.00 7,993.55

TOTAL COSTO INDIRECTO S/. 149,104.98 16.64%

Page 5: Cronograma

Nº DESCRIPCION UNID CANTIDAD PRECIO PARCIAL PRESUPUESTADO

DESEMBOLSO

1ER MES 2DO MES 3ER MES 4TO MES 5TO MES 6TO MES

CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO CANTIDAD PRESUPUESTO

TOTAL PRESUPUESTO

TOTAL PRESUPUESTO S/. 1,045,051.30

Page 6: Cronograma

CRONOGRAMA DE VALORIZACION DE OBRAPROYECTO :

"MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

01 CAMARA DE CAPTACION (01 UND.) 2,366.85 2,366.8501.01 TRABAJOS PRELIMINARES 18.45 18.4501.01.01 LIMPIEZA DE TERRENO m2 9.00 0.62 5.58 5.5801.01.02 TRAZO Y REPLANTEO M2 9.00 1.43 12.87 12.8701.02 MOVIMIENTO DE TIERRAS 84.71 84.7101.02.01 EXCAVACION MANUAL EN ROCA SUELTA-SEMIDURA m3 4.67 12.36 57.72 57.7201.02.02 REFINE, NIVELACION Y COMPACTACION m2 3.80 0.31 1.18 1.1801.02.03 ACARREO DE MATERIAL EXCEDENTE HASTA DIST.=30.00 ML m3 5.84 4.42 25.81 25.8101.03 OBRAS DE CONCRETO SIMPLE 146.76 146.7601.03.01 SOLADO E=4" MEZCLA 1:12 CEMENTO HORMIGON m2 1.84 16.16 29.73 29.7301.03.02 CONCRETO CUBIERTA DE FILTRO F'C=175 KG/CM2. m3 0.24 263.20 63.17 63.1701.03.03 CONCRETO BAJO FILTRO F'C=140 KG/CM2. m3 0.23 234.16 53.86 53.8601.04 OBRAS DE CONCRETO ARMADO 1,115.08 1,115.0801.04.01 CONCRETO FC=210 KG/CM2, LOSA FONDO m3 0.31 301.08 93.33 93.3301.04.02 CONCRETO FC=210 KG/CM2, MUROS m3 0.98 301.08 295.06 295.0601.04.03 ENCOFRADO Y DESENCOFRADO DE MUROS (2 CARAS) m2 13.86 26.98 373.94 373.9401.04.04 CONCRETO LOSA TAPA F'C=210 KG/CM2 m3 0.12 281.51 33.78 33.7801.04.05 ENCOFRADO Y DESENCOFRADO, LOSA TECHO m2 1.50 30.20 45.30 45.3001.04.06 ACERO FY=4200 KG/CM2 kg 56.31 4.86 273.67 273.6701.05 TARRAJEOS 131.67 131.6701.05.01 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA 1:1,E=1.5CM (INTERIOR) m2 2.73 22.23 60.69 60.6901.05.02 TARRAJEO EN EXTERIORES (MORTERO 1:5) m2 4.96 14.31 70.98 70.9801.06 FILTRO 13.60 13.6001.06.01 FILTRO DE ARENA m3 0.24 41.20 9.89 9.8901.06.02 FILTRO DE GRAVA m3 0.08 46.35 3.71 3.7101.07 VALVULAS Y ACCESORIOS DE SALIDA 641.58 641.5801.07.01 SUMINISTRO ACCESORIOS DE SALIDA 1 1/2" GLB 1.00 573.00 573.00 573.0001.07.02 COLOCACION ACCESORIOS und 18.00 3.81 68.58 68.5801.08 TAPA DE INSPECCION 215.00 215.0001.08.01 TAPA METALICA SANITARIA 0.60*0.60M Y 0.40*0.40M CON BISAGRA Y CA und 1.00 215.00 215.00 215.0002 LINEA DE CONDUCCION (CAPTACION A RESERVORIO) (814.40 ML) 23,266.90 23,266.9002.01 TRABAJOS PRELIMINARES 912.13 912.1302.01.01 LIMPIEZA DE TERRENO m2 570.08 0.62 353.45 353.4502.01.02 TRAZO Y REPLANTEO DE ZANJAS m2 570.08 0.98 558.68 558.6802.02 MOVIMIENTO DE TIERRAS 5,439.68 5,439.6802.02.01 EXCAVACION EN ROCA SUELTA 0.40M X 0.60M DE PROFUNDIDAD m 716.00 2.81 2,011.96 2,011.9602.02.02 EXCAVACION MANUAL EN ROCA FIJA 0.40M X 0.60M DE PROFUNDIDAD m 98.40 8.35 821.64 821.64

