Hoja N° 1/38HOJA DE RESUMEN DE METRADOS - ESTRUCTURAS
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA N°
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MODULOS
TOTALMODULO 1 MODULO 2 MODULO 3
04.00.00.00 ESTRUCTURAS
04.01.00.00 MOVIMIENTO DE TIERRAS
04.01.01.00 EXCAVACIONES DE ZANJAS EN ZAPATAS-CIMIENTOS CORRIDOS M3 139.22 258.24 44.77 442.23
04.01.02.00 RELLENO COMPACTADO DE MATERIAL PROPIO, C/EQUIPO M3 54.74 103.34 17.83 175.91
04.01.03.00 RELLENO COMPACTADO DE MATERIAL DE PRESTAMO, ARENILLA, C/EQUIPO M3 15.18 57.88 17.87 90.93
04.01.04.00 RELLENO COMPACTADO DE MATERIAL DE PRESTAMO, AFIRMADO, C/EQUIPO M3 11.88 22.73 5.41 40.03
04.01.05.00 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES M3 139.22 258.24 44.77 442.23
04.01.06.00 ELIMINACION MATERIAL EXCEDENTE M3 92.93 170.39 29.63 292.94
04.02.00.00 CONCRETO SIMPLE
04.02.01.00 SOLADO e=4" PARA ZAPATAS Y VIGAS DE CIMENTACION f'c=100 kg/cm2 M2 99.44 181.09 31.98 312.51
04.02.02.00 CONCRETO EN CIMIENTOS CORRIDOS f'c=120 kg/cm2 + 30% P.G. M3 0.00 6.54 0.00 6.54
04.02.03.00 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS CORRIDOS M3 0.00 26.40 0.00 26.40
04.02.04.00 CONCRETO EN SOBRECIMIENTOS f'c=120 kg/cm2 + 25% P.M. M3 2.11 9.26 0.00 11.37
04.02.05.00 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS M2 21.59 87.19 0.00 108.78
04.02.06.00 FALSO PISO f'c=140 kg/cm2 M2 127.26 22.73 54.11 204.11
04.03.00.00 CONCRETO ARMADO
04.03.01.00 ZAPATAS
04.03.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 M3 59.66 108.65 19.19 187.50
04.03.01.02 ACERO EN ZAPATAS fy=4200 kg/cm2 KG 1,446.00 2,187.00 641.00 4,274.00
04.03.02.00 VIGAS DE CIMENTACION
04.03.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 kg/cm2 M3 25.50 62.31 9.42 97.23
04.03.02.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS DE CIMENTACION M2 204.00 462.52 62.79 729.31
04.03.02.03 ACERO EN VIGAS DE CIMENTACION fy=4200 kg/cm2 KG 3,939.00 4,363.00 716.00 9,018.00
04.03.03.00 COLUMNAS
04.03.03.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 M3 24.22 44.82 10.19 79.23
04.03.03.02 ENCOFRADO Y DESCENCOFRADO DE COLUMNAS M2 255.96 435.93 47.00 738.89
04.03.03.03 ACERO EN COLUMNAS fy=4200 kg/cm2 KG 6,793.00 12,217.00 876.00 19,886.00
04.03.04.00 COLUMNETAS
04.03.04.01 CONCRETO EN COLUMNETAS f'c=210 kg/cm2 M3 4.07 5.90 0.30 10.27
04.03.04.02 ENCOFRADO Y DESCENCOFRADO DE COLUMNETAS M2 57.96 52.73 4.00 114.70
04.03.04.03 ACERO EN COLUMNETAS fy=4200 kg/cm2 KG 398.00 593.00 31.00 1,022.00
04.03.05.00 VIGAS
04.03.05.01 CONCRETO EN VIGAS f'c=210 kg/cm2 M3 22.17 37.11 10.33 69.62
04.03.05.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS M2 222.92 354.54 69.03 646.49
04.03.05.03 ACERO EN VIGAS fy=4200 kg/cm2 KG 4,081.00 7,405.00 1,835.00 13,321.00
04.03.06.00 VIGAS DE AMARRES
04.03.06.01 CONCRETO EN VIGAS DE AMARRES f'c=210 kg/cm2 M3 1.04 1.67 0.51 3.23
04.03.06.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS DE AMARRES M2 24.02 39.51 5.98 69.51
04.03.06.03 ACERO EN VIGAS DE AMARRES fy=4200 kg/cm2 KG 111.00 209.00 61.00 381.00
04.03.07.00 LOSA ALIGERADA
04.03.07.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 M3 27.44 38.46 9.75 75.64
04.03.07.02 ENCOFRADO Y DESCENCOFRADO DE LOSA ALIGERADA M2 328.62 457.58 75.28 861.47
04.03.07.03 ACERO EN LOSA ALIGERADA fy=4200 kg/cm2 KG 2,616.00 4,951.00 1,158.00 8,725.00
04.03.07.04 LADRILLO DE ARCILLA 15x30x30 CM PARA LOSA ALIGERADA UND 2,740.00 3,814.00 472.00 7,026.00
04.03.08.00 ESCALERA
04.03.08.01 CONCRETO EN ESCALERA f'c=210 kg/cm2 M3 0.00 4.54 0.00 4.54
04.03.08.02 ENCOFRADO Y DESCENCOFRADO DE ESCALERA M2 0.00 20.03 0.00 20.03
04.03.08.03 ACERO EN ESCALERA fy=4200 kg/cm2 KG 0.00 400.00 0.00 400.00
04.03.09.00 MURO INTERMEDIO DE ESCALERA
04.03.09.01 CONCRETO EN MURO INTERMEDIO DE ESCALERA f'c=210 kg/cm2 M3 0.00 2.03 0.00 2.03
04.03.09.02 ENCOFRADO Y DESCENCOFRADO DE MURO INTERMEDIO DE ESCALERA M2 0.00 13.50 0.00 13.50
04.03.09.03 ACERO EN MURO INTERMEDIO DE ESCALERA fy=4200 kg/cm2 KG 0.00 310.00 0.00 310.00
04.03.10.00 GARGOLAS
04.03.10.01 CONCRETO EN GARGOLAS f'c=175 kg/cm2 M3 0.01 0.01 0.00 0.02
04.03.10.02 ENCOFRADO Y DESCENCOFRADO DE GARGOLAS M2 0.32 0.47 0.00 0.79
04.03.10.03 ACERO EN GARGOLAS fy=4200 kg/cm2 KG 0.72 1.09 0.00 1.81
04.03.11.00 MESON PARA LAVATORIOS OVALINES
04.03.11.01 CONCRETO EN MESON f'c=210 kg/cm2 M3 0.00 0.18 0.00 0.18
04.03.11.02 ENCOFRADO Y DESCENCOFRADO DE MESON M2 0.00 3.88 0.00 3.88
04.03.11.03 ACERO EN MESON fy=4200 kg/cm2 KG 0.00 56.00 0.00 56.00
Hoja N° 2/38HOJA DE METRADOS DE ESTRUCTURAS
OBRA : CASA - HABITACION "SR. VITA" FECHA N° : 17/12/2011
UBICACIÓN : FERREÑAFE - FERREÑAFE - LAMBAYEQUE PLANO N° : CIMENTACIÓN
PROPIETARIO : SR. JUAN VITA ABARCA HECHO : KAUTSKY HITLIER NEIRA DE LA CRUZ
ESPECIALIDAD : ESTRUCTURAS REVISADO : ING. ANDRES VASQUEZ MANAY
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
01 OBRAS PROVISIONALES
01.01 CONSTRUCCIONES PROVISIONALES DE CERCO CON MADERA Y TRIPLAY 7.80
01.01 M 1.00 1.00 7.80 7.80
01.01
01.02 CARTEL DE OBRA DE 4.00 x 3.00 M UND 1.00 1.00 1.00 1.00
01.02
01.03 INSTALACION DE AGUA PARA LA CONSTRUCCIÓN GLB 1.00 1.00 1.00 1.00
01.03
02 TRABAJOS PRELIMINARES
02.01 LIMPIEZA DE TERRENO 142.50
1.00 1.00 23.75 6.00 142.50
0
02.02 TRAZOS, NIVELES Y REPLANTEO PRELIMINAR 142.50
1.00 1.00 23.75 6.00 142.50
0
CANT.REP.
N°ELEM.
M²
M²
3/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
OBRAS PROVISIONALES
04.01.00.00 MOVIMIENTO DE TIERRAS
04.01.01.00 EXCAVACIONES DE ZANJAS EN ZAPATAS-CIMIENTOS CORRIDOS 139.22
Exc. Zapatas
Zapata 1 (EJE A-A) M3 1.00 1.00 23.20 1.20 1.40 38.98
Zapata 2 (EJE C-C) M3 1.00 1.00 23.20 2.00 1.40 64.96
Exc. Cimiento Corrido
EJE 6-6, EJE 8-8, EJE 10-10, EJE 12-12 M3 1.00 4.00 4.20 0.90 1.40 21.17
EJE 7-7, EJE 9-9, EJE 11-11 M3 1.00 3.00 4.20 0.80 1.40 14.11
04.01.02.00 RELLENO COMPACTADO DE MATERIAL PROPIO, C/EQUIPO 54.74
Volumen de Excavación 139.22
Volumen de Concreto 84.48
Volumen de Concreto de Solado 9.94
Volumen de Concreto de Zapata 59.66
Volumen de Concreto de Viga de Cimentación 14.87
04.01.03.00 RELLENO COMPACTADO DE MATERIAL DE PRESTAMO, ARENILLA, C/EQUIPO 15.18
EJE C-C 1.00 2.00 3.43 1.00 0.30 2.06
1.00 4.00 3.40 1.00 0.30 4.08
EJE A-A 1.00 2.00 3.43 0.60 0.30 1.23
1.00 4.00 3.40 0.60 0.30 2.45
TRAMO 6-6,8-8,10-10,12-12 1.00 4.00 4.20 0.65 0.30 3.28
TRAMO 7-7,9-9,11-11 1.00 3.00 4.20 0.55 0.30 2.08
04.01.04.00 RELLENO COMPACTADO DE MATERIAL DE PRESTAMO, AFIRMADO, C/EQUIPO 11.88
AULA - 01 1.00 1.00 6.83 5.80 0.10 3.96
AULA - 02 1.00 1.00 6.83 5.80 0.10 3.96
AULA - 03 1.00 1.00 6.83 5.80 0.10 3.96
04.01.05.00 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 139.22
04.01.06.00 ELIMINACION MATERIAL EXCEDENTE 92.93
Volumen de Excavación 139.22
Volumen de Relleno Compactado con Material Propio 54.74
Factor de Esponjamiento 1.10
04.02.00.00 CONCRETO SIMPLE
04.02.01.00 SOLADO e=4" PARA ZAPATAS Y VIGAS DE CIMENTACION f'c=100 kg/cm2 M² 99.44
Zapatas
Zapata 1 (EJE C-C) M² 1.00 1.00 23.20 2.00 46.40
Zapata 2 (EJE A-A) M² 1.00 1.00 23.20 1.20 27.84
Cimiento corrido
EJE 6-6, EJE 8-8, EJE 10-10, EJE 12-12 M² 4.00 1.00 4.20 0.90 15.12
EJE 7-7, EJE 9-9, EJE 11-11 M² 3.00 1.00 4.20 0.80 10.08
04.02.02.00 CONCRETO EN CIMIENTOS CORRIDOS f'c=120 kg/cm2 + 30% P.G. 0.00
04.02.03.00 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS CORRIDOS M² 0.00
04.02.04.00 CONCRETO EN SOBRECIMIENTOS f'c=120 kg/cm2 + 25% P.M. 2.11
PRIMER NIVEL
EJE 6-6 dimension de muro =0.25 m 1.00 2.00 2.45 0.25 0.25 0.31
EJE 8-8 dimension de muro = 0.25 m 1.00 2.00 2.45 0.25 0.25 0.31
EJE 10-10 dimension de muro= 0.25 m 1.00 2.00 2.45 0.25 0.25 0.31
EJE 12-12 dimension de muro =0.25 m 1.00 2.00 2.45 0.25 0.25 0.31
PRIMER NIVEL
EJE A ENTRE 6-7 dimension de muro = 0.15 m 1.00 1.00 2.23 0.15 0.25 0.08
EJE A ENTRE 7-8 dimension de muro =0.15 m 1.00 1.00 2.20 0.15 0.25 0.08
EJE A ENTRE 8-9 dimension de muro =0.15m 1.00 1.00 2.20 0.15 0.25 0.08
EJE A ENTRE 9-10 dimension de muro=0.15m 1.00 1.00 2.20 0.15 0.25 0.08
EJE A ENTRE 10-11 dimension demuro =0.15m 1.00 1.00 2.20 0.15 0.25 0.08
EJE A ENTRE 11-12 dimension de muro = 0.15 1.00 1.00 2.23 0.15 0.25 0.08
EJE C ENTRE 6-7 dimension de muro = 0.15 m 1.00 1.00 1.25 0.15 0.25 0.05
EJE C ENTRE 7-8 dimension de muro =0.15 m 1.00 1.00 2.20 0.15 0.25 0.08
EJE C ENTRE 8-9 dimension de muro =0.15m 1.00 1.00 1.23 0.15 0.25 0.05
EJE C ENTRE 9-10 dimension de muro=0.15m 1.00 1.00 2.20 0.15 0.25 0.08
EJE C ENTRE 10-11 dimension demuro =0.15m 1.00 1.00 1.23 0.15 0.25 0.05
EJE C ENTRE 11-12 dimension de muro = 0.15 1.00 1.00 2.23 0.15 0.25 0.08
CANT.REP.
N°ELEM.
M³
M³
M³
M³
M³M³M³
M³
M³M³M³M³M³M³
M³
M³M³M³
M³
M³
M³M³
M³
M³
M²M²M²M²
M²M²M²M²M²M²M²M²M²M²M²M²
4/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
04.02.05.00 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS M² 21.59
EJE 6-6 dimension de muro =0.25 m 2.00 2.00 2.45 0.25 2.45
EJE 8-8 dimension de muro = 0.25 m 2.00 2.00 2.45 0.25 2.45
EJE 10-10 dimension de muro= 0.25 m 2.00 2.00 2.45 0.25 2.45
EJE 12-12 dimension de muro =0.25 m 2.00 2.00 2.45 0.25 2.45
PRIMER NIVEL
EJE A ENTRE 6-7 dimension de muro = 0.15 m 1.00 2.00 2.23 0.25 1.11
EJE A ENTRE 7-8 dimension de muro =0.15 m 1.00 2.00 2.20 0.25 1.10
EJE A ENTRE 8-9 dimension de muro =0.15m 1.00 2.00 2.20 0.25 1.10
EJE A ENTRE 9-10 dimension de muro=0.15m 1.00 2.00 2.20 0.25 1.10
EJE A ENTRE 10-11 dimension demuro =0.15m 1.00 2.00 2.20 0.25 1.10
EJE A ENTRE 11-12 dimension de muro = 0.15 1.00 2.00 2.23 0.25 1.11
EJE C ENTRE 6-7 dimension de muro = 0.15 m 1.00 2.00 1.25 0.25 0.63
EJE C ENTRE 7-8 dimension de muro =0.15 m 1.00 2.00 2.20 0.25 1.10
EJE C ENTRE 8-9 dimension de muro =0.15m 1.00 2.00 1.23 0.25 0.61
EJE C ENTRE 9-10 dimension de muro=0.15m 1.00 2.00 2.20 0.25 1.10
EJE C ENTRE 10-11 dimension demuro =0.15m 1.00 2.00 1.23 0.25 0.61
EJE C ENTRE 11-12 dimension de muro = 0.15 1.00 2.00 2.23 0.25 1.11
04.02.06.00 FALSO PISO f'c=140 kg/cm2 M² 127.26
AULA - 01 M² 1.00 1.00 7.08 6.00 42.48
AULA - 02 M² 1.00 1.00 7.05 6.00 42.30
AULA - 03 M² 1.00 1.00 7.08 6.00 42.48
04.03.00.00 CONCRETO ARMADO
04.03.01.00 ZAPATAS
04.03.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 59.66
Exc. Zapatas
Zapatas (Z-1) eje C-C 1.00 1.00 23.20 2.00 0.60 27.84
Zapatas (Z-2) eje A-A 1.00 1.00 23.20 1.20 0.60 16.70
Zapatas (Z-3) EJE 6-6, EJE 8-8, EJE 10-10, EJE 12-12 4.00 1.00 4.20 0.90 0.60 9.07
Zapatas (Z-4) EJE 7-7, EJE 9-9, EJE 11-11 3.00 1.00 4.20 0.80 0.60 6.05
04.03.01.02 ACERO EN ZAPATAS fy=4200 kg/cm2 Kg 1,446.00
04.03.02.00 VIGAS DE CIMENTACION
04.03.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 kg/cm2 25.50
Eje A-A 1.00 1.00 22.20 0.25 1.20 6.66
Eje C-C 1.00 1.00 22.20 0.25 1.20 6.66
Eje Verticales 7.00 1.00 5.80 0.25 1.20 12.18
04.03.02.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS DE CIMENTACION M² 204.00
Eje A-A M² 1.00 2.00 22.20 1.20 53.28
Eje C-C M² 1.00 2.00 22.20 1.20 53.28
Eje Verticales M² 7.00 2.00 5.80 1.20 97.44
04.03.02.03 ACERO EN VIGAS DE CIMENTACION fy=4200 kg/cm2 Kg 3,939.00
04.03.03.00 COLUMNAS
