PROGRESIVA DISTANCIA A.C. A.R V.C. V.R. V.C. V.C. V.C.
(m) m2 m2 m3 m3 M.S R.S. R.F
(1)+(2)+(3) (1) (2) (3)
+.00 0.89 0.00 0.00 0.00
+20.00 20.00 0.72 0.00 16.10 0.00
+40.00 20.00 1.22 0.00 19.40 0.00
+60.00 20.00 1.33 0.00 25.50 0.00
+80.00 20.00 1.43 0.00 27.60 0.00
+100.00 20.00 1.39 0.00 28.20 0.00
+120.00 20.00 0.86 0.00 22.50 0.00
+160.00 40.00 1.51 0.00 47.40 0.00
+170.00 10.00 0.59 0.00 10.50 0.00
+180.00 10.00 0.70 0.00 6.45 0.00
+200.00 20.00 0.63 0.00 13.30 0.00
+210.00 10.00 0.66 0.00 6.45 0.00
+220.00 10.00 0.59 0.00 6.25 0.00
+240.00 20.00 0.78 0.00 13.70 0.00
+250.00 10.00 0.71 0.00 7.45 0.00
+280.00 30.00 0.68 0.00 20.85 0.00
+290.00 10.00 0.72 0.00 7.00 0.00
+300.00 10.00 0.80 0.00 7.60 0.00
+320.00 20.00 0.86 0.00 16.60 0.00
+340.00 20.00 0.93 0.00 17.90 0.00
+360.00 20.00 0.59 0.00 15.20 0.00
+370.00 10.00 0.52 0.00 5.55 0.00
+400.00 30.00 0.57 0.00 16.35 0.00
+420.00 20.00 0.79 0.00 13.60 0.00
+430.00 10.00 0.72 0.00 7.55 0.00
+440.00 10.00 1.12 0.00 9.20 0.00
+480.00 40.00 0.79 0.00 38.20 0.00
+500.00 20.00 0.65 0.00 14.40 0.00
+520.00 20.00 1.02 0.00 16.70 0.00
+560.00 40.00 1.07 0.00 41.80 0.00
+580.00 20.00 0.65 0.00 17.20 0.00
+600.00 20.00 0.77 0.00 14.20 0.00
+620.00 20.00 0.64 0.00 14.10 0.00
+640.00 20.00 1.22 0.00 18.60 0.00
+660.00 20.00 0.84 0.00 20.60 0.00
+680.00 20.00 0.63 0.00 14.70 0.00
+700.00 20.00 0.60 0.00 12.30 0.00
+740.00 40.00 0.76 0.00 27.20 0.00
+760.00 20.00 0.91 0.00 16.70 0.00
+770.00 10.00 1.05 0.00 9.80 0.00
+780.00 10.00 1.70 0.00 13.75 0.00
+790.00 10.00 0.98 0.00 13.40 0.00
+800.00 10.00 0.73 0.00 8.55 0.00
+820.00 20.00 0.72 0.00 14.50 0.00
+880.00 60.00 0.84 0.00 46.80 0.00
+900.00 20.00 0.60 0.00 14.40 0.00
+920.00 20.00 0.77 0.00 13.70 0.00
+940.00 20.00 3.70 0.00 44.70 0.00
+960.00 20.00 1.05 0.00 47.50 0.00
+980.00 20.00 1.45 0.00 25.00 0.00
+990.00 10.00 23.03 0.00 122.40 0.00
1029.40 0.00 0.00 0.00 0.00
MEJORAMIENTO DEL SERVICIO DE AGUA PARA RIEGO HUAYLAS - ANCASH
SECTOR: CHULLIN - NUEVO PROGRESO
SUSTENTO DE METRADOS DE EXCAVACIONES DEL KM 0+000 AL KM 3+185.75
km 0+000 - km 0+990
MEJORAMIENTO DEL SERVICIO DE AGUA PARA RIEGO HUAYLAS - ANCASH
SECTOR: CHULLIN - NUEVO PROGRESO
SUSTENTO DE METRADOS DE EXCAVACIONES DEL KM 0+000 AL KM 3+185.75
PROGRESIVA DISTANCIA A.C. A.R V.C. V.R. V.C. V.C. V.C.