Page 7: Cronograma

CRONOGRAMA DE VALORIZACION DE OBRAPROYECTO :

"MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

02.02.03 REFINE, NIVELACION Y FONDOS PARA TUBERIA AGUA m 814.40 0.52 423.49 423.4902.02.04 CAMA DE APOYO (CON MATERIAL SARANDEADO) m 814.40 0.62 504.93 504.9302.02.05 RELLENO COMPACTADO MANUAL DE ZANJAS H>0.7MTS. m 814.40 2.06 1,677.66 1,677.6602.03 SUMINISTRO E INSTALACION DE TUBERIAS 16,915.09 16,915.0902.03.01 TUBERIA HDPE PE80 PN6 (87 PSI) POLITUBO Nac, 2" m 814.40 20.77 16,915.09 16,915.0903 VALVULAS DE PURGA DE AIRE (01 UND) 426.29 426.2903.01 TRABAJOS PRELIMINARES 0.63 0.6303.01.01 LIMPIEZA DE TERRENO m2 0.36 0.62 0.22 0.2203.01.02 TRAZO Y REPLANTEO m2 0.36 1.15 0.41 0.4103.02 MOVIMIENTO DE TIERRA 7.14 7.1403.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 0.36 12.36 4.45 4.4503.02.02 REFINE, NIVELACION Y COMPACTACION m2 0.36 1.03 0.37 0.3703.02.03 ACARREO DE MATERIAL EXCEDENTE HASTA DIST.=30.00 ML m3 0.45 5.15 2.32 2.3203.03 OBRAS DE CONCRETO ARMADO 141.42 141.4203.03.01 CONCRETO FC=210 KG/CM2 m3 0.26 301.08 78.28 78.2803.03.02 ENCOFRADO Y DESENCOFRADO m2 1.75 26.75 46.81 46.8103.03.03 ACERO FY = 4200 KG/CM2 kg 3.36 4.86 16.33 16.3303.04 TARRAJEOS 20.09 20.0903.04.01 TARRAJEO EN EXTERIORES, MORTERO 1:5 m2 2.04 9.85 20.09 20.0903.05 VALVULAS Y ACCESORIOS 257.01 257.0103.05.01 ACCESORIOS DE 2"-VALVULAS DE AIRE GLB 1.00 250.00 250.00 250.0003.05.02 COLOCACION DE ACCESORIOS und 1.00 7.01 7.01 7.0104 VALVULAS DE PURGA DE SEDIMENTOS (06 UND) 1,936.45 1,936.4504.01 TRABAJOS PRELIMINARES 3.82 3.8204.01.01 LIMPIEZA DE TERRENO M2 2.16 0.62 1.34 1.3404.01.02 TRAZO Y REPLANTEO M2 2.16 1.15 2.48 2.4804.02 MOVIMIENTO DE TIERRAS 42.83 42.8304.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 2.16 12.36 26.70 26.7004.02.02 REFINE, NIVELACION Y COMPACTACION m2 2.16 1.03 2.22 2.2204.02.03 ACARREO DE MATERIAL EXCEDENTE HASTA DIST.=30.00 ML m3 2.70 5.15 13.91 13.9104.03 OBRAS DE CONCRETO ARMADO 787.18 787.1804.03.01 CONCRETO FC=210 KG/CM2 m3 1.53 301.08 460.65 460.6504.03.02 ENCOFRADO Y DESENCOFRADO m2 10.74 21.28 228.55 228.5504.03.03 ACERO FY = 4200 KG/CM2 kg 20.16 4.86 97.98 97.9804.04 TARRAJEOS 120.56 120.5604.04.01 TARRAJEO EN EXTERIORES, MORTERO 1:5 m2 12.24 9.85 120.56 120.5604.05 VALVULAS Y ACCESORIOS 982.06 982.0604.05.01 ACCESORIOS DE 1"-VALVULAS PURGA DE SEDIMENTOS GLB 5.00 150.00 750.00 750.00