04.03.03.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 24.22
EJE A-A; COLUMNAS TIPO "L" 2.00 1.00 0.50 0.25 7.17 1.79
2.00 1.00 0.33 0.15 7.17 0.71
EJE C-C; COLUMNAS TIPO "L" 2.00 1.00 0.50 0.25 7.17 1.79
2.00 1.00 0.33 0.15 7.17 0.71
EJE A-A; COLUMNAS TIPO "T" 5.00 1.00 0.90 0.15 7.17 4.84
5.00 1.00 0.35 0.25 7.17 3.14
EJE C-C; COLUMNAS TIPO "T" 5.00 1.00 0.90 0.15 7.17 4.84
5.00 1.00 0.35 0.25 7.17 3.14
EJE B-B; COLUMNAS TIPO RECTANGULAR 4.00 1.00 0.40 0.25 8.16 3.26
04.03.03.02 ENCOFRADO Y DESCENCOFRADO DE COLUMNAS M² 255.96
COLUMNA EN EJE 6-6:A-A ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 1.08 7.17 7.71
1.00 1.00 0.15 3.28 0.49
1.00 1.00 0.15 3.28 0.49
1.00 1.00 0.43 3.45 1.47
1.00 1.00 0.43 3.10 1.32
M² 1.00 1.00 0.25 3.55 0.89
1.00 1.00 0.25 3.30 0.83
COLUMNA EN EJE 6-6:C-C ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.50 7.17 3.59
M² 1.00 1.00 0.25 3.35 0.84
1.00 1.00 0.33 3.65 1.19
M²M²M²M²
M²M²M²M²M²M²M²M²M²M²M²M²
M³
M³M³M³M³
M³
M³M³M³
M³
M³M³M³M³M³M³M³M³M³
M²M²M²M²M²
M²M²
M²
5/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
M² 1.00 1.00 0.25 2.90 0.73
1.00 1.00 0.33 3.20 1.04
M² 1.00 1.00 0.58 3.45 1.98
1.00 1.00 0.58 3.10 1.78
M² 1.00 1.00 0.25 3.55 0.89
1.00 1.00 0.25 3.30 0.83
COLUMNA EN EJE 12-12:A-A ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 1.08 7.17 7.71
M² 1.00 1.00 0.15 3.28 0.49
1.00 1.00 0.15 3.28 0.49
M² 1.00 1.00 0.43 3.45 1.47
1.00 1.00 0.43 3.10 1.32
M² 1.00 1.00 0.25 3.55 0.89
1.00 1.00 0.25 3.30 0.83
COLUMNA EN EJE 12-12:C-C ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.50 7.17 3.59
M² 1.00 1.00 0.25 3.35 0.84
1.00 1.00 0.33 3.65 1.19
M² 1.00 1.00 0.25 2.90 0.73
1.00 1.00 0.33 3.20 1.04
M² 1.00 1.00 0.15 3.28 0.49
1.00 1.00 0.15 3.28 0.49
M² 1.00 1.00 0.43 3.45 1.47
1.00 1.00 0.43 3.10 1.32
M² 1.00 1.00 0.25 3.55 0.89
1.00 1.00 0.25 3.30 0.83
COLUMNA EN EJE 7-7:A-A ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.90 7.04 6.34
2.00 2.00 0.15 3.28 1.97
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.44 3.44
1.00 2.00 0.25 3.13 1.56
COLUMNA EN EJE 8-8:A-A ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.90 7.04 6.34
2.00 2.00 0.15 3.28 1.97
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.44 3.44
COLUMNA EN EJE 9-9:A-A ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.90 7.04 6.34
2.00 2.00 0.15 3.28 1.97
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.44 3.44
1.00 2.00 0.25 3.13 1.56
COLUMNA EN EJE 10-10:A-A ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.90 7.04 6.34
2.00 2.00 0.15 3.28 1.97
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.44 3.44
COLUMNA EN EJE 11-11:A-A ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.90 7.04 6.34
2.00 2.00 0.15 3.28 1.97
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.45 3.45
1.00 2.00 0.25 3.13 1.56
COLUMNA EN EJE 6-6:B-B; 12-12:B-B ( PRIMER Y SEGUNDO NIVEL ) 2.00 1.00 0.40 8.16 6.53
2.00 2.00 0.40 3.84 6.14
COLUMNA EN EJE 8-8:B-B; 10-10:B-B ( PRIMER Y SEGUNDO NIVEL ) 2.00 4.00 0.40 3.84 12.29
COLUMNA EN EJE 7-7:C-C ( PRIMER Y SEGUNDO NIVEL ) 1.00 2.00 0.90 3.13 5.63
2.00 2.00 0.15 3.28 1.96
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.44 3.44
1.00 2.00 0.25 3.13 1.56
COLUMNA EN EJE 8-8:C-C ( PRIMER Y SEGUNDO NIVEL ) 1.00 2.00 0.90 3.13 5.63
2.00 2.00 0.15 3.28 1.96
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.44 3.44
COLUMNA EN EJE 9-9:C-C ( PRIMER Y SEGUNDO NIVEL ) 1.00 2.00 0.90 3.13 5.63
2.00 2.00 0.15 3.28 1.96
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.44 3.44
1.00 2.00 0.25 3.13 1.56
COLUMNA EN EJE 10-10:C-C ( PRIMER Y SEGUNDO NIVEL ) 1.00 2.00 0.90 3.13 5.63
2.00 2.00 0.15 3.28 1.96
2.00 2.00 0.43 3.28 5.57
2.00 2.00 0.25 3.44 3.44
COLUMNA EN EJE 11-11:C-C ( PRIMER Y SEGUNDO NIVEL ) 1.00 2.00 0.90 3.13 5.63
2.00 2.00 0.15 3.28 1.96
2.00 2.00 0.43 3.28 5.57
M²
M²
M²M²
M²
M²
M²M²
M²
M²
M²
M²
M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²
6/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
2.00 2.00 0.25 3.44 3.44
1.00 2.00 0.25 3.13 1.56
04.03.03.03 ACERO EN COLUMNAS fy=4200 kg/cm2 Kg 6,793.00
04.03.04.00 COLUMNETAS
04.03.04.01 CONCRETO EN COLUMNETAS f'c=210 kg/cm2 4.07
EJE A-A ( PRIMER Y SEGUNDO NIVEL ) 12.00 2.00 0.25 0.15 2.03 1.82
EJE C-C ( PRIMER Y SEGUNDO NIVEL ) 12.00 2.00 0.25 0.15 1.48 1.33
PARAPETOS 9.00 1.00 0.25 0.15 1.00 0.34
FALSO MURO 4.00 1.00 0.25 0.10 5.83 0.58
04.03.04.02 ENCOFRADO Y DESCENCOFRADO DE COLUMNETAS M² 57.96
COLUMNETAS EJE A-A ( PRIMER Y SEGUNDO NIVEL ) 12.00 4.00 0.25 2.03 24.30
COLUMNETAS EJE C-C ( PRIMER Y SEGUNDO NIVEL ) 12.00 4.00 0.25 1.48 17.70
3.00 1.00 0.15 1.40 0.63
PARAPETOS 9.00 1.00 2.15 0.25 4.84
FALSO MURO 4.00 1.00 0.45 5.83 10.49
04.03.04.03 ACERO EN COLUMNETAS fy=4200 kg/cm2 Kg 398.00
04.03.05.00 VIGAS
04.03.05.01 CONCRETO EN VIGAS f'c=210 kg/cm2 22.17
PRIMER NIVEL
EJE 6,8,10,12 4.00 2.00 2.45 0.25 0.30 1.47
EJE 7,9,11 3.00 1.00 5.30 0.25 0.60 2.39
EJE A; ENTRE EJE 6-7 Y 11-12 2.00 1.00 2.78 0.15 0.30 0.25
2.00 1.00 3.43 0.10 0.30 0.21
EJE A; ENTRE EJE 7 HASTA EJE 11 4.00 1.00 2.75 0.15 0.30 0.49
4.00 1.00 3.40 0.10 0.30 0.41
EJE C; ENTRE EJE 6-7 Y 11-12 2.00 1.00 3.43 0.10 0.30 0.21
2.00 1.00 2.78 0.15 0.30 0.25
EJE C; ENTRE EJE 7 HASTA EJE 11 4.00 1.00 3.40 0.10 0.30 0.41
4.00 1.00 2.75 0.15 0.30 0.49
VOLADIZOS
EJE 6 HASTA EJE 12 7.00 1.00 1.90 0.25 0.35 1.16
EJE 6-7 1.00 1.00 3.43 0.15 0.20 0.10
EJE 11-12 1.00 1.00 3.42 0.15 0.20 0.10
DESDE EJE 7 HASTA EJE 11 4.00 1.00 3.40 0.15 0.20 0.41
SEGUNDO NIVEL
EJE 6,8,10,12 4.00 2.00 2.45 0.25 0.30 1.47
EJE A; ENTRE EJE 6-7 Y 11-12 2.00 1.00 2.78 0.15 0.34 0.28
2.00 1.00 3.43 0.10 0.34 0.23
EJE A; ENTRE EJE 7 HASTA EJE 11 4.00 1.00 2.75 0.15 0.34 0.56
4.00 1.00 3.40 0.10 0.34 0.46
EJE C; ENTRE EJE 6-7 Y 11-12 2.00 1.00 3.43 0.10 0.34 0.23
2.00 1.00 2.78 0.15 0.34 0.28
EJE C; ENTRE EJE 7 HASTA EJE 11 4.00 1.00 3.40 0.10 0.34 0.46
4.00 1.00 2.75 0.15 0.34 0.56
TECHO
EJE 6,8,10,12 4.00 2.00 2.43 0.25 0.30 1.46
EJE 7,9,11 3.00 1.00 5.54 0.25 0.50 2.08
VIGAS CENTRALES
VOLADIZO EN EXTREMOS 2.00 1.00 0.80 0.80 0.17 0.22
EJE 6-7 1.00 1.00 3.43 0.80 0.17 0.47
EJE 11-12 1.00 1.00 3.42 0.80 0.17 0.47
EJE 7-11 4.00 1.00 3.40 0.80 0.17 1.85
VOLADIZOS EN ELEVACION PRINCIPAL
PRINCIPALES 7.00 1.00 2.00 0.25 0.35 1.22
EJE EXTERIORES 2.00 1.00 0.80 0.15 0.17 0.04
EJE 6-7 1.00 1.00 3.43 0.15 0.17 0.09
EJE 11-12 1.00 1.00 3.42 0.15 0.17 0.09
DESDE EJE 7 HASTA EJE 11 4.00 1.00 3.40 0.15 0.17 0.35
VOLADIZOS EN ELEVACION POSTERIOR
EJE EXTERIORES 2.00 1.00 0.80 0.15 0.17 0.04
EJE 6-7 1.00 1.00 3.43 0.15 0.17 0.09
EJE 11-12 1.00 1.00 3.42 0.15 0.17 0.09
DESDE EJE 7 HASTA EJE 11 4.00 1.00 3.40 0.15 0.17 0.35
VOLADIZOS EN LOS LATERALES
2.00 1.00 0.65 0.15 0.17 0.03
2.00 1.00 2.52 0.15 0.17 0.13
M²M²
M³
M³M³M²M²
M²M²M²M²M²
M³
M³M³M³M³M³M³M³M³M³M³
M³M³M³M³
M³M³M³M³M³M³M³M³M³
M³M³
M³M³M³M³
M³M³M³M³M³
M³M³M³M³
M³M³
7/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
2.00 1.00 2.52 0.15 0.17 0.13
2.00 1.00 1.85 0.15 0.17 0.09
04.03.05.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS M² 222.92
PRIMER NIVEL
EJE 6-6, EJE 12-12 M² 2.00 2.00 2.45 0.30 2.94
M² 2.00 2.00 2.45 0.10 0.98
EJE 7-7, EJE 9-9, EJE 11-11 M² 3.00 1.00 5.30 1.05 16.70
EJE 8-8, EJE 10-10 M² 2.00 4.00 2.45 0.10 1.96
VOLADIZO EJE 6-6, EJE 12-12 M² 2.00 1.00 1.90 0.35 1.33
M² 2.00 1.00 1.70 0.15 0.51
M² 2.00 1.00 2.12 0.25 1.06
VOLDIZO EJE 7-7, EJE 8-8, EJE 9-9, EJE 10-10, EJE 11-11 M² 5.00 2.00 1.70 0.15 2.55
M² 5.00 1.00 2.12 0.25 2.65
EJE A-A, EJE 6-6:7-7; EJE 11-11:12-12 M² 2.00 1.00 2.78 0.45 2.50
M² 2.00 1.00 3.43 0.20 1.37
EJE A-A, EJE 7-7:11-11 M² 4.00 1.00 2.75 0.45 4.95
M² 4.00 1.00 3.40 0.20 2.72
EJE C-C, EJE 6-6:7-7 M² 2.00 1.00 2.78 0.25 1.39
M² 2.00 1.00 3.43 0.20 1.37
EJE C-C, EJE 7-7:11-11 M² 4.00 1.00 2.75 0.25 2.75
M² 4.00 1.00 3.40 0.20 2.72
VOLADIZO, EJE 6-6:7-7 M² 2.00 1.00 3.43 0.40 2.74
VOLADIZO, EJE 7-7:11-11 M² 4.00 1.00 3.40 0.40 5.44
SEGUNDO NIVEL
EJE 6-6, EJE 12-12 M² 2.00 4.00 2.45 0.30 5.88
EJE 8-8, EJE 10-10 M² 2.00 4.00 2.45 0.30 5.88
EJE A-A, EJE 6-6:7-7; EJE 11-11:12-12 M² 2.00 1.00 2.78 0.45 2.50
M² 2.00 1.00 3.43 0.40 2.74
EJE A-A, EJE 7-7:11-11; EJE 11-11:12-12 M² 4.00 1.00 2.75 0.45 4.95
M² 4.00 1.00 3.40 0.40 5.44
EJE C-C, EJE 6-6:7-7 M² 2.00 1.00 2.78 0.45 2.50
M² 2.00 1.00 3.43 0.40 2.74
EJE C-C, EJE 7-7:11-11; EJE 11-11:12-12 M² 4.00 1.00 2.75 0.45 4.95
M² 4.00 1.00 3.40 0.40 5.44
TECHO
EJE 6-6, EJE 12-12 M² 2.00 4.00 2.80 0.13 2.91
EJE 7-7, EJE 9-9, EJE 11-11 M² 3.00 4.00 2.80 0.91 30.58
EJE 8-8, EJE 10-10 M² 2.00 4.00 2.80 0.13 2.91
VOLADIZO M² 7.00 1.00 1.04 0.31 2.27
M² 7.00 1.00 2.30 0.31 4.98
EJE A-A, EJE 6-6:7-7; EJE 11-11:12-12 M² 2.00 1.00 2.78 0.21 1.17
M² 2.00 1.00 3.43 0.26 1.78
EJE A-A, EJE 7-7:11-11 M² 4.00 1.00 2.75 0.21 2.31
M² 4.00 1.00 3.40 0.26 3.54
VOLADIZO M² 2.00 1.00 1.00 0.31 0.62
EJE C-C, EJE 6-6:7-7:11-11:12-12 M² 2.00 1.00 2.78 0.31 1.72
M² 2.00 1.00 3.43 0.26 1.78
EJE C-C, EJE 7-7:11-11; EJE 11-11:12-12 M² 4.00 1.00 2.75 0.31 3.41
M² 4.00 1.00 3.40 0.26 3.54
VOLADIZO M² 2.00 1.00 1.00 0.31 0.62
EJE A-A, EJE 6-6:7-7; EJE 11-11:12-12 M² 2.00 2.00 3.43 0.41 5.62
VOLADIZO, EJE 7-7:11-11 M² 4.00 2.00 3.40 0.41 11.15
M² 4.00 1.00 0.80 0.46 1.47
VOLADIZOS LATERALES M² 2.00 1.00 1.04 0.41 0.86
M² 2.00 1.00 2.70 0.41 2.21
M² 2.00 1.00 2.70 0.41 2.21
M² 2.00 1.00 2.30 0.41 1.88
EJE A-A, EJE 6-6:7-7; EJE 11-11:12-12 M² 2.00 2.00 3.43 0.74 10.14
VIGA CENTRAL, EJE 7-7:11-11 M² 4.00 2.00 3.40 0.74 20.13
M² 2.00 1.00 1.00 0.74 1.48
04.03.05.03 ACERO EN VIGAS fy=4200 kg/cm2 Kg 4,081.00
04.03.06.00 VIGAS DE AMARRES
04.03.06.01 CONCRETO EN VIGAS DE AMARRES f'c=210 kg/cm2 1.04
PRIMER NIVEL
EJE A ENTRE 6-7 Y 11-12 2.00 1.00 2.22 0.15 0.10 0.07
EJE A DESDE EJE 7 HASTA 11 4.00 1.00 2.20 0.15 0.10 0.13
EJE C ENTRE 6-7 1.00 1.00 1.23 0.15 0.10 0.02
EJE C ENTRE 7-8 1.00 1.00 2.20 0.15 0.10 0.03
EJE C ENTRE 8-9 Y 10-11 2.00 1.00 1.19 0.15 0.10 0.04
EJE C ENTRE 9-10 1.00 1.00 2.20 0.15 0.10 0.03
EJE C ENTRE 11-12 1.00 1.00 2.20 0.15 0.10 0.03
M³M³
M³
M³M³M³M³M³M³M³
8/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
SEGUNDO NIVEL 0.00
EJE A ENTRE 6-7 Y 11-12 2.00 1.00 2.22 0.15 0.10 0.07
EJE A DESDE EJE 7 HASTA 11 4.00 1.00 2.20 0.15 0.10 0.13
EJE C ENTRE 6-7 1.00 1.00 1.23 0.15 0.10 0.02
EJE C ENTRE 7-8 1.00 1.00 2.20 0.15 0.10 0.03
EJE C ENTRE 8-9 Y 10-11 2.00 1.00 1.19 0.15 0.10 0.04
EJE C ENTRE 9-10 1.00 1.00 2.20 0.15 0.10 0.03
EJE C ENTRE 11-12 1.00 1.00 2.20 0.15 0.10 0.03
VIGAS EN PARAPETOS
EJE C ENTRE 6-7 1.00 1.00 3.43 0.15 0.10 0.05
EJE C ENTRE 11-12 1.00 1.00 3.43 0.15 0.10 0.05
EJE C ENTRE 7-11 4.00 1.00 3.40 0.15 0.10 0.20
EJE 12 1.00 1.00 1.25 0.25 0.10 0.03
04.03.06.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS DE AMARRES M² 24.02
PRIMER NIVEL
EJE A ENTRE 6-7 Y 11-12 M² 2.00 2.00 2.22 0.18 1.56
EJE A DESDE EJE 7 HASTA 11 M² 4.00 2.00 2.20 0.18 3.08
EJE C ENTRE 6-7 M² 1.00 2.00 1.23 0.18 0.43
EJE C ENTRE 7-8 M² 1.00 2.00 2.20 0.18 0.77
EJE C ENTRE 8-9 Y 10-11 M² 2.00 2.00 1.19 0.18 0.84
EJE C ENTRE 9-10 M² 1.00 2.00 2.20 0.18 0.77
EJE C ENTRE 11-12 M² 1.00 2.00 2.20 0.18 0.77