(m) m2 m2 m3 m3 M.S R.S. R.F
(1)+(2)+(3) (1) (2) (3)
1+000.00 13.66 0.00 0.00
1+020.00 20.00 17.90 315.60 0.00
1+040.00 20.00 7.01 249.10 0.00
1+060.00 20.00 22.32 293.30 0.00
1+080.00 20.00 28.57 508.90 0.00
1+090.00 10.00 31.90 302.35 0.00
1+100.00 10.00 32.58 322.40 0.00
1+110.00 10.00 45.75 391.65 0.00
1+120.00 10.00 32.08 389.15 0.00
1+140.00 20.00 19.11 511.90 0.00
1+150.00 10.00 21.20 201.55 0.00
1+160.00 10.00 19.72 204.60 0.00
1+180.00 20.00 50.02 697.40 0.00
1+200.00 20.00 24.88 749.00 0.00
1+220.00 20.00 6.90 317.80 0.00
1+240.00 20.00 0.68 75.80 0.00
1+260.00 20.00 0.89 15.70 0.00
1+280.00 20.00 0.82 17.10 0.00
1+300.00 20.00 0.81 16.30 0.00
1+320.00 20.00 0.96 17.70 0.00
1+340.00 20.00 0.84 18.00 0.00
1+360.00 20.00 1.19 20.30 0.00
1+380.00 20.00 1.52 27.10 0.00
1+420.00 40.00 33.70 704.40 0.00
1+430.00 10.00 1.38 175.40 0.00
1+440.00 10.00 1.24 13.10 0.00
1+460.00 20.00 0.72 19.60 0.00
1+480.00 20.00 0.67 13.90 0.00
1+500.00 20.00 0.95 16.20 0.00
1+520.00 20.00 0.97 19.20 0.00
1+540.00 20.00 0.98 19.50 0.00
1+550.00 10.00 0.33 0.02 6.55 0.05
1+560.00 10.00 2.13 12.30 0.05
1+580.00 20.00 1.77 39.00 0.00
1+590.00 10.00 5.60 36.85 0.00
1+600.00 10.00 8.43 70.15 0.00
1+610.00 10.00 19.23 0.59 138.30 1.48
1+620.00 10.00 17.56 183.95 1.48
1+640.00 20.00 1.03 185.90 0.00
1+660.00 20.00 0.87 19.00 0.00
1+680.00 20.00 0.60 14.70 0.00
1+710.00 30.00 1.21 27.15 0.00
1+720.00 10.00 1.29 12.50 0.00
1+740.00 20.00 1.09 23.80 0.00
1+760.00 20.00 1.29 23.80 0.00
1+770.00 10.00 1.48 13.85 0.00
1+780.00 10.00 2.98 22.30 0.00
1+800.00 20.00 5.12 81.00 0.00
1+820.00 20.00 1.13 62.50 0.00
1+840.00 20.00 2.13 32.60 0.00
1+860.00 20.00 1.92 40.50 0.00
1+880.00 20.00 2.12 40.40 0.00
1+900.00 20.00 0.66 27.80 0.00
1+920.00 20.00 6.30 69.60 0.00
1+940.00 20.00 0.79 70.90 0.00
7899.40 3.05 0.00 0.00 0.00km 1+000 - km 1+940
MEJORAMIENTO DEL SERVICIO DE AGUA PARA RIEGO HUAYLAS - ANCASH
SECTOR: CHULLIN - NUEVO PROGRESO
SUSTENTO DE METRADOS DE EXCAVACIONES DEL KM 0+000 AL KM 3+185.75
PROGRESIVA DISTANCIA A.C. A.R V.C. V.R. V.C. V.C. V.C.