Page 8: Cronograma

CRONOGRAMA DE VALORIZACION DE OBRAPROYECTO :

"MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

04.05.02 ACCESORIOS DE 2"-VALVULAS PURGA DE SEDIMENTOS GLB 1.00 190.00 190.00 190.0004.05.03 COLOCACION DE ACCESORIOS und 6.00 7.01 42.06 42.0605 SISTEMA DE CLORACION (01 UND.) 4,000.00 4,000.0005.01 SISTEMA DE CLORACION POR GOTEO GLB 1.00 4,000.00 4,000.00 4,000.0006 RESERVORIO-1.58M3 (15 UND.) 1,247.67 1,247.6706.01 TRABAJOS PRELIMINARES 13.81 13.8106.01.01 LIMPIEZA DE TERRENO m2 5.29 0.62 3.28 3.2806.01.02 TRAZO Y REPLANTEO m2 5.29 1.99 10.53 10.5306.02 TARRAJEOS 592.18 592.1806.02.01 TARRAJEO CON IMPERMEABILIZANTE, MEZCLA 1:1,E=1.5CM M2 19.36 19.52 377.91 377.9106.02.02 TARRAJEO EN EXTERIORES (MORTERO 1:5) M2 8.97 16.15 144.87 144.8706.02.03 PENDIENTE FONDO C/IMPERMEABILIZANTE MORTERO 1:5 m2 4.00 17.35 69.40 69.4006.03 PINTURA 81.31 81.3106.03.01 PINTURA LATEX EN EXTERIORES m2 13.01 6.25 81.31 81.3106.04 OTRAS PARTIDAS 560.37 560.3706.04.01 TAPA METALICA SANITARIA 0.60*0.60M CON CANDADO UND 1.00 135.00 135.00 135.0006.04.02 SUMINISTRO Y ACCESORIOS GLB 1.00 166.00 166.00 166.0006.04.03 COLOCACION DE ACCESORIOS und 37.00 7.01 259.37 259.3707 LINEA DE ADUCCION Y RED DE DISTRIBUCION (3.323,38 ML) 105,416.53 16,211.71 89,204.8307.01 TRABAJOS PRELIMINARES 2,021.48 2,021.4807.01.01 TRAZO Y REPLANTEO DE ZANJAS / ML M 3,208.70 0.63 2,021.48 2,021.4807.02 MOVIMIENTO DE TIERRAS 27,827.43 14,190.23 13,637.2107.02.01 EXCAVACION EN ROCA SUELTA ZANJAS /ML 0.50*0.70M m 3,186.70 4.76 15,168.69 8,811.23 6,357.4707.02.02 EXCAVACION EN ROCA FIJA ZANJA/ML 0.50*0.7OM m 22.10 12.36 273.16 273.1607.02.03 REFINE, NIVELACION Y FONDOS PARA TUBERIA AGUA M 3,208.70 0.56 1,796.87 1,796.8707.02.04 CAMA DE APOYO PARA TUBERIA (CON MATERIAL PROPIO ZARANDEADO)M 3,208.70 1.24 3,978.79 1,243.37 2,735.4207.02.05 RELLENO COMPACTADO MANUAL DE ZANJAS H>0.7MTS. m 3,208.70 2.06 6,609.92 2,065.60 4,544.3207.03 SUMINISTRO E INSTALACION DE TUBERIAS 64,214.99 64,214.9907.03.01 TUBERIA PVC SAP CLASE 10, 1/2" m 1,304.90 2.77 3,614.57 3,614.5707.03.02 TUBERIA PVC SAP CLASE 10, 3" m 1,903.80 29.93 56,980.73 56,980.7307.03.03 PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIAS PVC ML m 3,208.70 0.65 2,085.66 2,085.6607.03.04 CONCRETO F'C=100 KG/CM2 DADOS DE ANCLAJE DE ACCESORIOS m3 9.98 153.71 1,534.03 1,534.0307.04 ACCESORIOS 11,352.63 11,352.6307.04.01 SUMINISTRO Y ACCESORIOS (RED DE ADUCCION Y DISTRIBUCION ) GLB 1.00 4,602.00 4,602.00 4,602.0007.04.02 COLOCACION DE ACCESORIOS und 963.00 7.01 6,750.63 6,750.6308 VALVULAS DE CONTROL (23 UND) 11,438.63 3,855.88 7,582.7508.01 TRABAJOS PRELIMINARES 14.65 14.6508.01.01 LIMPIEZA DE TERRENO m2 8.28 0.62 5.13 5.13