SEGUNDO NIVEL
EJE A ENTRE 6-7 Y 11-12 M² 2.00 2.00 2.22 0.18 1.56
EJE A DESDE EJE 7 HASTA 11 M² 4.00 2.00 2.20 0.18 3.08
EJE C ENTRE 6-7 M² 1.00 2.00 1.23 0.18 0.43
EJE C ENTRE 7-8 M² 1.00 2.00 2.20 0.18 0.77
EJE C ENTRE 8-9 Y 10-11 M² 2.00 2.00 1.19 0.18 0.84
EJE C ENTRE 9-10 M² 1.00 2.00 2.20 0.18 0.77
EJE C ENTRE 11-12 M² 1.00 2.00 2.20 0.18 0.77
VIGAS EN PARAPETOS
EJE C ENTRE 6-7 1.00 2.00 3.43 0.18 1.20
EJE C ENTRE 11-12 1.00 2.00 3.43 0.18 1.20
EJE C ENTRE 7-11 4.00 2.00 3.40 0.18 4.76
EJE 12 1.00 2.00 1.25 0.18 0.44
04.03.06.03 ACERO EN VIGAS DE AMARRES fy=4200 kg/cm2 Kg 111.00
04.03.07.00 LOSA ALIGERADA
04.03.07.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 27.44
AULA - 01 1.00 1.00 3.43 5.80 0.20 3.98
1.00 1.00 3.40 5.80 0.20 3.94
AULA - 02 1.00 1.00 3.40 5.80 0.20 3.94
1.00 1.00 3.40 5.80 0.20 3.94
AULA - 03 1.00 1.00 3.40 5.80 0.20 3.94
1.00 1.00 3.43 5.80 0.20 3.98
VOLADIZO 1.00 1.00 3.43 1.70 0.20 1.17
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 3.43 1.70 0.20 1.17
AULA - 04 1.00 2.00 3.43 2.70 0.17 3.15
1.00 2.00 3.40 2.70 0.17 3.12
AULA - 05 1.00 2.00 3.40 2.70 0.17 3.12
1.00 2.00 3.40 2.70 0.17 3.12
AULA - 06 1.00 2.00 3.40 2.70 0.17 3.12
1.00 2.00 3.43 2.70 0.17 3.15
VOLADIZO FRONTAL 1.00 1.00 3.43 1.95 0.17 1.14
1.00 1.00 3.40 1.95 0.17 1.13
1.00 1.00 3.40 1.95 0.17 1.13
1.00 1.00 3.40 1.95 0.17 1.13
1.00 1.00 3.40 1.95 0.17 1.13
1.00 1.00 3.43 1.95 0.17 1.14
VOLADIZO POSTERIOR 1.00 1.00 3.43 0.70 0.17 0.41
1.00 1.00 3.40 0.70 0.17 0.40
1.00 1.00 3.40 0.70 0.17 0.40
1.00 1.00 3.40 0.70 0.17 0.40
1.00 1.00 3.40 0.70 0.17 0.40
1.00 1.00 3.43 0.70 0.17 0.41
M³M³M³M³M³M³M³
M³M³M³M³
M³M³M³M³
M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
9/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
VOLADIZOS LATERALES 2.00 1.00 1.95 0.65 0.17 0.43
2.00 2.00 2.70 0.65 0.17 1.19
2.00 1.00 0.70 0.65 0.17 0.15
04.03.07.02 ENCOFRADO Y DESCENCOFRADO DE LOSA ALIGERADA M² 328.62
AULA - 01 M² 1.00 1.00 3.43 5.80 19.89
M² 1.00 1.00 3.40 5.80 19.72
AULA - 02 M² 1.00 1.00 3.40 5.80 19.72
M² 1.00 1.00 3.40 5.80 19.72
AULA - 03 M² 1.00 1.00 3.40 5.80 19.72
M² 1.00 1.00 3.43 5.80 19.89
VOLADIZO M² 1.00 1.00 3.43 1.70 5.83
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 3.43 1.70 5.83
AULA - 04 M² 1.00 2.00 3.43 2.70 18.52
M² 1.00 2.00 3.40 2.70 18.36
AULA - 05 M² 1.00 2.00 3.40 2.70 18.36
M² 1.00 2.00 3.40 2.70 18.36
AULA - 06 M² 1.00 2.00 3.40 2.70 18.36
M² 1.00 2.00 3.43 2.70 18.52
VOLADIZO FRONTAL M² 1.00 1.00 3.43 1.95 6.69
M² 1.00 1.00 3.40 1.95 6.63
M² 1.00 1.00 3.40 1.95 6.63
M² 1.00 1.00 3.40 1.95 6.63
M² 1.00 1.00 3.40 1.95 6.63
M² 1.00 1.00 3.43 1.95 6.69
VOLADIZO POSTERIOR M² 1.00 1.00 3.43 0.70 2.40
M² 1.00 1.00 3.40 0.70 2.38
M² 1.00 1.00 3.40 0.70 2.38
M² 1.00 1.00 3.40 0.70 2.38
M² 1.00 1.00 3.40 0.70 2.38
M² 1.00 1.00 3.43 0.70 2.40
VOLADIZOS LATERALES M² 2.00 1.00 1.95 0.65 2.54
M² 2.00 2.00 2.70 0.65 7.02
M² 2.00 1.00 0.70 0.65 0.91
04.03.07.03 ACERO EN LOSA ALIGERADA fy=4200 kg/cm2 Kg 2,616.00
04.03.07.04 LADRILLO DE ARCILLA 15x30x30 CM PARA LOSA ALIGERADA Und 2,740.00
04.03.08.00 ESCALERA
04.03.08.01 CONCRETO EN ESCALERA f'c=210 kg/cm2 0.00
04.03.08.02 ENCOFRADO Y DESCENCOFRADO DE ESCALERA M² 0.00
04.03.08.03 ACERO EN ESCALERA fy=4200 kg/cm2 Kg 0.00
04.03.09.00 MURO INTERMEDIO DE ESCALERA
04.03.09.01 CONCRETO EN MURO INTERMEDIO DE ESCALERA f'c=210 kg/cm2 0.00
04.03.09.02 ENCOFRADO Y DESCENCOFRADO DE MURO INTERMEDIO DE ESCALERA M² 0.00
04.03.09.03 ACERO EN MURO INTERMEDIO DE ESCALERA fy=4200 kg/cm2 Kg 0.00
04.03.10.00 GARGOLAS
04.03.10.01 CONCRETO EN GARGOLAS f'c=175 kg/cm2 0.01
2.00 1.00 0.18 0.05 0.15 0.00
2.00 1.00 0.25 0.05 0.10 0.00
2.00 1.00 0.25 0.10 0.10 0.01
04.03.10.02 ENCOFRADO Y DESCENCOFRADO DE GARGOLAS M² 0.32
M² 2.00 2.00 0.18 0.15 0.11
M² 2.00 1.00 0.25 0.10 0.05
M² 2.00 1.00 0.25 0.20 0.10
M² 2.00 1.00 0.20 0.10 0.04
M² 2.00 1.00 0.05 0.15 0.02
04.03.10.03 ACERO EN GARGOLAS fy=4200 kg/cm2 Kg 0.72
M³M³M³
M³
M³
M³
M³M³M³
10/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
04.03.11.00 MESON PARA LAVATORIOS OVALINES
04.03.11.01 CONCRETO EN MESON f'c=210 kg/cm2 0.00
04.03.11.02 ENCOFRADO Y DESCENCOFRADO DE MESON M² 0.00
04.03.11.03 ACERO EN MESON fy=4200 kg/cm2 Kg 0.00
M³
11/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"
04.03.00.00 OBRAS DE CONCRETO ARMADO
04.03.01.00 ZAPATAS
04.03.01.02 ACERO EN ZAPATAS fy=4200 kg/cm2 Kg 0.00 0.00 0.00 1446.00 0.00 0.00
Z-1 (2.00) Kg 1.00 9.00 5/8 24.40 - - - 219.60 - - - - - 341.00 - -
2.50 Kg 1.00 13.00 5/8 1.85 - - - 24.05 - - - - - 37.00 - -
2.80 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.80 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.80 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.80 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.50 Kg 1.00 13.00 5/8 1.85 - - - 24.05 - - - - - 37.00 - -
1.00 Kg 1.00 5.00 5/8 1.85 - - - 9.25 - - - - - 14.00 - -
Z-2 (1.20) Kg 1.00 5.00 5/8 22.65 - - - 113.25 - - - - - 176.00 - -
2.50 Kg 1.00 13.00 5/8 1.05 - - - 13.65 - - - - - 21.00 - -
2.80 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.80 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.80 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.80 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.50 Kg 1.00 13.00 5/8 1.05 - - - 13.65 - - - - - 21.00 - -
1.00 Kg 1.00 5.00 5/8 1.85 - - - 9.25 - - - - - 14.00 - -
Z-3 (0.90) Kg 4.00 4.00 5/8 7.25 - - - 116.00 - - - - - 180.00 - -
4.20 Kg 4.00 24.00 5/8 0.75 - - - 72.00 - - - - - 112.00 - -
Z-4 (0.80) Kg 3.00 4.00 5/8 9.00 - - - 108.00 - - - - - 168.00 - -
4.20 Kg 3.00 24.00 5/8 0.65 - - - 46.80 - - - - - 73.00 - -
04.03.02.00 VIGAS DE CIMENTACION
04.03.02.03 ACERO EN VIGAS DE CIMENTACIÓN: f'y = 4,200 kg/cm² Kg 0.00 1950.00 0.00 1989.00 0.00 0.00
VC (22.20) Kg 1.00 10.00 3/8 23.74 - 237.40 - - - - - 133.00 - - - -
Kg 1.00 6.00 5/8 23.74 - - - 142.44 - - - - - 221.00 - -
2.50 Kg 1.00 13.00 3/8 4.04 - 52.52 - - - - - 29.00 - - - -
2.80 Kg 1.00 14.00 3/8 4.04 - 56.56 - - - - - 32.00 - - - -
2.80 Kg 1.00 14.00 3/8 4.04 - 56.56 - - - - - 32.00 - - - -
2.80 Kg 1.00 14.00 3/8 4.04 - 56.56 - - - - - 32.00 - - - -
2.80 Kg 1.00 14.00 3/8 4.04 - 56.56 - - - - - 32.00 - - - -
2.50 Kg 1.00 13.00 3/8 4.04 - 52.52 - - - - - 29.00 - - - -
VC (22.20) Kg 1.00 10.00 3/8 23.74 - 237.40 - - - - - 133.00 - - - -
Kg 1.00 6.00 5/8 23.74 - - - 142.44 - - - - - 221.00 - -
2.50 Kg 1.00 13.00 3/8 4.04 - 52.52 - - - - - 29.00 - - - -
2.80 Kg 1.00 14.00 3/8 4.04 - 56.56 - - - - - 32.00 - - - -
2.80 Kg 1.00 14.00 3/8 4.04 - 56.56 - - - - - 32.00 - - - -
2.80 Kg 1.00 14.00 3/8 4.04 - 56.56 - - - - - 32.00 - - - -
2.80 Kg 1.00 14.00 3/8 4.04 - 56.56 - - - - - 32.00 - - - -
2.50 Kg 1.00 13.00 3/8 4.04 - 52.52 - - - - - 29.00 - - - -
VC (6.30) Kg 4.00 10.00 3/8 23.74 - 949.60 - - - - - 532.00 - - - -
Kg 4.00 6.00 5/8 23.74 - - - 569.76 - - - - - 884.00 - -
2.45 Kg 4.00 12.00 3/8 4.04 - 193.92 - - - - - 109.00 - - - -
2.45 Kg 4.00 12.00 3/8 4.04 - 193.92 - - - - - 109.00 - - - -
VC (6.30) Kg 3.00 10.00 3/8 23.74 - 712.20 - - - - - 399.00 - - - -
Kg 3.00 6.00 5/8 23.74 - - - 427.32 - - - - - 663.00 - -
5.30 Kg 3.00 24.00 3/8 4.04 - 290.88 - - - - - 163.00 - - - -
04.03.03.00 COLUMNAS
04.03.03.03 ACERO EN COLUMNAS fy=4200 kg/cm2 Kg 0.00 1848.00 280.00 2587.00 791.00 1287.00
C-1 Kg 3.00 6.00 1 10.12 - - - - - 182.16 - - - - - 724.00
Kg 3.00 10.00 5/8 10.12 - - - 303.60 - - - - - 471.00 - -
Kg 3.00 2.00 1/2 10.12 - - 60.72 - - - - - 60.00 - - -
3.15 Kg 3.00 34.00 3/8 2.02 - 206.04 - - - - - 115.00 - - - -
Kg 3.00 34.00 3/8 1.42 - 144.84 - - - - - 81.00 - - - -
2.30 Kg 3.00 28.00 3/8 2.02 - 169.68 - - - - - 95.00 - - - -
Kg 3.00 28.00 3/8 1.42 - 119.28 - - - - - 67.00 - - - -
C-2 Kg 2.00 4.00 1 10.12 - - - - - 80.96 - - - - - 322.00
Kg 2.00 2.00 3/4 10.12 - - - - 40.48 - - - - - 90.00 -
Kg 2.00 10.00 5/8 10.12 - - - 202.40 - - - - - 314.00 - -
Kg 2.00 2.00 1/2 10.12 - - 40.48 - - - - - 40.00 - - -
3.45 Kg 2.00 36.00 3/8 2.02 - 145.44 - - - - - 81.00 - - - -
Kg 2.00 36.00 3/8 1.42 - 102.24 - - - - - 57.00 - - - -
2.60 Kg 2.00 32.00 3/8 2.02 - 129.28 - - - - - 72.00 - - - -
Kg 2.00 32.00 3/8 1.42 - 90.88 - - - - - 51.00 - - - -
C-3 Kg 2.00 5.00 3/4 10.12 - - - - 101.20 - - - - - 226.00 -
Kg 2.00 6.00 5/8 10.12 - - - 121.44 - - - - - 188.00 - -
Kg 2.00 2.00 1/2 10.12 - - 40.48 - - - - - 40.00 - - -
3.45 Kg 2.00 36.00 3/8 1.37 - 98.64 - - - - - 55.00 - - - -
Kg 2.00 36.00 3/8 1.42 - 102.24 - - - - - 57.00 - - - -
2.60 Kg 2.00 32.00 3/8 1.37 - 87.68 - - - - - 49.00 - - - -
Kg 2.00 32.00 3/8 1.42 - 90.88 - - - - - 51.00 - - - -
C-4 Kg 3.00 2.00 1 10.12 - - - - - 60.72 - - - - - 241.00
Kg 3.00 3.00 3/4 10.12 - - - - 91.08 - - - - - 204.00 -
Kg 3.00 10.00 5/8 10.12 - - - 303.60 - - - - - 471.00 - -
Kg 3.00 2.00 1/2 10.12 - - 60.72 - - - - - 60.00 - - -
3.15 Kg 3.00 34.00 3/8 2.02 - 206.04 - - - - - 115.00 - - - -
Kg 3.00 34.00 3/8 1.42 - 144.84 - - - - - 81.00 - - - -
2.30 Kg 3.00 28.00 3/8 2.02 - 169.68 - - - - - 95.00 - - - -
Kg 3.00 28.00 3/8 1.42 - 119.28 - - - - - 67.00 - - - -
C-5 Kg 2.00 6.00 3/4 10.12 - - - - 121.44 - - - - - 271.00 -
Kg 2.00 10.00 5/8 10.12 - - - 202.40 - - - - - 314.00 - -
Kg 2.00 2.00 1/2 10.12 - - 40.48 - - - - - 40.00 - - -
3.45 Kg 2.00 36.00 3/8 2.02 - 145.44 - - - - - 81.00 - - - -
Kg 2.00 36.00 3/8 1.42 - 102.24 - - - - - 57.00 - - - -
2.60 Kg 2.00 32.00 3/8 2.02 - 129.28 - - - - - 72.00 - - - -
Kg 2.00 32.00 3/8 1.42 - 90.88 - - - - - 51.00 - - - -
C-6 Kg 2.00 11.00 5/8 10.12 - - - 222.64 - - - - - 346.00 - -
Kg 2.00 2.00 1/2 10.12 - - 40.48 - - - - - 40.00 - - -
3.45 Kg 2.00 36.00 3/8 1.37 - 98.64 - - - - - 55.00 - - - -
Kg 2.00 36.00 3/8 1.42 - 102.24 - - - - - 57.00 - - - -
2.60 Kg 2.00 32.00 3/8 1.37 - 87.68 - - - - - 49.00 - - - -
Kg 2.00 32.00 3/8 1.42 - 90.88 - - - - - 51.00 - - - -
C-7 Kg 2.00 6.00 5/8 11.11 - - - 133.32 - - - - - 207.00 - -
3.45 Kg 2.00 36.00 3/8 1.22 - 87.84 - - - - - 49.00 - - - -
2.60 Kg 2.00 32.00 3/8 1.22 - 78.08 - - - - - 44.00 - - - -
C-8 Kg 2.00 8.00 5/8 11.11 - - - 177.76 - - - - - 276.00 - -
3.45 Kg 2.00 36.00 3/8 1.22 - 87.84 - - - - - 49.00 - - - -
2.60 Kg 2.00 32.00 3/8 1.22 - 78.08 - - - - - 44.00 - - - -
04.03.04.00 COLUMNETAS
Nº DE ELEMENTOS
12/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"Nº DE
ELEMENTOS
04.03.04.03 ACERO EN COLUMNETAS fy=4200 kg/cm2 Kg 111.00 287.00 0.00 0.00 0.00 0.00
C-9 Kg 24.00 4.00 3/8 2.18 - 209.28 - - - - - 117.00 - - - -
Kg 24.00 4.00 3/8 2.73 - 262.08 - - - - - 147.00 - - - -
1.38 Kg 24.00 10.00 1/4 0.79 189.60 - - - - - 42.00 - - - - -
1.93 Kg 24.00 14.00 1/4 0.79 265.44 - - - - - 58.00 - - - - -
C-9 (Pasadiso) Kg 9.00 4.00 3/8 1.15 - 41.40 - - - - - 23.00 - - - -
0.90 Kg 9.00 7.00 1/4 0.79 49.77 - - - - - 11.00 - - - - -
04.03.05.00 VIGAS
04.03.05.03 ACERO EN VIGAS fy=4200 kg/cm2 Kg 0.00 1368.00 1269.00 866.00 278.00 300.00
1° NIVEL
VP-101 Kg 2.00 2.00 5/8 8.39 - - - 33.56 - - - - - 52.00 - -
Kg 2.00 2.00 5/8 6.59 - - - 26.36 - - - - - 41.00 - -
Kg 2.00 1.00 3/4 3.70 - - - - 7.40 - - - - - 17.00 -