(m) m2 m2 m3 m3 M.S R.S. R.F
(1)+(2)+(3) (1) (2) (3)
1+960.00 1.50 0.00 0.00
1+970.00 10.00 1.28 13.90 0.00
1+980.00 10.00 0.98 11.30 0.00
2+000.00 20.00 0.90 18.80 0.00
2+030.00 30.00 4.37 79.05 0.00
2+040.00 10.00 5.51 49.40 0.00
2+060.00 20.00 6.15 116.60 0.00
2+080.00 20.00 1.99 81.40 0.00
2+100.00 20.00 1.38 33.70 0.00
2+120.00 20.00 0.83 22.10 0.00
2+140.00 20.00 0.88 17.10 0.00
2+160.00 20.00 1.11 19.90 0.00
2+180.00 20.00 0.86 19.70 0.00
2+200.00 20.00 0.89 17.50 0.00
2+220.00 20.00 0.91 18.00 0.00
2+250.00 30.00 0.91 27.30 0.00
2+260.00 10.00 1.07 9.90 0.00
2+300.00 40.00 0.78 37.00 0.00
2+330.00 30.00 0.96 26.10 0.00
2+340.00 10.00 0.63 7.95 0.00
2+350.00 10.00 0.64 6.35 0.00
2+360.00 10.00 0.60 6.20 0.00
2+400.00 40.00 0.74 26.80 0.00
2+420.00 20.00 0.63 13.70 0.00
2+440.00 20.00 0.81 14.40 0.00
2+460.00 20.00 1.04 18.50 0.00
2+480.00 20.00 0.70 17.40 0.00
2+500.00 20.00 0.57 12.70 0.00
2+520.00 20.00 0.59 11.60 0.00
2+540.00 20.00 0.94 15.30 0.00
2+560.00 20.00 0.81 17.50 0.00
2+580.00 20.00 0.87 16.80 0.00
2+600.00 20.00 0.85 17.20 0.00
2+620.00 20.00 0.85 17.00 0.00
2+650.00 30.00 1.00 27.75 0.00
2+660.00 10.00 1.11 10.55 0.00
2+680.00 20.00 1.04 21.50 0.00
2+700.00 20.00 1.12 21.60 0.00
2+710.00 10.00 1.34 12.30 0.00
2+740.00 30.00 2.48 57.30 0.00
2+770.00 30.00 4.32 102.00 0.00
2+780.00 10.00 3.26 37.90 0.00
2+790.00 10.00 19.32 112.90 0.00
2+810.00 20.00 2.13 214.50 0.00
2+840.00 30.00 1.89 60.30 0.00
2+850.00 10.00 2.04 19.65 0.00
2+870.00 20.00 11.81 138.50 0.00
2+890.00 20.00 2.38 141.90 0.00
2+900.00 10.00 2.39 23.85 0.00
2+920.00 20.00 2.31 47.00 0.00
2+940.00 20.00 2.25 45.60 0.00
2+980.00 40.00 0.77 60.40 0.00
3+000.00 20.00 0.61 13.80 0.00
2007.45 0.00 0.00 0.00 0.00km 1+960 - km 3+000
MEJORAMIENTO DEL SERVICIO DE AGUA PARA RIEGO HUAYLAS - ANCASH
SECTOR: CHULLIN - NUEVO PROGRESO
SUSTENTO DE METRADOS DE EXCAVACIONES DEL KM 0+000 AL KM 3+185.75
PROGRESIVA DISTANCIA A.C. A.R V.C. V.R. V.C. V.C. V.C.
(m) m2 m2 m3 m3 M.S R.S. R.F
(1)+(2)+(3) (1) (2) (3)
3+020.00 0.96 0.00 0.00
3+040.00 20.00 0.75 17.10 0.00
3+050.00 10.00 1.02 8.85 0.00
3+070.00 20.00 0.49 15.10 0.00
3+080.00 10.00 0.65 5.70 0.00
3+090.00 10.00 0.81 7.30 0.00
3+100.00 10.00 2.55 16.80 0.00
3+120.00 20.00 1.18 37.30 0.00
3+130.00 10.00 0.89 10.35 0.00
3+140.00 10.00 0.70 7.95 0.00
3+160.00 20.00 0.87 15.70 0.00
3+185.75 25.75 0.87 22.40 0.00
164.55 0.00 0.00 0.00 0.00
11276.17 m3 10.29%
11100.80 m3 9.22%
175.37 m3 Diferencia de vol. 80.49%
EXPEDIENTE DIFERENCIA
1160.20 m3 18.04 m3
1039.57 m3 16.17 m3
9076.40 m3 141.16 m3
1142.16 m3
1023.40 m3
8935.24 m3
PROPUESTO
RESUMEN DE METRADO
VOLUMEN TOTAL DE EXCAVACION (ACTUAL):
VOLUMEN TOTAL DE EXCAVACION (EXPED.):
km 3+020 - km 3+185.75
VOL. MAT. SUELTO
VOL. ROCA SUELTA
VOL. ROCA FIJA