Page 9: Cronograma

CRONOGRAMA DE VALORIZACION DE OBRAPROYECTO :

"MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

08.01.02 TRAZO Y REPLANTEO m2 8.28 1.15 9.52 9.5208.02 MOVIMIENTO DE TIERRAS 164.17 164.1708.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 8.28 12.36 102.34 102.3408.02.02 REFINE, NIVELACION Y COMPACTACION m2 8.28 1.03 8.53 8.5308.02.03 ACARREO DE MATERIAL EXCEDENTE HASTA DIST.=30.00 ML m3 10.35 5.15 53.30 53.3008.03 OBRAS DE CONCRETO ARMADO 3,256.70 3,256.7008.03.01 CONCRETO FC=210 KG/CM2 m3 5.88 301.08 1,770.35 1,770.3508.03.02 ACERO FY = 4200 KG/CM2 kg 77.28 4.86 375.58 375.5808.03.03 ENCOFRADO Y DESENCOFRADO m2 41.17 26.98 1,110.77 1,110.7708.04 TARRAJEOS 481.88 420.36 61.5208.04.01 TARRAJEO EN EXTERIORES (MORTERO 1:5) m2 46.29 10.41 481.88 420.36 61.5208.05 VALVULAS Y ACCESORIOS 7,521.23 7,521.2308.05.01 ACCESORIOS DE 2" - VALVULAS DE CONTROL GLB 23.00 320.00 7,360.00 7,360.0008.05.02 COLOCACION DE ACCESORIOS und 23.00 7.01 161.23 161.2309 INSTALACIONES DOMICILIARIAS (100 UND.) 60,501.21 27,775.30 32,283.33 442.5809.01 TRABAJOS PRELIMINARES 545.49 545.4909.01.01 LIMPIEZA DE TERRENO m2 209.00 0.62 129.58 129.5809.01.02 TRAZO Y REPLANTEO m2 209.00 1.99 415.91 415.9109.02 MOVIMIENTO DE TIERRAS 2,348.66 2,348.6609.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 121.50 12.36 1,501.74 1,501.7409.02.02 REFINE, NIVELACION Y COMPACTACION m2 209.00 0.31 64.79 64.7909.02.03 ACARREO DE MATERIAL EXCEDENTE HASTA D PROM=30m m3 151.87 5.15 782.13 782.1309.03 OBRAS DE CONCRETO SIMPLE 6,667.73 6,667.7309.03.01 CONCRETO CICLOPEO FC=140 KG/CM2 + 70 % PM. m3 22.70 111.22 2,524.69 2,524.6909.03.02 ENCOFRADO Y DESENCOFRADO m2 154.88 26.75 4,143.04 4,143.0409.04 OBRAS DE CONCRETO ARMADO 20,444.31 18,213.42 2,230.8909.04.01 CONCRETO F'C=175 KG/CM2 m3 17.59 318.93 5,609.98 5,609.9809.04.02 ACERO FY=4200 KG/CM2 kg 973.15 4.86 4,729.51 4,729.5109.04.03 ENCOFRADO Y DESENCOFRADO m2 374.53 26.98 10,104.82 7,873.93 2,230.8909.05 TARRAJEOS 3,689.12 3,689.1209.05.01 TARRAJEO EN EXTERIORES, MORTERO 1:5 m2 374.53 9.85 3,689.12 3,689.1209.06 TUBERIAS Y ACCESORIOS 23,406.90 23,406.9009.06.01 TUBERIA PVC SAL 2", REVOSE Y LIMPIEZA m 990.00 8.09 8,009.10 8,009.1009.06.02 TUBERIA PVC SAP CLASE 10, 1/2" m 1,100.00 2.77 3,047.00 3,047.0009.06.03 ACCESORIOS DE ENTRADA, 1/2" GLB 110.00 81.80 8,998.00 8,998.0009.06.04 COLOCACION ACCESORIOS und 880.00 3.81 3,352.80 3,352.8009.07 OTROS 3,399.00 2,956.42 442.5809.07.01 POZO PERCOLADOR m3 110.00 30.90 3,399.00 2,956.42 442.58