Kg 2.00 2.00 5/8 3.26 - - - 13.03 - - - - - 20.00 - -
Kg 2.00 2.00 3/8 0.46 - 1.82 - - - - - 1.00 - - - -
2.45 Kg 2.00 18.00 3/8 1.02 - 36.72 - - - - - 21.00 - - - -
2.45 Kg 2.00 18.00 3/8 1.02 - 36.72 - - - - - 21.00 - - - -
1.75 Kg 2.00 13.00 3/8 1.14 - 29.74 - - - - - 17.00 - - - -
VP-102 Kg 2.00 3.00 5/8 8.39 - - - 50.34 - - - - - 78.00 - -
Kg 2.00 2.00 5/8 6.59 - - - 26.36 - - - - - 41.00 - -
Kg 2.00 2.00 3/4 3.70 - - - - 14.80 - - - - - 33.00 -
Kg 2.00 2.00 5/8 3.26 - - - 13.03 - - - - - 20.00 - -
Kg 2.00 2.00 3/8 0.46 - 1.82 - - - - - 1.00 - - - -
2.45 Kg 2.00 18.00 3/8 1.02 - 36.72 - - - - - 21.00 - - - -
2.45 Kg 2.00 18.00 3/8 1.02 - 36.72 - - - - - 21.00 - - - -
1.75 Kg 2.00 13.00 3/8 1.14 - 29.74 - - - - - 17.00 - - - -
VP-103 Kg 3.00 3.00 1 8.39 - - - - - 75.51 - - - - - 300.00
Kg 3.00 3.00 3/4 7.04 - - - - 63.36 - - - - - 142.00 -
Kg 3.00 2.00 1/2 6.24 - - 37.44 - - - - - 37.00 - - -
Kg 3.00 3.00 3/4 3.41 - - - - 30.67 - - - - - 69.00 -
Kg 3.00 2.00 3/8 0.46 - 2.73 - - - - - 2.00 - - - -
5.30 Kg 3.00 49.00 3/8 1.02 - 149.94 - - - - - 84.00 - - - -
1.75 Kg 3.00 13.00 3/8 1.14 - 44.62 - - - - - 25.00 - - - -
VS-104 Kg 2.00 4.00 1/2 23.54 - - 188.32 - - - - - 187.00 - - -
Kg 2.00 4.00 1/2 2.15 - - 17.16 - - - - - 17.00 - - -
Kg 2.00 10.00 1/2 3.30 - - 66.00 - - - - - 66.00 - - -
2.78 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.75 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.75 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.75 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.75 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.78 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
VA Kg 1.00 4.00 1/2 23.35 - - 93.40 - - - - - 93.00 - - -
3.43 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.40 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.40 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.40 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.40 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.43 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
NIVEL INTERMEDIO
VIGA DE ARRIOSTRE Kg 4.00 4.00 1/2 6.74 - - 107.84 - - - - - 107.00 - - -
2.45 Kg 4.00 17.00 3/8 1.02 - 69.36 - - - - - 39.00 - - - -
2.45 Kg 4.00 17.00 3/8 1.02 - 69.36 - - - - - 39.00 - - - -
TECHO
VS-204 Kg 2.00 2.00 1/2 24.94 - - 99.76 - - - - - 99.00 - - -
Kg 2.00 2.00 1/2 23.54 - - 94.16 - - - - - 94.00 - - -
Kg 2.00 2.00 1/2 2.35 - - 9.40 - - - - - 9.00 - - -
0.80 Kg 2.00 5.00 3/8 0.86 - 8.62 - - - - - 5.00 - - - -
2.78 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.75 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.75 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.75 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.75 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.78 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
0.80 Kg 2.00 5.00 3/8 0.86 - 8.62 - - - - - 5.00 - - - -
VA Kg 2.00 4.00 1/2 23.35 - - 186.80 - - - - - 186.00 - - -
0.80 Kg 2.00 6.00 3/8 0.75 - 9.00 - - - - - 5.00 - - - -
3.43 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.40 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.40 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.40 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.40 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.43 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
0.80 Kg 2.00 6.00 3/8 0.75 - 9.00 - - - - - 5.00 - - - -
VA-2 Kg 4.00 4.00 1/2 5.71 - - 91.30 - - - - - 91.00 - - -
1.95 Kg 4.00 14.00 3/8 0.75 - 42.00 - - - - - 24.00 - - - -
2.65 Kg 4.00 17.00 3/8 0.75 - 51.00 - - - - - 29.00 - - - -
V-201 (Frontal) Kg 2.00 2.00 5/8 7.08 - - - 28.32 - - - - - 44.00 - -
Kg 2.00 1.00 3/4 3.91 - - - - 7.81 - - - - - 17.00 -
Kg 2.00 2.00 5/8 4.88 - - - 19.51 - - - - - 30.00 - -
Kg 2.00 2.00 5/8 2.93 - - - 11.73 - - - - - 18.00 - -
3.18 Kg 2.00 28.00 3/8 1.02 - 57.12 - - - - - 32.00 - - - -
2.11 Kg 2.00 17.00 3/8 1.20 - 40.80 - - - - - 23.00 - - - -
V-201 (Posterior) Kg 2.00 2.00 5/8 6.03 - - - 24.11 - - - - - 37.00 - -
Kg 2.00 2.00 5/8 4.95 - - - 19.82 - - - - - 31.00 - -
Kg 2.00 2.00 1/2 2.50 - - 10.02 - - - - - 10.00 - - -
3.21 Kg 2.00 28.00 3/8 1.02 - 57.12 - - - - - 32.00 - - - -
0.78 Kg 2.00 6.00 3/8 1.20 - 14.40 - - - - - 8.00 - - - -
V-202 (Frontal) Kg 2.00 2.00 5/8 7.08 - - - 28.32 - - - - - 44.00 - -
Kg 2.00 1.00 5/8 3.91 - - - 7.81 - - - - - 12.00 - -
Kg 2.00 2.00 5/8 4.88 - - - 19.51 - - - - - 30.00 - -
Kg 2.00 2.00 5/8 2.93 - - - 11.73 - - - - - 18.00 - -
3.18 Kg 2.00 28.00 3/8 1.02 - 57.12 - - - - - 32.00 - - - -
2.11 Kg 2.00 17.00 3/8 1.20 - 40.80 - - - - - 23.00 - - - -
V-202 (Posterior) Kg 2.00 2.00 5/8 6.03 - - - 24.11 - - - - - 37.00 - -
Kg 2.00 2.00 5/8 4.95 - - - 19.82 - - - - - 31.00 - -
Kg 2.00 2.00 1/2 2.50 - - 10.02 - - - - - 10.00 - - -
3.21 Kg 2.00 28.00 3/8 1.02 - 57.12 - - - - - 32.00 - - - -
0.78 Kg 2.00 6.00 3/8 1.20 - 14.40 - - - - - 8.00 - - - -
V-203 (Frontal) Kg 3.00 2.00 5/8 7.20 - - - 43.18 - - - - - 67.00 - -
Kg 3.00 2.00 5/8 4.13 - - - 24.76 - - - - - 38.00 - -
Kg 3.00 2.00 5/8 5.06 - - - 30.36 - - - - - 47.00 - -
13/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 1
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"Nº DE
ELEMENTOS
Kg 3.00 2.00 5/8 2.95 - - - 17.67 - - - - - 27.00 - -
3.31 Kg 3.00 27.00 3/8 1.02 - 82.62 - - - - - 46.00 - - - -
2.11 Kg 3.00 17.00 3/8 1.20 - 61.20 - - - - - 34.00 - - - -
V-203 (Posterior) Kg 3.00 2.00 5/8 6.03 - - - 36.18 - - - - - 56.00 - -
Kg 3.00 2.00 5/8 5.01 - - - 30.08 - - - - - 47.00 - -
Kg 3.00 2.00 1/2 2.50 - - 15.02 - - - - - 15.00 - - -
3.34 Kg 3.00 27.00 3/8 1.02 - 82.62 - - - - - 46.00 - - - -
0.78 Kg 3.00 6.00 3/8 1.20 - 21.60 - - - - - 12.00 - - - -
VIGA CORONA Kg 1.00 10.00 1/2 24.95 - - 249.50 - - - - - 248.00 - - -
0.80 Kg 1.00 3.00 3/8 2.33 - 6.99 - - - - - 4.00 - - - -
3.43 Kg 1.00 17.00 3/8 2.33 - 39.61 - - - - - 22.00 - - - -
3.40 Kg 1.00 16.00 3/8 2.33 - 37.28 - - - - - 21.00 - - - -
3.40 Kg 1.00 16.00 3/8 2.33 - 37.28 - - - - - 21.00 - - - -
3.40 Kg 1.00 16.00 3/8 2.33 - 37.28 - - - - - 21.00 - - - -
3.40 Kg 1.00 16.00 3/8 2.33 - 37.28 - - - - - 21.00 - - - -
3.43 Kg 1.00 17.00 3/8 2.33 - 39.61 - - - - - 22.00 - - - -
0.80 Kg 1.00 3.00 3/8 2.33 - 6.99 - - - - - 4.00 - - - -
04.03.06.00 VIGAS DE AMARRE
04.03.06.03 ACERO EN VIGAS DE AMARRE fy=4200 kg/cm2 Kg 12.00 99.00 0.00 0.00 0.00 0.00
VA Kg 8.00 2.00 3/8 3.08 - 49.28 - - - - - 28.00 - - - -
Kg 16.00 2.00 3/8 3.05 - 97.60 - - - - - 55.00 - - - -
2.23 Kg 8.00 11.00 1/4 0.21 18.48 - - - - - 4.00 - - - - -
2.20 Kg 16.00 10.00 1/4 0.21 33.60 - - - - - 7.00 - - - - -
VA (Pasadiso) Kg 9.00 2.00 3/8 1.61 - 28.98 - - - - - 16.00 - - - -
0.76 Kg 9.00 3.00 1/4 0.21 5.67 - - - - - 1.00 - - - - -
04.03.07.00 LOSA ALIGERADA
04.03.07.03 ACERO EN LOSA ALIGERADA fy=4200 kg/cm2 Kg 340.00 0.00 2276.00 0.00 0.00 0.00
Aulas As (-) Kg 14.00 2.00 1/2 1.58 - - 44.10 - - - - - 44.00 - - -
Kg 14.00 5.00 1/2 2.65 - - 185.50 - - - - - 184.00 - - -
Aulas As (+) Kg 14.00 2.00 1/2 23.15 - - 648.20 - - - - - 644.00 - - -
Voladizo As (-) Kg 4.00 2.00 1/2 1.58 - - 12.60 - - - - - 13.00 - - -
Kg 4.00 3.00 1/2 2.65 - - 31.80 - - - - - 32.00 - - -
Voladizo As (+) Kg 4.00 2.00 1/2 23.15 - - 185.20 - - - - - 184.00 - - -
As Temperatura Kg 6.00 13.00 1/4 8.45 659.10 - - - - - 145.00 - - - - -
Aulas As (-) Kg 12.00 2.00 1/2 2.38 - - 57.00 - - - - - 57.00 - - -
Kg 12.00 5.00 1/2 2.65 - - 159.00 - - - - - 158.00 - - -
Aulas As (+) Kg 12.00 2.00 1/2 24.75 - - 594.00 - - - - - 590.00 - - -
Voladizo As (-) Kg 6.00 2.00 1/2 2.38 - - 28.50 - - - - - 28.00 - - -
Kg 6.00 3.00 1/2 2.65 - - 47.70 - - - - - 47.00 - - -
Voladizo As (+) Kg 6.00 2.00 1/2 24.75 - - 297.00 - - - - - 295.00 - - -
As Temperatura Kg 7.00 13.00 1/4 9.75 887.25 - - - - - 195.00 - - - - -
04.03.08.00 ESCALERA
04.03.08.03 ACERO EN ESCALERA fy = 4,200 kg/cm2 Kg 0.00 0.00 0.00 0.00 0.00 0.00
04.03.09.00 MURO INTERMEDIO DE ESCALERA
04.03.09.03 ACERO EN MURO INTERMEDIO DE ESCALERA fy=4200 kg/cm2 Kg 0.00 0.00 0.00 0.00 0.00 0.00
04.03.10.00 GARGOLAS
04.03.10.03 ACERO EN GARGOLAS fy=4200 kg/cm2 Kg 0.72 0.00 0.00 0.00 0.00 0.00
Kg 2.00 2.00 1/4 0.46 1.85 - - - - - 0.41 - - - - -
Kg 2.00 2.00 1/4 0.35 1.40 - - - - - 0.31 - - - - -
04.03.11.00 MESON PARA LAVATORIOS OVALINES
04.03.11.03 ACERO EN MESON fy=4200 kg/cm2 Kg 0.00 0.00 0.00 0.00 0.00 0.00
14/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
04.01.00.00 MOVIMIENTO DE TIERRAS
04.01.01.00 EXCAVACIONES DE ZANJAS EN ZAPATAS-CIMIENTOS CORRIDOS 258.24
Exc. Zapatas
Zapatas (Z-1) 1.00 1.00 41.80 2.00 1.40 117.04
Zapatas (Z-2) 1.00 1.00 41.80 1.20 1.40 70.22
Zapatas (Z-3) 6.00 1.00 4.23 0.90 1.40 31.94
Zapatas (Z-4) 3.00 1.00 4.23 0.80 1.40 14.20
Zapatas (Z-5) 2.00 1.00 4.23 1.20 1.40 14.20
Zapatas (Z-6) 1.00 1.00 4.23 1.00 1.40 5.92
Cimientos 1.00 1.00 2.45 0.50 0.80 0.98
1.00 1.00 1.80 0.50 0.80 0.72
1.00 1.00 1.55 0.50 0.80 0.62
1.00 1.00 0.93 0.50 0.80 0.37
ESCALERA 1.00 1.00 1.33 0.50 1.20 0.80
1.00 1.00 3.08 0.50 0.80 1.23
04.01.02.00 RELLENO COMPACTADO DE MATERIAL PROPIO, C/EQUIPO 103.34
Volumen de Excavación 258.24
Volumen de Concreto 154.90
Volumen de Concreto de Solado 18.11
Volumen de Concreto de Zapata 108.65
Volumen de Concreto de Viga de Cimentación 28.14
04.01.03.00 RELLENO COMPACTADO DE MATERIAL DE PRESTAMO, ARENILLA, C/EQUIPO 57.88
EJE 1-1 4.00 1.00 3.42 0.60 0.65 5.34
4.00 1.00 3.40 0.60 0.65 5.30
1.00 1.00 2.05 0.60 0.65 0.80
1.00 1.00 3.05 0.60 0.65 1.19
1.00 1.00 3.80 0.60 0.65 1.48
EJE 3-3 4.00 1.00 3.42 0.98 0.65 8.67
4.00 1.00 3.40 0.98 0.65 8.62
1.00 1.00 2.05 0.98 0.65 1.30
1.00 1.00 3.05 0.98 0.65 1.93
1.00 1.00 3.80 0.98 0.65 2.41
EJE CON MUROS 8.00 1.00 4.23 0.65 0.65 14.28
1.00 1.00 4.23 0.75 0.65 2.06
EJES SIN MUROS 3.00 1.00 4.20 0.55 0.65 4.50
04.01.04.00 RELLENO COMPACTADO DE MATERIAL DE PRESTAMO, AFIRMADO, C/EQUIPO 22.73
CUBICULO DE LIMPIEZA 1.00 1.00 3.43 2.80 0.10 0.96
SS.HH PERS.MASCULINO 1.00 1.00 3.05 1.64 0.10 0.50
SS.HH PERS.FEMENINO 1.00 1.00 3.05 1.64 0.10 0.50
SS.HH. NIÑOS 1.00 1.00 2.94 2.80 0.10 0.82
1.00 1.00 3.20 2.15 0.10 0.69
1.00 1.00 3.40 3.05 0.10 1.04
SS.HH.NIÑAS 1.00 1.00 6.00 1.93 0.10 1.16
1.00 1.00 3.05 1.48 0.10 0.45
SS.HH.DISCAPACITADO 1.00 1.00 2.80 1.90 0.10 0.53
DEPOSITO 1.00 1.00 6.00 3.43 0.10 2.05
SALA DE USOS MULTIPLES 1.00 1.00 14.40 6.00 0.10 8.64
GUARDIANIA 1.00 1.00 6.00 2.05 0.10 1.23
DIRECCION 1.00 1.00 6.00 3.05 0.10 1.83
ESCALERA 1.00 1.00 6.15 3.80 0.10 2.34
04.01.05.00 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 258.24
04.01.06.00 ELIMINACION MATERIAL EXCEDENTE 170.39
Volumen de Excavación 258.24
Volumen de Relleno Compactado con Material Propio 103.34
Factor de Esponjamiento 1.10
04.02.00.00 CONCRETO SIMPLE
04.02.01.00 SOLADO e=4" PARA ZAPATAS Y VIGAS DE CIMENTACION f'c=100 kg/cm2 M² 181.09
Zapatas
Zapatas (Z-1) 1.00 1.00 41.80 2.00 83.60
Zapatas (Z-2) 1.00 1.00 41.80 1.20 50.16
Zapatas (Z-3) 6.00 1.00 4.23 0.90 22.82
Zapatas (Z-4) 3.00 1.00 4.23 0.80 10.14
Zapatas (Z-5) 2.00 1.00 4.23 1.20 10.14
CANT.REP.
N°ELEM.