Page 10: Cronograma

CRONOGRAMA DE VALORIZACION DE OBRAPROYECTO :

"MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

10 FLETES 71,611.46 71,611.4610.01 FLETES 71,611.46 71,611.4610.01.01 FLETE TERRESTRE GLB 1.00 47,156.99 47,156.99 47,156.9910.01.02 FLETE TERRESTRE EN ZONA RURAL GLB 1.00 24,454.47 24,454.47 24,454.4711 PRUEBAS DE LABORATORIO 1,500.00 1,500.0011.01 PRUEBA DE LABORATORIO Y ESTUDIOS DE SUELOS 1,500.00 1,500.0011.01.01 DISEÑO DE MEZCLAS und 1.00 300.00 300.00 300.0011.01.02 ROTURA DE TESTIGOS DE CONCRETO und 40.00 15.00 600.00 600.0011.01.03 ENSAYO DE CAPACIDAD PORTANTE und 3.00 200.00 600.00 600.0012 OTROS 890.42 890.4212.01 CARTEL DE OBRA Y PLACA RECORDATORIA 890.42 890.4212.01.01 CARTEL DE OBRA CON GIGANTOGRAFIA und 1.00 890.42 890.42 890.4213 UNIDADES BASICAS DE SANEAMIENTO BAÑO (100 UND.) 339,276.01 1,521.01 243,991.32 92,687.02 1,076.6813.01 TRABAJOS PRELIMINARES 714.12 714.1213.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 460.72 1.55 714.12 714.1213.02 MOVIMIENTO DE TIERRAS 955.35 806.89 148.4613.02.01 EXCAVACION MANUAL PARA BAÑOS m3 60.00 11.03 661.80 661.8013.02.02 RELLENO COMPACTADO MANUAL DE ZANJAS H<0.7MTS. m 30.00 2.06 61.80 61.8013.02.03 ACARREO DE MATERIAL EXCEDENTE A MENOS DE 30MTS m3 37.50 6.18 231.75 83.29 148.4613.03 CONSTRUCCION DE LA CASETA 174,016.73 162,522.39 11,494.3513.03.01 CIMIENTO CORRIDO CON Cº 1:10 + 30% PG m3 55.90 137.60 7,691.84 7,691.8413.03.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 232.96 26.75 6,231.68 6,231.6813.03.03 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 18.53 185.73 3,441.58 3,441.5813.03.04 FABRICACION DE BLOQUETAS-MURO und 10,024.34 2.95 29,571.80 25,067.43 4,504.3713.03.05 ASENTADO MURO DE BLOQUETAS m2 1,043.52 26.63 27,788.94 21,496.78 6,292.1713.03.06 TARRAJEO EXTERIOR e=1.5CM C/MORTERO 1:5 m2 1,158.32 8.40 9,729.89 9,729.8913.03.07 PUERTA METALICA 0.90MX1.90M Y VENTANA METALICA 0.40MX0.40M (I GLB 116.00 474.50 55,042.00 54,344.19 697.8113.03.08 VENTANA METALICA 0.40Mx0.40M,CON VIDRIO SEMIDOBLE m2 100.00 55.00 5,500.00 5,500.0013.03.09 COBERTURA DE MADERA Y CALAM. GAL. PARA BAÑOS und 100.00 290.19 29,019.00 29,019.0013.04 CONCRETO SIMPLE 2,055.93 2,055.9313.04.01 CONCRETO F'C=140 KG/CM2., MUROS SIN MEZCLADORA m3 6.27 327.90 2,055.93 2,055.9313.05 CONCRETO ARMADO 27,350.18 27,350.1813.05.01 CONCRETO F'C=175 KG/CM2 SIN MEZCLADORA m3 24.34 248.79 6,055.55 6,055.5513.05.02 ACERO FY=4200 KG/CM2 kg 2,202.12 4.86 10,702.30 10,702.3013.05.03 ENCOFRADO Y DESENCOFRADO m2 497.76 21.28 10,592.33 10,592.3313.06 INSTALACION SANITARIA 113,366.40 49,274.36 64,092.0513.06.01 TUBERIA DESAGUE PVC SAL 2" m 112.00 7.92 887.04 887.0413.06.02 TUBERIA DESAGUE PVC SAL 4" m 125.00 7.92 990.00 990.00

Page 11: Cronograma

CRONOGRAMA DE VALORIZACION DE OBRAPROYECTO :

"MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

13.06.03 DUCHA CROMADA (INC. LLAVE, ACCESORIOS) GLB 100.00 865.74 86,574.00 40,795.44 45,778.5613.06.04 REGISTRO DE BRONCE 2" und 100.00 31.49 3,149.00 2,521.29 627.7213.06.05 SUMIDERO DE CROMO DE 2" pza 196.00 25.91 5,078.36 4,080.59 997.7713.06.06 INODORO TANQUE BAJO BLANCO pza 112.00 149.00 16,688.00 16,688.0013.07 PINTURA 7,309.44 7,309.4413.07.01 PINTURA EN PUERTA Y VENTANAMETALICA DE BAÑOS (ESMALTE Y ANTICm2 656.64 4.55 2,987.71 2,987.7113.07.02 PINTURA ESMALTE m2 1,171.20 3.69 4,321.73 4,321.7313.08 CIERRE AUTOMATICO 1,358.00 1,358.0013.08.01 CIERRE AUTOMATICO ARTESANAL und 100.00 13.58 1,358.00 1,358.0013.09 TARRAJEOS 8,433.18 8,433.1813.09.01 TARRAJEO EXTERIOR e=1.5CM C/MORTERO 1:5 m2 1,003.95 8.40 8,433.18 8,433.1813.10 ACCESORIOS 3,716.68 2,640.00 1,076.6813.10.01 ACCESORIOS PARA UBS GLB 96.00 27.50 2,640.00 2,640.0013.10.02 ACCESORIOS PARA MODULO UBS GLB 4.00 63.50 254.00 254.0013.10.03 COLOCACION DE ACCESORIOS PARA UBS und 96.00 7.54 723.84 723.8413.10.04 COLOCACION DE ACCESORIOS PARA MODULO UBS und 4.00 24.71 98.84 98.8414 EXPEDIENTE SOCIAL 31,472.75 31,472.7514.01 PRESUPUESTO SOCIAL 31,472.75 31,472.7514.01.01 PRESUPUESTO SOCIAL GLB 1.00 31,472.75 31,472.75 31,472.7515 INSTALACION DE TUBERIA 152,823.15 47,112.48 63,123.07 42,587.6015.01 OBRAS PROVISIONALES 8,321.45 8,321.4515.01.01 CASETA DE GUARDIANIA Y ALMACEN m2 48.00 92.16 4,423.68 4,423.6815.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M m2 8.64 100.17 865.47 865.4715.01.03 PUENTE DE MADERA P/PASE PEATONAL und 11.00 205.31 2,258.41 2,258.4115.01.04 CINTA PLASTICA P/SEÑAL DE PELIGRO-LIMITE DE OBRA m 1,228.40 0.63 773.89 773.8915.02 OBRAS PRELIMINARES 3,672.91 3,672.9115.02.01 TRAZO Y REPLANTEOS INICIALES DE OBRA m 1,228.40 0.71 872.16 872.1615.02.02 TRAZO Y REPLANTEOS DURANTE LA EJECUCION DE OBRA m 1,228.40 2.28 2,800.75 2,800.7515.03 MOVIMIENTO DE TIERRA 46,452.19 35,118.12 11,334.0715.03.01 EXCAVACION DE ZANJA HASTA H=2.00mEN TERRENO NORMAL m3 1,184.28 15.77 18,676.10 18,676.1015.03.02 ENTIBADO DE ZANJAS CON PANELES METALICOS m2 108.36 56.53 6,125.59 6,125.5915.03.03 REFINE Y NIVELACION DE ZANJA EN T.N. TUB. 6" m 1,228.40 0.31 380.80 380.8015.03.04 PREPARACION DE CAMA DE APOYO EN T.N. TUB 6" m 1,228.40 1.81 2,223.40 2,190.45 32.9515.03.05 RELLENO Y COMPACTACION DE ZANJAS m3 1,098.29 12.19 13,388.16 7,745.18 5,642.9815.03.06 ELIMINACION DE MATERIAL EXCEDENTE m3 111.78 34.18 3,820.64 3,820.6415.03.07 DOBLE TRANSPORTE DE MATERIAL EXCAVADO m3 297.33 6.18 1,837.50 1,837.5015.04 SUMINISTRO E INSTALACION DE TUBERIAS 25,624.42 25,624.4215.04.01 SUMINISTRO Y TENDIDO DE TUBERIAS DE PVC D=6" m 1,228.40 19.53 23,990.65 23,990.65