M³
M³M³M³M³M³M³M³M³M³M³M³M³
M³
M³
M³
M³M³M³
M³
M³M³M³M³M³M³M³M³M³M³M³M³M³
M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³
M³
M³
M³M³
M³M³M³M³M³
15/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
Zapatas (Z-6) 1.00 1.00 4.23 1.00 4.23
04.02.02.00 CONCRETO EN CIMIENTOS CORRIDOS f'c=120 kg/cm2 + 30% P.G. 6.54
1.00 2.00 1.64 0.50 0.80 1.31
1.00 1.00 2.70 0.50 0.80 1.08
1.00 1.00 2.60 0.50 0.80 1.04
1.00 1.00 0.85 0.50 0.80 0.34
1.00 1.00 1.33 0.50 0.80 0.53
1.00 1.00 2.60 0.50 0.80 1.04
1.00 1.00 3.00 0.50 0.80 1.20
04.02.03.00 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS CORRIDOS M² 26.40
1.00 4.00 1.64 0.80 5.24
1.00 2.00 2.70 0.80 4.32
1.00 2.00 2.60 0.80 4.16
1.00 2.00 0.85 0.80 1.36
1.00 2.00 1.33 0.80 2.12
1.00 2.00 2.60 0.80 4.16
1.00 2.00 3.15 0.80 5.04
04.02.04.00 CONCRETO EN SOBRECIMIENTOS f'c=120 kg/cm2 + 25% P.M. 9.26
PRIMER NIVELEJE O -O (1-2) 1.00 1.00 1.33 0.25 0.25 0.08EJE O O (2-3) 1.00 1.00 2.10 0.25 0.25 0.13EJE N-N ( 1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE N-N(2-3) 1.00 1.00 2.45 0.25 0.25 0.15
EJE M-M(1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE L -L(1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE L -L(2-3) 1.00 1.00 2.45 0.25 0.25 0.15
EJE K"K"(1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE K' -K"(2-3) 1.00 1.00 2.45 0.25 0.25 0.15
EJE K -K(1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE K-K(2-3) 1.00 1.00 2.45 0.25 0.25 0.15
EJE G-G (1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE G-G(-2-3) 1.00 1.00 1.65 0.25 0.25 0.10
EJE F -F(1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE F-F(2-3) 1.00 1.00 2.45 0.25 0.25 0.15
1.00 1.00 2.45 0.25 0.25 0.15
1.00 1.00 2.45 0.25 0.25 0.15
EJE E -E(1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE E-E(2-3) 1.00 1.00 2.45 0.25 0.25 0.15
EJE D-D (1-2) 1.00 1.00 2.45 0.25 0.25 0.15
EJE D-D (2-3) 1.00 1.00 2.45 0.25 0.25 0.15
PRIMER NIVEL
EJE 1 (O-N) 1.00 1.00 2.23 0.15 0.25 0.08
EJE 1 (N-M) 1.00 1.00 1.58 0.15 0.25 0.06
EJE 1 (M-L) 1.00 1.00 2.20 0.15 0.25 0.08
EJE 1 (L-K") 1.00 1.00 2.23 0.15 0.25 0.08
EJE 1 (K-J) 1.00 1.00 2.23 0.15 0.25 0.08
EJE 1 (J-I) 1.00 1.00 2.20 0.15 0.25 0.08
EJE 1 (I-H) 1.00 1.00 2.20 0.15 0.25 0.08
EJE 1 (H-G) 1.00 1.00 2.23 0.15 0.25 0.08
EJE 1 (G-F) 1.00 1.00 1.50 0.15 0.25 0.06
EJE 1 (F-E") 1.00 1.00 1.85 0.15 0.25 0.07
EJE 1 (E-D) 1.00 1.00 3.25 0.15 0.25 0.12
SS.HH. DE PERSONAL 1.00 1.00 2.75 0.15 1.15 0.47
1.00 2.00 1.64 0.15 1.15 0.56
SS.HH. DE NIÑOS Y NIÑAS 1.00 1.00 2.60 0.15 1.15 0.45
1.00 1.00 0.85 0.15 1.15 0.15
2.00 2.00 1.60 0.15 1.15 1.10
2.00 1.00 0.35 0.15 1.15 0.12
2.00 2.00 1.75 0.15 1.15 1.21
2.00 2.00 0.15 0.15 1.15 0.10
1.00 1.00 2.70 0.15 1.15 0.47
1.00 1.00 1.33 0.15 1.15 0.23
EJE 3 (N-M) 1.00 1.00 1.03 0.15 0.25 0.04
EJE 3 (L-K) 1.00 1.00 1.25 0.15 0.25 0.05
EJE 3 (K--J) 1.00 1.00 1.25 0.15 0.25 0.05
EJE 3(J-I) 1.00 1.00 2.20 0.15 0.25 0.08
EJE 3 (I-H) 1.00 1.00 2.20 0.15 0.25 0.08
EJE 3 (H-G) 1.00 1.00 1.25 0.15 0.25 0.05
M³
M³
M³M³M³M³M³M³M³
M³M³M³M³M³M³M³
M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
EJE E'-E" (1-2) M³EJE E'-E" (2-3) M³
M³M³M³M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
16/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
EJE (G-F) 1.00 1.00 1.50 0.15 0.25 0.06
EJE 3 (F-E") 1.00 1.00 0.88 0.15 0.25 0.03
04.02.05.00 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS M² 87.19
PRIMER NIVELEJE O -O (1-2) 1.00 2.00 1.33 0.25 0.66EJE O O (2-3) 1.00 2.00 2.10 0.25 1.05EJE N-N ( 1-2) 1.00 2.00 2.45 0.25 1.23
EJE N-N(2-3) 1.00 2.00 2.45 0.25 1.23
EJE M-M(1-2) 1.00 2.00 2.45 0.25 1.23
EJE L -L(1-2) 1.00 2.00 2.45 0.25 1.23
EJE L -L(2-3) 1.00 2.00 2.45 0.25 1.23
EJE K"K"(1-2) 1.00 2.00 2.45 0.25 1.23
EJE K' -K"(2-3) 1.00 2.00 2.45 0.25 1.23
EJE K -K(1-2) 1.00 2.00 2.45 0.25 1.23
EJE K-K(2-3) 1.00 2.00 2.45 0.25 1.23
EJE G-G (1-2) 1.00 2.00 2.45 0.25 1.23
EJE G-G(-2-3) 1.00 2.00 1.65 0.25 0.83
EJE F -F(1-2) 1.00 2.00 2.45 0.25 1.23
EJE F-F(2-3) 1.00 2.00 2.45 0.25 1.23
1.00 2.00 2.45 0.25 1.23
1.00 2.00 2.45 0.25 1.23
EJE E -E(1-2) 1.00 2.00 2.45 0.25 1.23
EJE E-E(2-3) 1.00 2.00 2.45 0.25 1.23
EJE D-D (1-2) 1.00 2.00 2.45 0.25 1.23
EJE D-D (2-3) 1.00 2.00 2.45 0.25 1.23
PRIMER NIVEL
EJE 1 (O-N) 1.00 2.00 2.23 0.25 1.11
EJE 1 (N-M) 1.00 2.00 1.58 0.25 0.79
EJE 1 (M-L) 1.00 2.00 2.20 0.25 1.10
EJE 1 (L-K") 1.00 2.00 2.23 0.25 1.11
EJE 1 (K-J) 1.00 2.00 2.23 0.25 1.11
EJE 1 (J-I) 1.00 2.00 2.20 0.25 1.10
EJE 1 (I-H) 1.00 2.00 2.20 0.25 1.10
EJE 1 (H-G) 1.00 2.00 2.23 0.25 1.11
EJE 1 (G-F) 1.00 2.00 1.50 0.25 0.75
EJE 1 (F-E") 1.00 2.00 1.85 0.25 0.93
EJE 1 (E-D) 1.00 2.00 3.25 0.25 1.63
SS.HH. DE PERSONAL 1.00 2.00 2.75 1.15 6.32
1.00 2.00 1.64 1.15 3.77
SS.HH. DE NIÑOS Y NIÑAS 1.00 2.00 2.60 1.15 5.98
1.00 2.00 0.85 1.15 1.95
2.00 2.00 1.60 1.15 7.36
2.00 2.00 0.35 1.15 1.61
2.00 2.00 1.75 1.15 8.05
2.00 2.00 0.15 1.15 0.69
1.00 2.00 2.70 1.15 6.21
1.00 2.00 1.33 1.15 3.05
EJE 3 (N-M) 1.00 2.00 1.03 0.25 0.51
EJE 3 (L-K) 1.00 2.00 1.25 0.25 0.63
EJE 3 (K--J) 1.00 2.00 1.25 0.25 0.63
EJE 3(J-I) 1.00 2.00 2.20 0.25 1.10
EJE 3 (I-H) 1.00 2.00 2.20 0.25 1.10
EJE 3 (H-G) 1.00 2.00 1.25 0.25 0.63
EJE (G-F) 1.00 2.00 1.50 0.25 0.75
EJE 3 (F-E") 1.00 2.00 0.88 0.25 0.44
04.02.06.00 FALSO PISO f'c=140 kg/cm2 M² 22.73
CUBICULO DE LIMPIEZA 1.00 1.00 3.43 2.80 0.10 0.96
SS.HH PERS.MASCULINO 1.00 1.00 3.05 1.64 0.10 0.50
SS.HH PERS.FEMENINO 1.00 1.00 3.05 1.64 0.10 0.50
SS.HH. NIÑOS 1.00 1.00 2.94 2.80 0.10 0.82
1.00 1.00 3.20 2.15 0.10 0.69
1.00 1.00 3.40 3.05 0.10 1.04
SS.HH.NIÑAS 1.00 1.00 6.00 1.93 0.10 1.16
1.00 1.00 3.05 1.48 0.10 0.45
SS.HH.DISCAPACITADO 1.00 1.00 2.80 1.90 0.10 0.53
DEPOSITO 1.00 1.00 6.00 3.43 0.10 2.05
SALA DE USOS MULTIPLES 1.00 1.00 14.40 6.00 0.10 8.64
GUARDIANIA 1.00 1.00 6.00 2.05 0.10 1.23
DIRECCION 1.00 1.00 6.00 3.05 0.10 1.83
ESCALERA 1.00 1.00 6.15 3.80 0.10 2.34
M³M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
EJE E'-E" (1-2) M³EJE E'-E" (2-3) M³
M³M³M³M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³
17/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
04.03.00.00 CONCRETO ARMADO
04.03.01.00 ZAPATAS
04.03.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 108.65
Exc. Zapatas
Exc. Zapatas
Zapatas (Z-1) 1.00 1.00 41.80 2.00 0.60 50.16
Zapatas (Z-2) 1.00 1.00 41.80 1.20 0.60 30.10
Zapatas (Z-3) 6.00 1.00 4.23 0.90 0.60 13.69
Zapatas (Z-4) 3.00 1.00 4.23 0.80 0.60 6.08
Zapatas (Z-5) 2.00 1.00 4.23 1.20 0.60 6.08
Zapatas (Z-6) 1.00 1.00 4.23 1.00 0.60 2.54
04.03.01.02 ACERO EN ZAPATAS fy=4200 kg/cm2 Kg 2,187.00
04.03.02.00 VIGAS DE CIMENTACION
04.03.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 kg/cm2 62.31
Eje 1-1 1.00 1.00 39.80 0.25 1.55 15.42
Eje 3-3 1.00 1.00 39.80 0.25 1.55 15.42
Eje Verticales 14.00 1.00 5.80 0.25 1.55 31.47
04.03.02.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS DE CIMENTACION M² 462.52
Eje A-A M² 1.00 2.00 39.80 1.55 123.38
Eje C-C M² 1.00 2.00 39.80 1.55 123.38
Eje Verticales M² 12.00 2.00 5.80 1.55 215.76
04.03.02.03 ACERO EN VIGAS DE CIMENTACION fy=4200 kg/cm2 Kg 4,363.00
04.03.03.00 COLUMNAS
04.03.03.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 44.82
EJE 1-1; COLUMNAS TIPO "L" 6.00 1.00 0.50 0.25 6.88 5.16
6.00 1.00 0.33 0.15 6.88 2.04
EJE 3-3; COLUMNAS TIPO "L" 6.00 1.00 0.50 0.25 6.88 5.16
6.00 1.00 0.33 0.15 6.88 2.04
EJE 1-1; COLUMNAS TIPO "T" 6.00 1.00 0.90 0.15 6.88 5.57
6.00 1.00 0.35 0.25 6.88 3.61
EJE 3-3; COLUMNAS TIPO "T" 5.00 1.00 0.90 0.15 6.88 4.64
5.00 1.00 0.35 0.25 6.88 3.01
EJE 2-2; COLUMNAS TIPO RECTANGULAR 11.00 1.00 0.40 0.25 7.71 8.48
C-9 6.00 1.00 0.25 0.15 3.10 0.70
C-10 4.00 1.00 0.50 0.25 6.88 3.44
C-11 1.00 1.00 0.18 0.15 3.10 0.08
C-12 1.00 1.00 0.78 0.15 3.10 0.36
1.00 1.00 0.20 0.15 3.10 0.09
OTROS 1.00 1.00 0.35 0.15 3.10 0.16
1.00 1.00 0.60 0.15 3.10 0.28
04.03.03.02 ENCOFRADO Y DESCENCOFRADO DE COLUMNAS M² 435.93
COLUMNA EN EJE 1-1:O-O ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 1.08 6.88 7.39
1.00 1.00 0.15 3.18 0.48
1.00 1.00 0.15 3.18 0.48
1.00 1.00 0.43 3.10 1.32
1.00 1.00 0.43 3.10 1.32
M² 1.00 1.00 0.25 3.20 0.80
1.00 1.00 0.25 3.30 0.83
COLUMNA EN EJE 1-1:K'-K';1-1:K-K;1-1:E'-E' ( PRIMER Y SEGUNDO NIVEL ) 3.00 1.00 0.58 6.88 11.86
M² 3.00 1.00 0.15 3.18 1.43
3.00 1.00 0.15 3.18 1.43
M² 3.00 1.00 0.43 3.10 3.95
3.00 1.00 0.43 3.10 3.95
M² 3.00 1.00 0.25 3.20 2.40
3.00 1.00 0.25 3.30 2.47
COLUMNA EN EJE 1-1:G-G;1-1:F-F ( PRIMER Y SEGUNDO NIVEL ) 2.00 1.00 0.58 6.88 7.91
M² 2.00 1.00 0.15 3.18 0.95
2.00 1.00 0.15 3.18 0.95
M² 2.00 1.00 0.43 3.10 2.64
2.00 1.00 0.43 3.10 2.64
M² 2.00 1.00 0.25 3.20 1.60
2.00 1.00 0.25 3.30 1.65
M³
M³M³M³M³M³M³
M³
M³M³M³
M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
M²M²M²M²M²
M²M²
M²
M²
M²M²
M²
M²
M²
18/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
2.00 1.00 0.25 3.20 1.60
2.00 1.00 0.25 3.30 1.65
1.00 1.00 0.25 2.80 0.70
COLUMNA EN EJE 3-3:O-O ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.50 6.88 3.44
M² 1.00 1.00 0.25 3.00 0.75
1.00 1.00 0.33 3.30 1.07
M² 1.00 1.00 0.25 2.90 0.73
1.00 1.00 0.33 3.20 1.04
M² 1.00 1.00 0.58 3.10 1.78
1.00 1.00 0.58 3.10 1.78
M² 1.00 1.00 0.25 3.20 0.80
1.00 1.00 0.25 3.30 0.83
COLUMNA EN EJE 3-3:K'-K';3-3:K-K;3-3:E'-E' ( PRIMER Y SEGUNDO NIVEL ) M² 3.00 1.00 0.25 3.00 2.25
3.00 1.00 0.33 3.30 3.22
M² 3.00 1.00 0.25 2.90 2.18
3.00 1.00 0.33 3.20 3.12
M² 3.00 1.00 0.15 3.10 1.39
3.00 1.00 0.15 3.10 1.39
M² 3.00 1.00 0.43 3.10 3.95
3.00 1.00 0.43 3.10 3.95
M² 3.00 1.00 0.25 3.20 2.40
3.00 1.00 0.25 3.30 2.47
COLUMNA EN EJE 3-3:G-G;3-3:F-F ( PRIMER Y SEGUNDO NIVEL ) M² 2.00 1.00 0.25 3.00 1.50
2.00 1.00 0.33 3.30 2.15
M² 2.00 1.00 0.25 2.90 1.45
2.00 1.00 0.33 3.20 2.08
M² 1.00 2.00 0.15 3.10 0.93
1.00 2.00 0.15 3.10 0.93
M² 2.00 1.00 0.43 3.10 2.64
2.00 1.00 0.43 3.10 2.64
M² 2.00 1.00 0.25 3.20 1.60
2.00 1.00 0.25 3.30 1.65
2.00 1.00 0.25 3.20 1.60
2.00 1.00 0.25 3.30 1.65
1.00 2.00 0.25 3.10 1.55
COLUMNA EN EJE 1-1:N-N ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.90 6.88 6.19
1.00 3.00 0.15 3.18 1.43
1.00 1.00 0.15 0.50 0.08
2.00 2.00 0.43 3.10 5.27
2.00 2.00 0.25 3.25 3.25
1.00 2.00 0.25 2.80 1.40
COLUMNA EN EJE 1-1:M-M ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.90 6.88 6.19
1.00 2.00 0.15 3.18 0.95
1.00 2.00 0.15 0.50 0.15
2.00 2.00 0.43 3.10 5.27
2.00 2.00 0.25 3.25 3.25
1.00 2.00 0.25 2.80 1.40
COLUMNA EN EJE 1-1:L-L ( PRIMER Y SEGUNDO NIVEL ) 1.00 1.00 0.90 6.88 6.19
1.00 3.00 0.15 3.18 1.43
1.00 1.00 0.15 0.50 0.08
2.00 2.00 0.43 3.10 5.27
2.00 2.00 0.25 3.25 3.25
1.00 2.00 0.25 2.80 1.40
COLUMNA EN EJE 1-1:J-J;1-1:I-I;1-1:H-H ( PRIMER Y SEGUNDO NIVEL ) 3.00 1.00 0.90 6.88 18.56
6.00 2.00 0.15 3.18 5.71
6.00 2.00 0.43 3.10 15.81
6.00 2.00 0.25 3.25 9.75
3.00 2.00 0.25 2.80 4.20
COLUMNA EN EJE 2-2:O-O;2-2:D-D ( PRIMER Y SEGUNDO NIVEL ) 2.00 1.00 0.40 7.85 6.28
2.00 2.00 0.40 3.69 5.90
1.00 2.00 0.25 0.50 0.25
COLUMNA EN EJE 2-2:K'-K;2-2:K-K;2-2:E'E';2-2:E-E ( PRIMER Y SEGUNDO NIVEL ) 4.00 2.00 0.40 3.82 12.22
COLUMNA EN EJE 2-2:G-G; 2-2:F-F ( PRIMER Y SEGUNDO NIVEL ) 2.00 4.00 0.40 3.69 11.79
COLUMNA EN EJE 3-3:N-N ( PRIMER Y SEGUNDO NIVEL ) 2.00 1.00 0.90 2.95 5.31
2.00 2.00 0.15 3.10 1.86
2.00 2.00 0.15 3.10 1.86
2.00 2.00 0.43 3.10 5.27
2.00 2.00 0.25 3.25 3.25
1.00 2.00 0.25 2.80 1.40
M²M²M²M²
M²
M²
M²
M²
M²
M²
M²
M²
M²
M²
M²
M²
M²
M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²
19/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
COLUMNA EN EJE 3-3:M-M ( PRIMER Y SEGUNDO NIVEL ) 2.00 1.00 0.90 2.95 5.31
1.00 2.00 0.15 3.10 0.93
2.00 2.00 0.15 3.10 1.86
2.00 2.00 0.43 3.10 5.27
2.00 2.00 0.25 3.25 3.25
1.00 2.00 0.25 2.80 1.40
COLUMNA EN EJE 3-3:L-L ( PRIMER Y SEGUNDO NIVEL ) 2.00 1.00 0.90 2.95 5.31
1.00 1.00 0.15 3.10 0.46
2.00 1.50 0.15 3.10 1.39
2.00 2.00 0.43 3.10 5.27
2.00 2.00 0.25 3.25 3.25
1.00 2.00 0.25 2.80 1.40
COLUMNA EN EJE 3-3:J-J;3-3:I-I;3-3:H-H ( PRIMER Y SEGUNDO NIVEL ) 3.00 1.00 0.90 6.88 18.56
6.00 2.00 0.15 3.10 5.58
6.00 2.00 0.43 3.10 15.81
6.00 2.00 0.25 3.25 9.75
3.00 2.00 0.25 2.80 4.20
COLUMNA EN ESCALERAS ( PRIMER Y SEGUNDO NIVEL ) 2.00 1.00 0.75 6.88 10.31
2.00 1.00 0.25 6.88 3.44
4.00 1.00 0.50 3.10 6.20
6.00 2.00 0.25 3.25 9.75
6.00 1.00 0.25 6.68 10.01
OTROS
EJE O-O 4.00 1.00 5.55 0.25 5.55
1.00 1.00 2.70 0.15 0.41
SS.HH. PERSONAL 1.00 1.00 3.10 0.15 0.46
1.00 2.00 0.10 1.70 0.34
SS.HH. NIÑOS Y NIÑAS 1.00 2.00 0.25 1.70 0.85
1.00 1.00 0.15 1.70 0.26
1.00 2.00 0.10 1.75 0.35
1.00 1.00 0.40 1.70 0.68
1.00 1.00 0.33 1.60 0.52
1.00 1.00 0.08 3.10 0.23
1.00 1.00 0.25 3.20 0.80
1.00 1.00 0.30 3.20 0.96
1.00 1.00 0.30 1.70 0.51
1.00 1.00 0.15 3.10 0.46
1.00 2.00 0.10 1.75 0.35
1.00 1.00 0.15 3.20 0.48
1.00 1.00 0.40 3.20 1.28
1.00 1.00 0.10 1.80 0.18
1.00 1.00 0.25 1.70 0.43
1.00 1.00 0.08 3.10 0.23
1.00 1.00 0.18 3.20 0.56
PLACAS 1.00 1.00 0.63 3.40 2.13
1.00 1.00 0.63 1.70 1.06
1.00 1.00 0.15 0.50 0.08
1.00 1.00 0.55 3.20 1.76
1.00 1.00 0.40 1.70 0.68
1.00 1.00 0.15 3.10 0.46
04.03.03.03 ACERO EN COLUMNAS fy=4200 kg/cm2 Kg 12,217.00
04.03.04.00 COLUMNETAS
04.03.04.01 CONCRETO EN COLUMNETAS f'c=210 kg/cm2 5.90
COLUMNETAS EJE 1-1 ( PRIMER Y SEGUNDO NIVEL ) 2.00 18.00 0.25 0.15 1.80 2.43
M² 2.00 2.00 0.25 0.15 2.60 0.39
COLUMNETAS EJE 2-2 ( PRIMER Y SEGUNDO NIVEL ) 2.00 17.00 0.25 0.15 1.20 1.53
PARAPETOS 1.00 15.00 0.25 0.15 1.00 0.56