Page 12: Cronograma

CRONOGRAMA DE VALORIZACION DE OBRAPROYECTO :

"MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

15.04.02 DOBLE PRUEBA HIDRAULICA TUB. 6" Y 8" m 1,228.40 1.33 1,633.77 1,633.7715.05 BUZONES RED COLECTORA 26,164.58 26,164.5815.05.01 BUZON DE CONCRETO H=1.50m D=1.20m T.N. und 18.00 1,263.15 22,736.70 22,736.7015.05.02 DADOS P/EMPALME DE TUBERIA A BUZONES und 64.00 46.92 3,002.88 3,002.8815.05.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 17.00 25.00 425.00 425.0015.06 DEPRESION DE NAPA FREATICA 2,661.18 2,661.1815.06.01 DEPRESION DE NAPA FREATICA h 51.00 52.18 2,661.18 2,661.1815.07 FLETE 8,593.76 8,593.7615.07.01 TRANSPORTE DE EQUIPOS Y MATERIALES A OBRA GLB 1.00 8,593.76 8,593.76 8,593.7615.08 MITIGACION DE IMPACTO AMBIENTALES 31,270.86 31,270.8615.08.01 HUMEDECIMIENTO DE MATERIAL EXCAVADO DE ZANJAS m3 1,184.00 3.29 3,895.36 3,895.3615.08.02 SUMINISTRO DE AGUA POTABLE EN TANQUE CISTERNA GLB 1.00 27,375.50 27,375.50 27,375.5015.09 CAMARA DE REJAS 61.80 61.8015.09.01 LIMPIEZA DE CAMARA DE REJAS und 1.00 61.80 61.80 61.8016 CONEXIONES DOMICILIARIAS 58,464.92 12,953.37 45,511.5516.01 TRABAJOS PRELIMINARES 270.09 270.0916.01.01 TRAZO Y REPLANTEO m 1,038.80 0.26 270.09 270.0916.02 MOVIMIENTO DE TIERRA 23,829.63 12,683.28 11,146.3516.02.01 EXCAVACION DE ZANJAS A PULSO MENOR DE 1M m3 1,090.74 8.83 9,631.23 7,395.41 2,235.8216.02.02 REFINE Y NIVELACION DE ZANJA EN T.N. m 1,038.80 0.31 322.03 84.17 237.8616.02.03 PREPARACION DE CAMA DE APOYO EN T.N. m 1,038.80 1.29 1,340.05 1,340.0516.02.04 RELLENO Y COMPACTACION DE ZANJAS m3 1,028.41 12.19 12,536.32 5,203.70 7,332.6216.03 SUMINISTRO E INSTALACION DE CONEXIONES DOMICILIARIAS 34,365.20 34,365.2016.03.01 CONEXION DOMICILIARIAS und 106.00 324.20 34,365.20 34,365.2017 PLACA RECORDATORIA 29,306.87 29,306.8717.01 OBRAS PROVISIONALES 6,000.00 6,000.0017.01.01 LIMPIEZA DE FONDO DE LA LAGUNA DE OXIDACION GLB 1.00 6,000.00 6,000.00 6,000.0017.02 OBRAS PRELIMINARES 24.40 24.4017.02.01 LIMPIEZA DE TERRENO m2 8.94 0.62 5.54 5.5417.02.02 TRAZO Y REPLANTEO m2 8.94 2.11 18.86 18.8617.03 MOVIMIENTO DE TIERRA 110.14 110.1417.03.01 EXCAVACION MANUAL m3 2.25 8.83 19.87 19.8717.03.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 0.51 30.90 15.76 15.7617.03.03 ELIMINACION DE MATERIAL EXCEDENTE m3 2.18 34.18 74.51 74.5117.04 OBRAS DE CONCRETO SIMPLE 1,596.18 1,596.1817.04.01 CAMARA DE REJAS 134.46 134.4617.04.01.01 ENCOFRADO Y DESENCOFRADO TIPO CARAVISTA m2 1.47 58.08 85.38 85.3817.04.01.02 CONCRETO F'C = 175 Kg/Cm2 m3 0.16 306.75 49.08 49.08

Page 13: Cronograma

CRONOGRAMA DE VALORIZACION DE OBRAPROYECTO :

"MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE SANEAMIENTO BASICO INTEGRAL EN EL SECTOR ALTO QUENEQUE DIST. SANDIA , PROVINCIA DE SANDIA - PUNO"ITEM DESCRIPCION UND METRADO PRECIO PARCIAL MES 1 MES 2 MES 3 MES 4 MES 5 MES 6

17.04.02 DESARENADOR, MEDIDOR PARSHALL, POZOS PERCOLADORES 1,292.08 1,292.0817.04.02.01 ENCOFRADO Y DESENCOFRADO TIPO CARAVISTA m2 16.12 58.08 936.25 936.2517.04.02.02 CONCRETO F'C = 175 Kg/Cm2 m3 1.16 306.75 355.83 355.8317.04.03 CANAL DE CONEXION ENTRE DESARENADOR Y LAGUNA DE OXIDACION 169.64 169.6417.04.03.01 ENCOFRADO Y DESENCOFRADO TIPO CARAVISTA m2 1.97 58.08 114.42 114.4217.04.03.02 CONCRETO F'C = 175 Kg/Cm2 m3 0.18 306.75 55.22 55.2217.05 OBRAS COMPLEMENTARIAS EN UNIDADES DE INGRESO 3,139.77 3,139.7717.05.01 REJILLA METALICA EN CAMARA DE REJAS und 1.00 328.00 328.00 328.0017.05.02 COMPUERTA METALICA TIPO TARJETA, PLANCHA LAC 1/4" 0.15x0.15m und 2.00 121.10 242.20 242.2017.05.03 COMPUERTA METALICA TIPO TARJETA, PLANCHA LAC 1/4" 0.26x0.15m und 2.00 121.10 242.20 242.2017.05.04 GLB 1.00 2,031.51 2,031.51 2,031.5117.05.05 GLB 1.00 161.83 161.83 161.8317.05.06 MEDIOS FILTRANTES EN POZO PERCOLADO GLB 1.00 134.03 134.03 134.0317.06 CULMINACION Y MEJORAMIENTO DEL SISTEMA DE IMPERMEABILIZACION CON GEOMENBRANAS HDPE 18,436.38 18,436.3817.06.01 m3 26.37 48.29 1,273.41 1,273.4117.06.02 m3 26.37 1.37 36.13 36.1317.06.03 m2 740.14 23.14 17,126.84 17,126.84

COSTO DIRECTO 895,946.11 54,832.76 368,554.20 124,970.35 165,983.06 139,018.17 42,587.60GASTOS GENERALES 99,253.99 6,074.44 40,828.88 13,844.37 18,387.80 15,400.60 4,717.91GASTOS DE SUPERVISION 49,850.99 3,050.93 20,506.58 6,953.43 9,235.40 7,735.06 2,369.60SUB TOTAL 1,045,051.09 63,958.13 429,889.66 145,768.14 193,606.26 162,153.83 49,675.11COSTO TOTAL DE LA OBRA 1,045,051.09 63,958.13 429,889.66 145,768.14 193,606.26 162,153.83 49,675.11PORCENTAJE DE AVANCE PARCIAL 1 6.12% 41.14% 13.95% 18.53% 15.52% 4.75%

PORCENTAJE DE AVANCE ACUMULADO PARCIAL 1 6.12% 47.26% 61.20% 79.73% 95.25% 100.00%

TUBERIA DE CONEXION ENTRE DESARENADOR, LECHOS DE SECADO Y POZO 1.00 2,031.51DE PERCOLACION MEDIOS FILTRANTES EN LECHOS DE SECADODE PERCOLACION

EXCAVACION MANUAL DE ZANJAS EN TERRENO COMPACTADO, PARA ANCLAJE 26.37 1,273.41DE GEOMENBRANA EN CORONA, SECCION 0.50x0.50m RELLENO COMPACTADO CON M/PROPIO, EN ZANJA 0.50x0.50m PARA ANCLAJE 26.37 36.13DE GEOMENBRANA EN CORONADE GEOMENBRANA EN CORONA, SECCION 0.50x0.50m COLOCACION DE SISTEMA DE IMPERMEABILIZACION CON GEOMEMBRANA 740.14 17,104.64HDPE