FALSO MURO 4.00 1.00 0.45 0.10 5.48 0.99
04.03.04.02 ENCOFRADO Y DESCENCOFRADO DE COLUMNETAS M² 52.73
COLUMNETAS EJE 1-1 ( PRIMER Y SEGUNDO NIVEL ) 2.00 8.00 0.25 1.85 7.40
M² 2.00 8.00 0.25 1.80 7.20
3.00 2.00 0.25 2.95 4.43
M² 3.00 2.00 0.25 2.90 4.35
COLUMNETAS EJE 2-2 ( PRIMER Y SEGUNDO NIVEL ) 2.00 7.00 0.25 1.25 4.38
M² 1.00 4.00 0.15 1.20 0.72
M² 2.00 10.00 0.25 1.20 6.00
M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²
M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²M²
M³
M²
M²M²M²
M²
M²
M²
20/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
M² 1.00 5.00 0.15 1.20 0.90
PARAPETOS 15.00 2.00 0.25 1.00 7.50
FALSO MURO 4.00 1.00 0.45 5.48 9.86
04.03.04.03 ACERO EN COLUMNETAS fy=4200 kg/cm2 Kg 593.00
04.03.05.00 VIGAS
04.03.05.01 CONCRETO EN VIGAS f'c=210 kg/cm2 37.11
PRIMER NIVEL
EJE O-O VP-101 2.00 1.00 2.45 0.25 0.30 0.37
EJE K"-K" VP-101 2.00 1.00 2.45 0.25 0.30 0.37
EJE E"-E" VP 101 2.00 1.00 2.45 0.25 0.30 0.37
EJE E-E VP - 101 2.00 1.00 2.45 0.25 0.30 0.37
EJE K-K VP 101 2.00 1.00 2.45 0.25 0.30 0.37
EJE N-N VP -102 2.00 1.00 2.45 0.25 0.30 0.37
EJE M-M VP -102 2.00 1.00 2.45 0.25 0.30 0.37
EJE L-L VP- 102 2.00 1.00 2.45 0.25 0.30 0.37
EJE G-G VP-102 2.00 1.00 2.45 0.25 0.30 0.37
EJE J-J VP -103 1.00 1.00 5.30 0.25 0.60 0.79
EJE I - I VP - 103 1.00 1.00 5.30 0.25 0.60 0.79
EJE H-H VP-103 1.00 1.00 5.30 0.25 0.60 0.79
EJE 1-1 (0- N ) VS 104 1.00 1.00 3.42 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (N-M) VS 104 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (M-L) VS 104 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (L-K") VS 104 1.00 1.00 2.43 0.25 0.30 0.18
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (K-J ) VS 104 1.00 1.00 3.42 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (J- I) VS 104 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (I-H) VS 104 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (H-G) VS 104 1.00 1.00 3.43 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (G-F) VS 104 1.00 1.00 2.05 0.25 0.30 0.15
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (F-E) VS 104 1.00 1.00 3.05 0.25 0.30 0.23
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (E-D) VS 104 1.00 1.00 3.80 0.25 0.30 0.29
EJE 3-3 (0- N ) VS 104 1.00 1.00 3.42 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (N-M) VS 104 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (M-L) VS 104 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (L-K") VS 104 1.00 1.00 2.43 0.25 0.30 0.18
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (K-J ) VS 104 1.00 1.00 3.42 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (J- I) VS 104 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (I-H) VS 104 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (H-G) VS 104 1.00 1.00 3.43 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (G-F) VS 104 1.00 1.00 2.05 0.25 0.30 0.15
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (F-E) VS 104 1.00 1.00 3.05 0.25 0.30 0.23
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (E-D) VS 104 1.00 1.00 3.80 0.25 0.30 0.29
EJE 3-3 (E-D) VS 104 1.00 1.00 3.80 0.25 0.30 0.29
SEGUNDO NIVEL
EJE O-O VP-201 2.00 1.00 2.45 0.25 0.30 0.37
EJE K"-K" VP-201 2.00 1.00 2.45 0.25 0.30 0.37
EJE E"-E" VP 201 2.00 1.00 2.45 0.25 0.30 0.37
EJE E-E VP - 201 2.00 1.00 2.45 0.25 0.30 0.37
M²M²
M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
M³M³M³M³
21/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
EJE K-K VP 201 2.00 1.00 2.45 0.25 0.30 0.37
EJE G-G VP-202 2.00 1.00 2.45 0.25 0.30 0.37
EJE F-F VP 202 2.00 1.00 2.45 0.25 0.30 0.37
EJE N-N VP -203 1.00 1.00 5.54 0.25 0.50 0.69
EJE M-M VP - 203 1.00 1.00 5.54 0.25 0.50 0.69
EJE L-L VP-203 1.00 1.00 5.54 0.25 0.50 0.69
EJE J-J VP -203 1.00 1.00 5.54 0.25 0.50 0.69
EJE I - I VP - 203 1.00 1.00 5.54 0.25 0.50 0.69
EJE H-H VP-203 1.00 1.00 5.54 0.25 0.50 0.69
EJE 1-1 (O- N ) VS 204 1.00 1.00 3.42 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (N-M) VS 204 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (M-L) VS 204 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (L-K") VS 204 1.00 1.00 2.43 0.25 0.30 0.18
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (K-J ) VS 204 1.00 1.00 3.42 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (J- I) VS 204 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (I-H) VS 204 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (H-G) VS 204 1.00 1.00 3.43 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (G-F) VS 204 1.00 1.00 2.05 0.25 0.30 0.15
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (F-E) VS 204 1.00 1.00 3.05 0.25 0.30 0.23
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 1-1 (E-D) VS 204 1.00 1.00 3.80 0.25 0.30 0.29
EJE 3-3 (O- N ) VS 204 1.00 1.00 3.42 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (N-M) VS 204 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (M-L) VS 204 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (L-K") VS 204 1.00 1.00 2.43 0.25 0.30 0.18
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (K-J ) VS 204 1.00 1.00 3.42 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (J- I) VS 204 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (I-H) VS 204 1.00 1.00 3.40 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (H-G) VS 204 1.00 1.00 3.43 0.25 0.30 0.26
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (G-F) VS 204 1.00 1.00 2.05 0.25 0.30 0.15
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (F-E) VS 204 1.00 1.00 3.05 0.25 0.30 0.23
-2.00 -1.00 -0.33 -0.15 -0.30 -0.03
EJE 3-3 (E-D) VS 204 1.00 1.00 3.80 0.25 0.30 0.29
EJE 1-1 Y 3-3 4.00 1.00 0.65 0.25 0.30 0.20
VIGAS EN TECHO 1.00 1.00 40.40 0.80 0.17 5.49
-6.00 -1.00 -0.40 -0.25 -0.17 -0.10
-2.00 -1.00 -0.40 -0.25 -0.17 -0.03
VIGAS EN VOLADIZO 14.00 2.00 2.00 0.25 0.35 4.90
4.00 2.00 3.43 0.15 0.19 0.76
4.00 2.00 3.40 0.15 0.19 0.75
1.00 2.00 3.05 0.15 0.19 0.17
1.00 2.00 3.80 0.15 0.19 0.21
VIGA EN TECHO LATERALES 2.00 1.00 0.84 0.15 0.17 0.04
2.00 1.00 2.07 0.15 0.17 0.11
4.00 1.00 0.80 0.15 0.17 0.08
VIGA DE TECHO FRONTAL 1.00 1.00 0.65 0.15 0.17 0.02
4.00 1.00 3.43 0.15 0.17 0.35
4.00 1.00 3.40 0.15 0.17 0.35
1.00 1.00 2.05 0.15 0.17 0.05
1.00 1.00 3.05 0.15 0.17 0.08
1.00 1.00 3.80 0.15 0.17 0.10
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
22/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
1.00 1.00 3.80 0.15 0.17 0.10
VIGA DE TECHO POSTERIOR 1.00 1.00 0.65 0.15 0.17 0.02
4.00 1.00 3.43 0.15 0.17 0.35
4.00 1.00 3.40 0.15 0.17 0.35
1.00 1.00 2.05 0.15 0.17 0.05
1.00 1.00 3.05 0.15 0.17 0.08
1.00 1.00 3.80 0.15 0.17 0.10
1.00 1.00 0.80 0.15 0.17 0.02
SSHH. PERSONAL FEMENINO Y MASCULINO 2.00 1.00 1.64 0.15 0.20 0.10
1.00 1.00 2.70 0.15 0.20 0.08
SSHH. NIÑOS, DISCAPACITADOS Y NIÑAS 1.00 1.00 1.35 0.15 0.20 0.04
1.00 1.00 2.60 0.15 0.20 0.08
1.00 1.00 0.52 0.15 0.20 0.02
1.00 1.00 0.33 0.15 0.20 0.01
1.00 1.00 1.32 0.15 0.20 0.04
1.00 1.00 2.60 0.15 0.20 0.08
04.03.05.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS M² 354.54
PRIMER NIVEL
EJE O-O M² 1.00 2.00 2.45 0.65 3.19
EJE E-E, EJE D-D M² 2.00 3.00 2.45 0.30 4.41
EJE N-N, EJE M-M, EJE L-L M² 3.00 4.00 2.45 0.10 2.94
EJE K'K', EJE K-K M² 2.00 2.00 2.45 0.10 0.98
EJE J-J, EJE I-I, EJE H-H M² 3.00 1.00 5.30 1.05 16.70
EJE G-G, EJE F-F M² 2.00 4.00 2.45 0.10 1.96
EJE E'-E' M² 1.00 2.00 2.45 0.10 0.49
VOLADIZO EJE O-O, EJE D-D M² 2.00 1.00 1.90 0.35 1.33
M² 2.00 1.00 1.70 0.15 0.51
M² 2.00 1.00 2.12 0.25 1.06
VOLDIZO EJE N-N, EJE M-M, EJE L-L, EJE J-J, EJE I-I, EJE H-H, EJE G-G, EJE F-F M² 8.00 2.00 1.70 0.15 4.08
M² 8.00 1.00 2.12 0.25 4.25
VOLADIZO EJE K'K', EJE K-K, EJE E'E', EJE E-E M² 4.00 1.00 1.70 0.15 1.02
M² 4.00 1.00 2.12 0.25 2.12
EJE 1-1, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 1.00 2.78 0.45 5.00
M² 4.00 1.00 3.43 0.20 2.74
EJE 1-1, EJE N-N:M-M; EJE M-M:L-L M² 2.00 1.00 2.75 0.45 2.48
M² 2.00 1.00 3.40 0.20 1.36
EJE 1-1, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 2.75 0.45 2.48
M² 2.00 1.00 3.40 0.20 1.36
EJE 1-1, EJE G-G:F-F M² 1.00 1.00 2.05 0.65 1.33
EJE 1-1, EJE F-F:E'-E' M² 1.00 1.00 2.40 0.45 1.08
M² 1.00 1.00 3.05 0.20 0.61
EJE 3-3, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 1.00 2.78 0.25 2.78
M² 4.00 1.00 3.43 0.20 2.74
EJE 3-3, EJE N-N:M-M; EJE M-M:L-L M² 2.00 1.00 2.75 0.25 1.38
M² 2.00 1.00 3.40 0.20 1.36
EJE 3-3, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 2.75 0.25 1.38
M² 2.00 1.00 3.40 0.20 1.36
EJE 3-3, EJE G-G:F-F M² 1.00 1.00 2.05 0.45 0.92
EJE 3-3, EJE F-F:E'-E' M² 1.00 1.00 2.40 0.45 1.08
M² 1.00 1.00 3.05 0.20 0.61
VOLADIZO, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 1.00 3.43 0.40 5.48
VOLADIZO, EJE N-N:M-M; EJE M-M:L-L M² 2.00 1.00 3.40 0.40 2.72
VOLADIZO, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 3.40 0.40 2.72
VOLADIZO, EJE G-G:F-F M² 1.00 1.00 2.05 0.40 0.82
VOLADIZO, EJE F-F:E'-E' M² 1.00 1.00 3.05 0.40 1.22
VOLADIZO, EJE E-E:D-D M² 1.00 1.00 3.80 0.40 1.52
ESCALERA M² 1.00 1.00 3.80 1.05 3.99
M² 1.00 1.00 3.80 0.65 2.47
M² 1.00 1.00 3.80 0.65 2.47
SEGUNDO NIVEL
EJE O-O M² 1.00 2.00 2.45 0.30 1.47
M² 1.00 2.00 2.45 0.30 1.47
EJE E-E, EJE D-D M² 2.00 3.00 2.45 0.30 4.41
EJE K'K', EJE K-K M² 2.00 2.00 2.45 0.30 2.94
EJE G-G, EJE F-F M² 2.00 4.00 2.45 0.30 5.88
EJE E'-E' M² 1.00 2.00 2.45 0.30 1.47
EJE 1-1, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 1.00 2.78 0.45 5.00
M² 4.00 1.00 3.43 0.40 5.48
EJE 1-1, EJE N-N:M-M; EJE M-M:L-L M² 2.00 1.00 2.75 0.45 2.48
M² 2.00 1.00 3.40 0.40 2.72
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
23/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
EJE 1-1, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 2.75 0.45 2.48
M² 2.00 1.00 3.40 0.40 2.72
EJE 1-1, EJE G-G:F-F M² 1.00 1.00 2.05 0.85 1.74
EJE 1-1, EJE F-F:E'-E' M² 1.00 1.00 2.40 0.45 1.08
M² 1.00 1.00 3.05 0.40 1.22
EJE 3-3, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 1.00 2.78 0.25 2.78
M² 4.00 1.00 3.43 0.40 5.48
EJE 3-3, EJE N-N:M-M; EJE M-M:L-L M² 2.00 1.00 2.75 0.25 1.38
M² 2.00 1.00 3.40 0.40 2.72
EJE 3-3, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 2.75 0.25 1.38
M² 2.00 1.00 3.40 0.40 2.72
EJE 3-3, EJE G-G:F-F M² 1.00 1.00 2.05 0.65 1.33
EJE 3-3, EJE F-F:E'-E' M² 1.00 1.00 2.40 0.45 1.08
M² 1.00 1.00 3.05 0.40 1.22
ESCALERA M² 2.00 1.00 3.80 0.85 6.46
TECHO
EJE O-O;EJE G-G; EJE F-F; EJE D-D M² 4.00 4.00 2.70 0.13 5.61
EJE K'-K', EJE K-K, EJE E'-E', EJE E-E M² 4.00 2.00 2.70 0.13 2.80
EJE N-N, EJE M-M, EJE L-L, EJE J-J, EJE I-I, EJE H-H M² 6.00 4.00 2.70 0.91 58.86
VOLADIZO M² 14.00 1.00 1.04 0.31 4.53
M² 14.00 1.00 2.30 0.31 9.97
EJE 1-1, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 1.00 2.78 0.21 2.33
M² 4.00 1.00 3.43 0.26 3.56
EJE 1-1, EJE N-N:M-M; EJE M-M:L-L M² 2.00 1.00 2.75 0.21 1.16
M² 2.00 1.00 3.40 0.26 1.77
EJE 1-1, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 2.75 0.21 1.16
M² 2.00 1.00 3.40 0.26 1.77
EJE 1-1, EJE G-G:F-F M² 1.00 1.00 2.05 0.51 1.05
EJE 1-1, EJE F-F:E'-E' M² 1.00 1.00 2.40 0.31 0.74
M² 1.00 1.00 3.05 0.26 0.79
VOLADIZO M² 2.00 1.00 1.00 0.31 0.62
EJE 3-3, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 1.00 2.78 0.21 2.33
M² 4.00 1.00 3.43 0.26 3.56
EJE 3-3, EJE N-N:M-M; EJE M-M:L-L M² 2.00 1.00 2.75 0.21 1.16
M² 2.00 1.00 3.40 0.26 1.77
EJE 3-3, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 2.75 0.21 1.16
M² 2.00 1.00 3.40 0.26 1.77
EJE 3-3, EJE G-G:F-F M² 1.00 1.00 2.05 0.51 1.05
EJE 3-3, EJE F-F:E'-E' M² 1.00 1.00 2.40 0.31 0.74
M² 1.00 1.00 3.05 0.26 0.79
VOLADIZO M² 2.00 1.00 1.00 0.31 0.62
VOLADIZO, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 2.00 3.43 0.41 11.23
VOLADIZO, EJE N-N:M-M; EJE M-M:L-L M² 2.00 2.00 3.40 0.41 5.58
VOLADIZO, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 3.40 0.21 1.43
VOLADIZO, EJE G-G:F-F M² 1.00 1.00 2.05 0.51 1.05
VOLADIZO, EJE F-F:E'-E' M² 1.00 1.00 3.05 0.31 0.95
M² 2.00 1.00 0.80 0.46 0.74
VOLADIZOS LATERALES M² 2.00 1.00 1.04 0.41 0.86
M² 2.00 1.00 2.70 0.41 2.21
M² 2.00 1.00 2.70 0.41 2.21
M² 2.00 1.00 2.30 0.41 1.88
VIGA CENTRAL, EJE O-O:N-N; EJE L-L:K'-K'; EJE KK:J-J; EJE H-H:G-G M² 4.00 2.00 3.43 0.74 20.28
VIGA CENTRAL, EJE N-N:M-M; EJE M-M:L-L M² 2.00 2.00 3.40 0.74 10.06
VIGA CENTRAL, EJE J-J:I-I; EJE I-I:H-H M² 2.00 1.00 3.40 0.74 5.03
VIGA CENTRAL, EJE G-G:F-F M² 1.00 1.00 2.05 0.74 1.52
VIGA CENTRAL, EJE F-F:E'-E' M² 1.00 1.00 3.05 0.74 2.26
M² 2.00 1.00 1.00 0.74 1.48
OTROS
SS.HH. PERSONAL M² 1.00 2.00 3.43 0.20 1.37
M² 1.00 2.00 2.75 0.20 1.10
SS.HH. NIÑOS M² 1.00 2.00 2.60 0.20 1.04
SS.HH. NIÑAS M² 1.00 2.00 2.70 0.20 1.08
04.03.05.03 ACERO EN VIGAS fy=4200 kg/cm2 Kg 7,405.00
04.03.06.00 VIGAS DE AMARRES
04.03.06.01 CONCRETO EN VIGAS DE AMARRES f'c=210 kg/cm2 1.67
PRIMER NIVEL EJE 3-3 1.00 1.00 1.25 0.15 0.10 0.02
1.00 1.00 1.25 0.15 0.10 0.02
1.00 1.00 2.20 0.15 0.10 0.03
1.00 1.00 2.20 0.15 0.10 0.03
M³
M³M³M³M³
24/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
1.00 1.00 1.25 0.15 0.10 0.02
1.00 1.00 1.50 0.15 0.10 0.02
1.00 1.00 0.88 0.15 0.10 0.01
PRIMER NIVEL EJE 1-1 1.00 1.00 2.23 0.15 0.10 0.03
1.00 1.00 2.20 0.15 0.10 0.03
1.00 1.00 2.20 0.15 0.10 0.03
1.00 1.00 2.23 0.15 0.10 0.03
1.00 1.00 2.23 0.15 0.10 0.03
1.00 1.00 2.20 0.15 0.10 0.03
1.00 1.00 2.20 0.15 0.10 0.03
1.00 1.00 2.23 0.15 0.10 0.03
1.00 1.00 1.50 0.15 0.10 0.02
1.00 1.00 1.85 0.15 0.10 0.03
1.00 1.00 3.30 0.15 0.10 0.05
SEGUNDO NIVEL EJE 3-3 4.00 1.00 1.25 0.15 0.10 0.08
4.00 1.00 2.20 0.15 0.10 0.13
1.00 1.00 1.50 0.15 0.10 0.02
1.00 1.00 0.88 0.15 0.10 0.01
SEGUNDO NIVEL EJE 1-1 4.00 1.00 2.23 0.15 0.10 0.13
4.00 1.00 2.20 0.15 0.10 0.13
1.00 1.00 1.50 0.15 0.10 0.02
1.00 1.00 1.85 0.15 0.10 0.03
1.00 1.00 3.30 0.15 0.10 0.05
VIGAS EN PARAPETOS
4.00 1.00 3.43 0.15 0.10 0.21
4.00 1.00 3.40 0.15 0.10 0.20
1.00 1.00 2.05 0.15 0.10 0.03
1.00 1.00 3.05 0.15 0.10 0.05
1.00 1.00 3.80 0.15 0.10 0.06
04.03.06.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS DE AMARRES M² 39.51
VIGAS DE AMARRE
PRIMER NIVEL EJE O-O M² 1.00 1.00 1.33 0.18 0.23
M² 1.00 1.00 2.10 0.18 0.37
PRIMER NIVEL EJE 3-3 M² 1.00 2.00 1.25 0.18 0.44
M² 1.00 2.00 1.25 0.18 0.44
M² 1.00 2.00 2.20 0.18 0.77
M² 1.00 2.00 2.20 0.18 0.77
M² 1.00 2.00 1.25 0.18 0.44
M² 1.00 2.00 1.50 0.18 0.53
M² 1.00 2.00 0.88 0.18 0.31
PRIMER NIVEL EJE 1-1 M² 1.00 2.00 2.23 0.18 0.78
M² 1.00 2.00 1.58 0.18 0.55
M² 1.00 2.00 2.20 0.18 0.77
M² 1.00 2.00 2.23 0.18 0.78
M² 1.00 2.00 2.23 0.18 0.78
M² 1.00 2.00 2.20 0.18 0.77
M² 1.00 2.00 2.20 0.18 0.77
M² 1.00 2.00 2.23 0.18 0.78
M² 1.00 2.00 1.50 0.18 0.53
M² 1.00 2.00 1.85 0.18 0.65
M² 1.00 2.00 3.30 0.18 1.16
SEGUNDO NIVEL EJE 3-3 M² 4.00 2.00 1.25 0.18 1.75
M² 4.00 2.00 2.20 0.18 3.08
M² 1.00 2.00 1.50 0.18 0.53
M² 1.00 2.00 0.88 0.18 0.31
SEGUNDO NIVEL EJE 1-1 M² 4.00 2.00 2.23 0.18 3.12
M² 4.00 2.00 2.20 0.18 3.08
M² 1.00 2.00 1.50 0.18 0.53
M² 1.00 2.00 1.85 0.18 0.65
M² 1.00 2.00 3.30 0.18 1.16
VIGAS EN PARAPETOS
M² 4.00 2.00 3.43 0.18 4.80
M² 4.00 2.00 3.40 0.18 4.76
M² 1.00 2.00 2.05 0.18 0.72
M² 1.00 2.00 3.05 0.18 1.07
M² 1.00 2.00 3.80 0.18 1.33
04.03.06.03 ACERO EN VIGAS DE AMARRES fy=4200 kg/cm2 Kg 209.00
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
M³M³M³M³M³
25/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
04.03.07.00 LOSA ALIGERADA
04.03.07.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 38.46
PRIMER NIVEL
CIRCULO DE LIMPIEZA,SS.HH PERSONAL 1.00 1.00 5.80 3.43 0.20 3.97
SS.HH NIÑOS 1.00 1.00 3.40 2.95 0.20 2.01
SS.HH NIÑOS 1.00 1.00 3.10 2.92 0.20 1.81
SS.HH NIÑAS 1.00 1.00 3.40 3.06 0.20 2.08
SS.HH NIÑAS 1.00 1.00 2.83 1.93 0.20 1.09
SS.HH DISAPACITADOS 1.00 1.00 2.70 1.83 0.20 0.99
DEPOSITO 1.00 1.00 5.80 3.43 0.20 3.97
SALA DE USOS MULTIPLES 1.00 1.00 14.40 5.80 0.20 16.70
GUARDIANIA 1.00 1.00 5.80 2.05 0.20 2.38
DIRECCION 1.00 1.00 5.80 3.05 0.20 3.54
VOLADIZOS 1.00 1.00 3.43 1.70 0.20 1.17
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 3.42 1.70 0.20 1.16
1.00 1.00 3.42 1.70 0.20 1.16
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 3.40 1.70 0.20 1.16
1.00 1.00 2.05 1.70 0.20 0.70
1.00 1.00 2.55 1.70 0.20 0.87
SEGUNDO NIVEL
SALA DE COMPUTO 2.00 1.00 3.43 2.70 0.17 3.14
2.00 1.00 3.40 2.70 0.17 3.12
2.00 1.00 3.40 2.70 0.17 3.12
2.00 1.00 3.43 2.70 0.17 3.14
BIBLIOTECA 2.00 1.00 3.43 2.70 0.17 3.14
2.00 1.00 3.40 2.70 0.17 3.12
2.00 1.00 3.40 2.70 0.17 3.12
2.00 1.00 3.43 2.70 0.17 3.14
ENTREGA Y RECEPCION DE LIBROS 2.00 1.00 2.05 2.70 0.17 1.88
ALMACEN 2.00 1.00 3.05 2.70 0.17 2.80
VOLADIZOS 2.00 1.00 0.65 2.70 0.17 0.60
SALA DE COMPUTO 1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
BIBLIOTECA 1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
ENTREGA Y RECEPCION DE LIBROS 1.00 1.00 0.65 1.94 0.17 0.21
ALMACEN 1.00 1.00 0.65 1.94 0.17 0.21
VOLADIZOS 1.00 1.00 0.65 1.94 0.17 0.21
SALA DE COMPUTO 1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
BIBLIOTECA 1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
1.00 1.00 0.65 1.94 0.17 0.21
ENTREGA Y RECEPCION DE LIBROS 1.00 1.00 0.65 1.94 0.17 0.21
ALMACEN 1.00 1.00 0.65 1.94 0.17 0.21
VOLADIZOS 1.00 1.00 0.65 1.94 0.17 0.21
SALA DE COMPUTO 1.00 1.00 0.65 0.69 0.17 0.08
1.00 1.00 0.65 0.69 0.17 0.08
1.00 1.00 0.65 0.69 0.17 0.08
1.00 1.00 0.65 0.69 0.17 0.08
BIBLIOTECA 1.00 1.00 0.65 0.69 0.17 0.08
1.00 1.00 0.65 0.69 0.17 0.08
1.00 1.00 0.65 0.69 0.17 0.08
1.00 1.00 0.65 0.69 0.17 0.08
ENTREGA Y RECEPCION DE LIBROS 1.00 1.00 0.65 0.69 0.17 0.08
ALMACEN 1.00 1.00 0.65 0.69 0.17 0.08
04.03.07.02 ENCOFRADO Y DESCENCOFRADO DE LOSA ALIGERADA M² 457.58
PRIMER NIVEL
CIRCULO DE LIMPIEZA,SS.HH PERSONAL M² 1.00 1.00 5.80 3.43 19.87
M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³M³
26/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
SS.HH NIÑOS M² 1.00 1.00 3.40 2.95 10.03
SS.HH NIÑOS M² 1.00 1.00 3.10 2.92 9.05
SS.HH NIÑAS M² 1.00 1.00 3.40 3.06 10.40
SS.HH NIÑAS M² 1.00 1.00 2.83 1.93 5.45
SS.HH DISAPACITADOS M² 1.00 1.00 2.70 1.83 4.94
DEPOSITO M² 1.00 1.00 5.80 3.43 19.87
SALA DE USOS MULTIPLES M² 1.00 1.00 14.40 5.80 83.52
GUARDIANIA M² 1.00 1.00 5.80 2.05 11.89
DIRECCION M² 1.00 1.00 5.80 3.05 17.69
VOLADIZOS M² 1.00 1.00 3.43 1.70 5.83
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 3.42 1.70 5.81
M² 1.00 1.00 3.42 1.70 5.81
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 3.40 1.70 5.78
M² 1.00 1.00 2.05 1.70 3.48
M² 1.00 1.00 2.55 1.70 4.34
SEGUNDO NIVEL
SALA DE COMPUTO M² 2.00 1.00 3.43 2.70 18.50
M² 2.00 1.00 3.40 2.70 18.36
M² 2.00 1.00 3.40 2.70 18.36
M² 2.00 1.00 3.43 2.70 18.50
BIBLIOTECA M² 2.00 1.00 3.43 2.70 18.50
M² 2.00 1.00 3.40 2.70 18.36
M² 2.00 1.00 3.40 2.70 18.36
M² 2.00 1.00 3.43 2.70 18.50
ENTREGA Y RECEPCION DE LIBROS M² 2.00 1.00 2.05 2.70 11.07
ALMACEN M² 2.00 1.00 3.05 2.70 16.47
VOLADIZOS M² 2.00 1.00 0.65 2.70 3.51
SALA DE COMPUTO M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
BIBLIOTECA M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
ENTREGA Y RECEPCION DE LIBROS M² 1.00 1.00 0.65 1.94 1.26
ALMACEN M² 1.00 1.00 0.65 1.94 1.26
VOLADIZOS M² 1.00 1.00 0.65 1.94 1.26
SALA DE COMPUTO M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
BIBLIOTECA M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
M² 1.00 1.00 0.65 1.94 1.26
ENTREGA Y RECEPCION DE LIBROS M² 1.00 1.00 0.65 1.94 1.26
ALMACEN M² 1.00 1.00 0.65 1.94 1.26
VOLADIZOS M² 1.00 1.00 0.65 1.94 1.26
SALA DE COMPUTO M² 1.00 1.00 0.65 0.69 0.45
M² 1.00 1.00 0.65 0.69 0.45
M² 1.00 1.00 0.65 0.69 0.45
M² 1.00 1.00 0.65 0.69 0.45
BIBLIOTECA M² 1.00 1.00 0.65 0.69 0.45
M² 1.00 1.00 0.65 0.69 0.45
M² 1.00 1.00 0.65 0.69 0.45
M² 1.00 1.00 0.65 0.69 0.45
ENTREGA Y RECEPCION DE LIBROS M² 1.00 1.00 0.65 0.69 0.45
ALMACEN M² 1.00 1.00 0.65 0.69 0.45
04.03.07.03 ACERO EN LOSA ALIGERADA fy=4200 kg/cm2 Kg 4,951.00
04.03.07.04 LADRILLO DE ARCILLA 15x30x30 CM PARA LOSA ALIGERADA Und 3,814.00
04.03.08.00 ESCALERA
04.03.08.01 CONCRETO EN ESCALERA f'c=210 kg/cm2 4.54
EN BASE 1.00 1.00 1.83 0.40 0.60 0.44
ESCALONES - 1° TRAMO 1.00 1.00 1.83 0.40 0.05 0.04
M³
M³M³
27/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
6.00 1.00 1.83 0.45 0.17 0.83
1.00 1.00 1.83 0.43 0.14 0.11
1.00 1.00 1.83 0.30 0.03 0.02
DESCANSO EN 1° TRAMO 1.00 1.00 1.91 2.33 0.20 0.89
DESCANSO EN 2° TRAMO 1.00 1.00 1.91 2.28 0.20 0.87
ESCALONES - 2° TRAMO 1.00 1.00 1.91 0.05 0.19 0.02
9.00 1.00 1.83 0.45 0.17 1.24
1.00 1.00 1.83 0.30 0.17 0.09
04.03.08.02 ENCOFRADO Y DESCENCOFRADO DE ESCALERA M² 20.03
TRAMO I
FONDO DE ESCALERA M² 1.00 1.00 2.99 1.83 5.47
FONDO DE DESCANSO M² 1.00 1.00 2.08 1.91 3.97
TRAMO II
FONDO DE DESCANSO M² 1.00 1.00 2.29 1.91 4.37
FONDO DE ESCALERA M² 1.00 1.00 3.40 1.83 6.22
04.03.08.03 ACERO EN ESCALERA fy=4200 kg/cm2 Kg 400.00
04.03.09.00 MURO INTERMEDIO DE ESCALERA
04.03.09.01 CONCRETO EN MURO INTERMEDIO DE ESCALERA f'c=210 kg/cm2 2.03
1.00 1.00 3.00 0.15 4.50 2.03
04.03.09.02 ENCOFRADO Y DESCENCOFRADO DE MURO INTERMEDIO DE ESCALERA M² 13.50
M² 1.00 1.00 3.00 4.50 13.50
04.03.09.03 ACERO EN MURO INTERMEDIO DE ESCALERA fy=4200 kg/cm2 Kg 310.00
04.03.10.00 GARGOLAS
04.03.10.01 CONCRETO EN GARGOLAS f'c=175 kg/cm2 0.01
3.00 1.00 0.18 0.05 0.15 0.00
3.00 1.00 0.25 0.05 0.10 0.00
3.00 1.00 0.25 0.10 0.10 0.01
04.03.10.02 ENCOFRADO Y DESCENCOFRADO DE GARGOLAS M² 0.47
M² 3.00 2.00 0.18 0.15 0.16
M² 3.00 1.00 0.25 0.10 0.08
M² 3.00 1.00 0.25 0.20 0.15
M² 3.00 1.00 0.20 0.10 0.06
M² 3.00 1.00 0.05 0.15 0.02
04.03.10.03 ACERO EN GARGOLAS fy=4200 kg/cm2 Kg 1.09
04.03.11.00 MESON PARA LAVATORIOS OVALINES
04.03.11.01 CONCRETO EN MESON f'c=210 kg/cm2 0.18
LAVATORIO SS.HH NIÑOS Y NIÑAS 2.00 1.00 2.85 0.53 0.05 0.15
LAVATORIO SS.HH DISCAPACITADOS 1.00 1.00 1.05 0.53 0.05 0.03
04.03.11.02 ENCOFRADO Y DESCENCOFRADO DE MESON M² 3.88
LAVATORIO SS.HH NIÑOS Y NIÑAS 2.00 1.00 2.85 0.58 3.28LAVATORIO SS.HH DISCAPACITADOS 1.00 1.00 1.05 0.58 0.60
04.03.11.03 ACERO EN MESON fy=4200 kg/cm2 Kg 56.00
M³M³M³M³M³M³M³M³
M³
M³
M³
M³M³M³
M³
M³M³
M³M³
28/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"
04.03.00.00 OBRAS DE CONCRETO ARMADO
04.03.01.00 ZAPATAS
04.03.01.02 ACERO EN ZAPATAS fy=4200 kg/cm2 Kg 0.00 0.00 0.00 2187.00 0.00 0.00
Z-1 (2.00) Kg 1.00 9.00 5/8 24.40 - - - 219.60 - - - - - 341.00 - -
1.00 Kg 1.00 5.00 5/8 1.85 - - - 9.25 - - - - - 14.00 - -
2.45 Kg 1.00 13.00 5/8 1.85 - - - 24.05 - - - - - 37.00 - -
2.75 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.75 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.78 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.83 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.85 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
2.85 Kg 1.00 15.00 5/8 1.85 - - - 27.75 - - - - - 43.00 - -
2.83 Kg 1.00 15.00 5/8 1.85 - - - 27.75 - - - - - 43.00 - -
1.40 Kg 1.00 7.00 5/8 1.85 - - - 12.95 - - - - - 20.00 - -
2.40 Kg 1.00 12.00 5/8 1.85 - - - 22.20 - - - - - 34.00 - -
2.73 Kg 1.00 14.00 5/8 1.85 - - - 25.90 - - - - - 40.00 - -
1.00 Kg 1.00 5.00 5/8 1.85 - - - 9.25 - - - - - 14.00 - -
Z-2 (1.20) Kg 1.00 5.00 5/8 22.65 - - - 113.25 - - - - - 176.00 - -
1.00 Kg 1.00 5.00 5/8 1.05 - - - 5.25 - - - - - 8.00 - -
2.45 Kg 1.00 13.00 5/8 1.05 - - - 13.65 - - - - - 21.00 - -
2.75 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.75 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.78 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.83 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.85 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
2.85 Kg 1.00 15.00 5/8 1.05 - - - 15.75 - - - - - 24.00 - -
2.83 Kg 1.00 15.00 5/8 1.05 - - - 15.75 - - - - - 24.00 - -
1.40 Kg 1.00 7.00 5/8 1.05 - - - 7.35 - - - - - 11.00 - -
2.40 Kg 1.00 12.00 5/8 1.05 - - - 12.60 - - - - - 20.00 - -
2.73 Kg 1.00 14.00 5/8 1.05 - - - 14.70 - - - - - 23.00 - -
1.00 Kg 1.00 5.00 5/8 1.05 - - - 5.25 - - - - - 8.00 - -
Z-3 (0.90) Kg 6.00 4.00 5/8 7.25 - - - 174.00 - - - - - 270.00 - -
4.23 Kg 6.00 25.00 5/8 0.75 - - - 112.50 - - - - - 175.00 - -
Z-4 (0.80) Kg 3.00 4.00 5/8 9.00 - - - 108.00 - - - - - 168.00 - -
4.23 Kg 3.00 25.00 5/8 0.65 - - - 48.75 - - - - - 76.00 - -
Z-5 (1.20) Kg 2.00 4.00 5/8 9.00 - - - 72.00 - - - - - 112.00 - -
4.23 Kg 2.00 25.00 5/8 1.05 - - - 52.50 - - - - - 81.00 - -
Z-6 (1.00) Kg 1.00 4.00 5/8 9.00 - - - 36.00 - - - - - 56.00 - -
4.23 Kg 1.00 25.00 5/8 0.85 - - - 21.25 - - - - - 33.00 - -
04.03.02.00 VIGAS DE CIMENTACION
04.03.02.03 ACERO EN VIGAS DE CIMENTACIÓN: f'y = 4,200 kg/cm² Kg 0.00 2982.00 0.00 1381.00 0.00 0.00
VC (39.80) Kg 1.00 12.00 3/8 41.34 - 496.08 - - - - - 278.00 - - - -
Kg 1.00 6.00 5/8 41.34 - - - 248.04 - - - - - 385.00 - -
2.45 Kg 1.00 12.00 3/8 4.74 - 56.88 - - - - - 32.00 - - - -
2.75 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.75 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.78 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.83 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.85 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.85 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.83 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
1.40 Kg 1.00 8.00 3/8 4.74 - 37.92 - - - - - 21.00 - - - -
2.40 Kg 1.00 12.00 3/8 4.74 - 56.88 - - - - - 32.00 - - - -
2.73 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
VC (39.80) Kg 1.00 12.00 3/8 41.34 - 496.08 - - - - - 278.00 - - - -
Kg 1.00 6.00 5/8 41.34 - - - 248.04 - - - - - 385.00 - -
2.45 Kg 1.00 12.00 3/8 4.74 - 56.88 - - - - - 32.00 - - - -
2.75 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.75 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.78 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.83 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.85 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.85 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
2.83 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
1.40 Kg 1.00 8.00 3/8 4.74 - 37.92 - - - - - 21.00 - - - -
2.40 Kg 1.00 12.00 3/8 4.74 - 56.88 - - - - - 32.00 - - - -
2.73 Kg 1.00 14.00 3/8 4.74 - 66.36 - - - - - 37.00 - - - -
VC (6.30) Kg 7.00 12.00 3/8 7.84 - 658.56 - - - - - 369.00 - - - -
Kg 7.00 6.00 5/8 1.54 - - - 64.68 - - - - - 100.00 - -
2.45 Kg 7.00 12.00 3/8 4.74 - 398.16 - - - - - 223.00 - - - -
2.45 Kg 7.00 12.00 3/8 4.74 - 398.16 - - - - - 223.00 - - - -
VC (6.30) Kg 4.00 14.00 3/8 7.84 - 439.04 - - - - - 246.00 - - - -
Kg 4.00 6.00 5/8 7.84 - - - 188.16 - - - - - 292.00 - -
2.45 Kg 4.00 12.00 3/8 4.74 - 227.52 - - - - - 127.00 - - - -
2.45 Kg 4.00 12.00 3/8 4.74 - 227.52 - - - - - 127.00 - - - -
VC (6.30) Kg 3.00 12.00 3/8 7.84 - 282.24 - - - - - 158.00 - - - -
Kg 3.00 6.00 5/8 7.84 - - - 141.12 - - - - - 219.00 - -
5.30 Kg 3.00 24.00 3/8 4.74 - 341.28 - - - - - 191.00 - - - -
04.03.03.00 COLUMNAS
04.03.03.03 ACERO EN COLUMNAS fy=4200 kg/cm2 Kg 47.00 3809.00 466.00 5121.00 1376.00 1398.00
C-1 Kg 3.00 6.00 1 9.77 - - - - - 175.86 - - - - - 699.00
Kg 3.00 10.00 5/8 9.77 - - - 293.10 - - - - - 455.00 - -
Kg 3.00 2.00 1/2 9.77 - - 58.62 - - - - - 58.00 - - -
3.15 Kg 3.00 34.00 3/8 2.02 - 206.04 - - - - - 115.00 - - - -
Kg 3.00 34.00 3/8 1.42 - 144.84 - - - - - 81.00 - - - -
2.30 Kg 3.00 28.00 3/8 2.02 - 169.68 - - - - - 95.00 - - - -
Kg 3.00 28.00 3/8 1.42 - 119.28 - - - - - 67.00 - - - -
C-2 Kg 3.00 4.00 1 9.77 - - - - - 117.24 - - - - - 466.00
Kg 3.00 2.00 3/4 9.77 - - - - 58.62 - - - - - 131.00 -
Kg 3.00 10.00 5/8 9.77 - - - 293.10 - - - - - 455.00 - -
Kg 3.00 2.00 1/2 9.77 - - 58.62 - - - - - 58.00 - - -
3.45 Kg 3.00 36.00 3/8 2.02 - 218.16 - - - - - 122.00 - - - -
Kg 3.00 36.00 3/8 1.42 - 153.36 - - - - - 86.00 - - - -
2.60 Kg 3.00 32.00 3/8 2.02 - 193.92 - - - - - 109.00 - - - -
Kg 3.00 32.00 3/8 1.42 - 136.32 - - - - - 76.00 - - - -
C-3 Kg 6.00 5.00 3/4 9.77 - - - - 293.10 - - - - - 655.00 -
Kg 6.00 6.00 5/8 9.77 - - - 351.72 - - - - - 546.00 - -
Kg 6.00 2.00 1/2 9.77 - - 117.24 - - - - - 117.00 - - -
3.45 Kg 6.00 36.00 3/8 1.37 - 295.92 - - - - - 166.00 - - - -
Kg 6.00 36.00 3/8 1.42 - 306.72 - - - - - 172.00 - - - -
2.60 Kg 6.00 32.00 3/8 1.37 - 263.04 - - - - - 147.00 - - - -
Nº DE ELEMENTOS
29/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"Nº DE
ELEMENTOS
Kg 6.00 32.00 3/8 1.42 - 272.64 - - - - - 153.00 - - - -
C-4 Kg 3.00 2.00 1 9.77 - - - - - 58.62 - - - - - 233.00
Kg 3.00 3.00 3/4 9.77 - - - - 87.93 - - - - - 197.00 -
Kg 3.00 10.00 5/8 9.77 - - - 293.10 - - - - - 455.00 - -
Kg 3.00 2.00 1/2 9.77 - - 58.62 - - - - - 58.00 - - -
3.15 Kg 3.00 34.00 3/8 2.02 - 206.04 - - - - - 115.00 - - - -
Kg 3.00 34.00 3/8 1.42 - 144.84 - - - - - 81.00 - - - -
2.30 Kg 3.00 28.00 3/8 2.02 - 169.68 - - - - - 95.00 - - - -
Kg 3.00 28.00 3/8 1.42 - 119.28 - - - - - 67.00 - - - -
C-5 Kg 3.00 6.00 3/4 9.77 - - - - 175.86 - - - - - 393.00 -
Kg 3.00 10.00 5/8 9.77 - - - 293.10 - - - - - 455.00 - -
Kg 3.00 2.00 1/2 9.77 - - 58.62 - - - - - 58.00 - - -
3.45 Kg 3.00 36.00 3/8 2.02 - 218.16 - - - - - 122.00 - - - -
Kg 3.00 36.00 3/8 1.42 - 153.36 - - - - - 86.00 - - - -
2.60 Kg 3.00 32.00 3/8 2.02 - 193.92 - - - - - 109.00 - - - -
Kg 3.00 32.00 3/8 1.42 - 136.32 - - - - - 76.00 - - - -
C-6 Kg 6.00 11.00 5/8 9.77 - - - 644.82 - - - - - 1,001.00 - -
Kg 6.00 2.00 1/2 9.77 - - 117.24 - - - - - 117.00 - - -
3.45 Kg 6.00 36.00 3/8 1.37 - 295.92 - - - - - 166.00 - - - -
Kg 6.00 36.00 3/8 1.42 - 306.72 - - - - - 172.00 - - - -
2.60 Kg 6.00 32.00 3/8 1.37 - 263.04 - - - - - 147.00 - - - -
Kg 6.00 32.00 3/8 1.42 - 272.64 - - - - - 153.00 - - - -
C-7 Kg 6.00 6.00 5/8 10.76 - - - 387.36 - - - - - 601.00 - -
3.45 Kg 6.00 36.00 3/8 1.22 - 263.52 - - - - - 148.00 - - - -
2.60 Kg 6.00 32.00 3/8 1.22 - 234.24 - - - - - 131.00 - - - -
C-8 Kg 5.00 8.00 5/8 10.76 - - - 430.40 - - - - - 668.00 - -
3.45 Kg 5.00 36.00 3/8 1.22 - 219.60 - - - - - 123.00 - - - -
2.60 Kg 5.00 32.00 3/8 1.22 - 195.20 - - - - - 109.00 - - - -
C-9 Kg 6.00 4.00 3/8 5.60 - 134.40 - - - - - 75.00 - - - -
3.20 Kg 6.00 32.00 1/4 0.84 161.28 - - - - - 35.00 - - - - -
C-10 Kg 4.00 8.00 5/8 9.77 - - - 312.64 - - - - - 485.00 - -
3.20 Kg 4.00 34.00 3/8 1.42 - 193.12 - - - - - 108.00 - - - -
C-11 Kg 1.00 4.00 3/8 5.60 - 22.40 - - - - - 13.00 - - - -
3.20 Kg 1.00 32.00 1/4 0.59 18.88 - - - - - 4.00 - - - - -
C-12 Kg 1.00 14.00 3/8 5.60 - 78.40 - - - - - 44.00 - - - -
3.20 Kg 1.00 32.00 3/8 1.70 - 54.40 - - - - - 30.00 - - - -
Kg 1.00 34.00 1/4 1.04 35.36 - - - - - 8.00 - - - - -
OTROS
3.28 Kg 1.00 12.00 3/8 3.93 - 47.10 - - - - - 26.00 - - - -
Kg 1.00 16.00 3/8 2.40 - 38.40 - - - - - 22.00 - - - -
2.70 Kg 1.00 12.00 3/8 3.35 - 40.20 - - - - - 23.00 - - - -
Kg 1.00 14.00 3/8 2.40 - 33.60 - - - - - 19.00 - - - -
2.60 Kg 1.00 12.00 3/8 3.25 - 39.00 - - - - - 22.00 - - - -
Kg 1.00 13.00 3/8 2.40 - 31.20 - - - - - 17.00 - - - -
0.85 Kg 1.00 12.00 3/8 1.50 - 18.00 - - - - - 10.00 - - - -
Kg 1.00 4.00 3/8 2.40 - 9.60 - - - - - 5.00 - - - -
1.33 Kg 1.00 12.00 3/8 1.98 - 23.70 - - - - - 13.00 - - - -
Kg 1.00 7.00 3/8 2.40 - 16.80 - - - - - 9.00 - - - -
2.60 Kg 1.00 12.00 3/8 3.25 - 39.00 - - - - - 22.00 - - - -
Kg 1.00 13.00 3/8 2.40 - 31.20 - - - - - 17.00 - - - -
3.00 Kg 1.00 12.00 3/8 3.65 - 43.80 - - - - - 25.00 - - - -
Kg 1.00 15.00 3/8 2.40 - 36.00 - - - - - 20.00 - - - -
04.03.04.00 COLUMNETAS
04.03.04.03 ACERO EN COLUMNETAS fy=4200 kg/cm2 Kg 160.00 433.00 0.00 0.00 0.00 0.00
C-9 Kg 34.00 4.00 3/8 1.88 - 255.68 - - - - - 143.00 - - - -
Kg 40.00 4.00 3/8 2.48 - 396.80 - - - - - 222.00 - - - -
Kg 4.00 4.00 3/8 3.28 - 52.48 - - - - - 29.00 - - - -
1.10 Kg 34.00 8.00 1/4 0.79 214.88 - - - - - 47.00 - - - - -
1.70 Kg 40.00 12.00 1/4 0.79 379.20 - - - - - 83.00 - - - - -
2.50 Kg 4.00 17.00 1/4 0.79 53.72 - - - - - 12.00 - - - - -
C-9 (Pasadiso) Kg 15.00 4.00 3/8 1.15 - 69.00 - - - - - 39.00 - - - -
0.90 Kg 15.00 7.00 1/4 0.79 82.95 - - - - - 18.00 - - - - -
04.03.05.00 VIGAS
04.03.05.03 ACERO EN VIGAS fy=4200 kg/cm2 Kg 0.00 2532.00 2292.00 1885.00 396.00 300.00
1° NIVEL
VP-101 Kg 6.00 2.00 5/8 8.39 - - - 100.68 - - - - - 156.00 - -
Kg 6.00 2.00 5/8 6.59 - - - 79.08 - - - - - 123.00 - -
Kg 6.00 1.00 3/4 3.70 - - - - 22.20 - - - - - 50.00 -
Kg 6.00 2.00 5/8 3.26 - - - 39.09 - - - - - 61.00 - -
Kg 6.00 2.00 3/8 0.46 - 5.46 - - - - - 3.00 - - - -
2.45 Kg 6.00 18.00 3/8 1.02 - 110.16 - - - - - 62.00 - - - -
2.45 Kg 6.00 18.00 3/8 1.02 - 110.16 - - - - - 62.00 - - - -
1.75 Kg 6.00 13.00 3/8 1.14 - 89.23 - - - - - 50.00 - - - -
VP-102 Kg 5.00 3.00 5/8 8.39 - - - 125.85 - - - - - 195.00 - -
Kg 5.00 2.00 5/8 6.59 - - - 65.90 - - - - - 102.00 - -
Kg 5.00 2.00 3/4 3.70 - - - - 37.00 - - - - - 83.00 -
Kg 5.00 2.00 5/8 3.26 - - - 32.58 - - - - - 51.00 - -
Kg 5.00 2.00 3/8 0.46 - 4.55 - - - - - 3.00 - - - -
2.45 Kg 5.00 18.00 3/8 1.02 - 91.80 - - - - - 51.00 - - - -
2.45 Kg 5.00 18.00 3/8 1.02 - 91.80 - - - - - 51.00 - - - -
1.75 Kg 5.00 13.00 3/8 1.14 - 74.36 - - - - - 42.00 - - - -
VP-103 Kg 3.00 3.00 1 8.39 - - - - - 75.51 - - - - - 300.00
Kg 3.00 3.00 3/4 7.04 - - - - 63.36 - - - - - 142.00 -
Kg 3.00 2.00 1/2 6.24 - - 37.44 - - - - - 37.00 - - -
Kg 3.00 3.00 3/4 3.41 - - - - 30.67 - - - - - 69.00 -
Kg 3.00 2.00 3/8 0.46 - 2.73 - - - - - 2.00 - - - -
5.30 Kg 3.00 49.00 3/8 1.02 - 149.94 - - - - - 84.00 - - - -
1.75 Kg 3.00 13.00 3/8 1.14 - 44.62 - - - - - 25.00 - - - -
VS-104a Kg 2.00 4.00 1/2 16.24 - - 129.92 - - - - - 129.00 - - -
Kg 2.00 4.00 1/2 2.15 - - 17.16 - - - - - 17.00 - - -
Kg 2.00 6.00 1/2 3.30 - - 39.60 - - - - - 39.00 - - -
2.78 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.75 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.75 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.78 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
VS-104b Kg 2.00 4.00 1/2 21.84 - - 174.72 - - - - - 174.00 - - -
Kg 2.00 4.00 1/2 2.15 - - 17.16 - - - - - 17.00 - - -
Kg 2.00 10.00 1/2 3.30 - - 66.00 - - - - - 66.00 - - -
2.78 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.75 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.75 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
30/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"Nº DE
ELEMENTOS
2.78 Kg 2.00 22.00 3/8 1.14 - 50.16 - - - - - 28.00 - - - -
2.05 Kg 2.00 19.00 3/8 1.14 - 43.32 - - - - - 24.00 - - - -
2.40 Kg 2.00 20.00 3/8 1.14 - 45.60 - - - - - 26.00 - - - -
VS-104c Kg 2.00 4.00 1/2 4.64 - - 37.12 - - - - - 37.00 - - -
Kg 2.00 4.00 1/2 2.15 - - 17.16 - - - - - 17.00 - - -
3.80 Kg 2.00 27.00 3/8 1.14 - 61.56 - - - - - 34.00 - - - -
Vaa Kg 1.00 4.00 1/2 16.05 - - 64.20 - - - - - 64.00 - - -
3.43 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.40 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.40 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.43 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
Vab Kg 1.00 4.00 1/2 21.65 - - 86.60 - - - - - 86.00 - - -
3.43 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.40 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.40 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
3.43 Kg 1.00 21.00 3/8 0.75 - 15.75 - - - - - 9.00 - - - -
2.05 Kg 1.00 14.00 3/8 0.75 - 10.50 - - - - - 6.00 - - - -
3.05 Kg 1.00 19.00 3/8 0.75 - 14.25 - - - - - 8.00 - - - -
Vac Kg 1.00 4.00 1/2 5.45 - - 21.80 - - - - - 22.00 - - -
3.80 Kg 1.00 23.00 3/8 0.75 - 17.25 - - - - - 10.00 - - - -
NIVEL INTERMEDIO
VIGA DE ARRIOSTRE Kg 11.00 4.00 1/2 6.74 - - 296.56 - - - - - 295.00 - - -
2.45 Kg 11.00 17.00 3/8 1.02 - 190.74 - - - - - 107.00 - - - -
2.45 Kg 11.00 17.00 3/8 1.02 - 190.74 - - - - - 107.00 - - - -
TECHO
VS-204a Kg 2.00 2.00 1/2 16.84 - - 67.36 - - - - - 67.00 - - -
Kg 2.00 2.00 1/2 16.24 - - 64.96 - - - - - 65.00 - - -
Kg 2.00 2.00 1/2 2.35 - - 9.40 - - - - - 9.00 - - -
0.80 Kg 2.00 5.00 3/8 0.86 - 8.62 - - - - - 5.00 - - - -
2.78 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.75 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.75 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.78 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
VS-204b Kg 2.00 2.00 1/2 21.64 - - 86.56 - - - - - 86.00 - - -
Kg 2.00 2.00 1/2 21.84 - - 87.36 - - - - - 87.00 - - -
2.78 Kg 2.00 19.00 3/8 0.86 - 32.76 - - - - - 18.00 - - - -
2.75 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.75 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.78 Kg 2.00 25.00 3/8 1.15 - 57.44 - - - - - 32.00 - - - -
2.05 Kg 2.00 20.00 3/8 1.15 - 45.95 - - - - - 26.00 - - - -
2.40 Kg 2.00 23.00 3/8 1.15 - 52.84 - - - - - 30.00 - - - -
VS-204c Kg 2.00 2.00 1/2 5.24 - - 20.96 - - - - - 21.00 - - -
Kg 2.00 2.00 1/2 4.64 - - 18.56 - - - - - 18.00 - - -
3.80 Kg 2.00 25.00 3/8 0.86 - 43.11 - - - - - 24.00 - - - -
0.80 Kg 2.00 5.00 3/8 0.86 - 8.62 - - - - - 5.00 - - - -
VAa Kg 2.00 4.00 1/2 16.85 - - 134.80 - - - - - 134.00 - - -
0.80 Kg 2.00 6.00 3/8 0.75 - 9.00 - - - - - 5.00 - - - -
3.43 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.40 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.40 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.43 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
VAb Kg 2.00 4.00 1/2 21.65 - - 173.20 - - - - - 172.00 - - -
3.43 Kg 2.00 19.00 3/8 0.75 - 28.50 - - - - - 16.00 - - - -
3.40 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.40 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
3.43 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
2.05 Kg 2.00 14.00 3/8 0.75 - 21.00 - - - - - 12.00 - - - -
3.05 Kg 2.00 19.00 3/8 0.75 - 28.50 - - - - - 16.00 - - - -
VAc Kg 2.00 4.00 1/2 5.25 - - 42.00 - - - - - 42.00 - - -
3.80 Kg 2.00 21.00 3/8 0.75 - 31.50 - - - - - 18.00 - - - -
0.80 Kg 2.00 5.00 3/8 0.86 - 8.62 - - - - - 5.00 - - - -
VA-2 Kg 4.00 4.00 1/2 5.71 - - 91.30 - - - - - 91.00 - - -
1.95 Kg 4.00 14.00 3/8 0.75 - 42.00 - - - - - 24.00 - - - -
2.65 Kg 4.00 17.00 3/8 0.75 - 51.00 - - - - - 29.00 - - - -
V-201 (Frontal) Kg 6.00 2.00 5/8 7.08 - - - 84.96 - - - - - 132.00 - -
Kg 6.00 1.00 3/4 3.91 - - - - 23.44 - - - - - 52.00 -
Kg 6.00 2.00 5/8 4.88 - - - 58.52 - - - - - 91.00 - -
Kg 6.00 2.00 5/8 2.93 - - - 35.20 - - - - - 55.00 - -
3.18 Kg 6.00 28.00 3/8 1.02 - 171.36 - - - - - 96.00 - - - -
2.11 Kg 6.00 17.00 3/8 1.20 - 122.40 - - - - - 69.00 - - - -
V-201 (Posterior) Kg 6.00 2.00 5/8 6.03 - - - 72.34 - - - - - 112.00 - -
Kg 6.00 2.00 5/8 4.95 - - - 59.45 - - - - - 92.00 - -
Kg 6.00 2.00 1/2 2.50 - - 30.05 - - - - - 30.00 - - -
3.21 Kg 6.00 28.00 3/8 1.02 - 171.36 - - - - - 96.00 - - - -
0.78 Kg 6.00 6.00 3/8 1.20 - 43.20 - - - - - 24.00 - - - -
V-202 (Frontal) Kg 5.00 2.00 5/8 7.08 - - - 70.80 - - - - - 110.00 - -
Kg 5.00 1.00 5/8 3.91 - - - 19.53 - - - - - 30.00 - -
Kg 5.00 2.00 5/8 4.88 - - - 48.77 - - - - - 76.00 - -
Kg 5.00 2.00 5/8 2.93 - - - 29.33 - - - - - 46.00 - -
3.18 Kg 5.00 28.00 3/8 1.02 - 142.80 - - - - - 80.00 - - - -
2.11 Kg 5.00 17.00 3/8 1.20 - 102.00 - - - - - 57.00 - - - -
V-202 (Posterior) Kg 5.00 2.00 5/8 6.03 - - - 60.28 - - - - - 94.00 - -
Kg 5.00 2.00 5/8 4.95 - - - 49.54 - - - - - 77.00 - -
Kg 5.00 2.00 1/2 2.50 - - 25.04 - - - - - 25.00 - - -
3.21 Kg 5.00 28.00 3/8 1.02 - 142.80 - - - - - 80.00 - - - -
0.78 Kg 5.00 6.00 3/8 1.20 - 36.00 - - - - - 20.00 - - - -
V-203 (Frontal) Kg 3.00 2.00 5/8 7.20 - - - 43.18 - - - - - 67.00 - -
Kg 3.00 2.00 5/8 4.13 - - - 24.76 - - - - - 38.00 - -
Kg 3.00 2.00 5/8 5.06 - - - 30.36 - - - - - 47.00 - -
Kg 3.00 2.00 5/8 2.95 - - - 17.67 - - - - - 27.00 - -
3.31 Kg 3.00 27.00 3/8 1.02 - 82.62 - - - - - 46.00 - - - -
2.11 Kg 3.00 17.00 3/8 1.20 - 61.20 - - - - - 34.00 - - - -
V-203 (Posterior) Kg 3.00 2.00 5/8 6.03 - - - 36.18 - - - - - 56.00 - -
Kg 3.00 2.00 5/8 5.01 - - - 30.08 - - - - - 47.00 - -
Kg 3.00 2.00 1/2 2.50 - - 15.02 - - - - - 15.00 - - -
3.34 Kg 3.00 27.00 3/8 1.02 - 82.62 - - - - - 46.00 - - - -
0.78 Kg 3.00 6.00 3/8 1.20 - 21.60 - - - - - 12.00 - - - -
VIGA CORONAa Kg 1.00 10.00 1/2 16.35 - - 163.50 - - - - - 163.00 - - -
0.80 Kg 1.00 3.00 3/8 2.33 - 6.99 - - - - - 4.00 - - - -
3.43 Kg 1.00 17.00 3/8 2.33 - 39.61 - - - - - 22.00 - - - -
3.40 Kg 1.00 16.00 3/8 2.33 - 37.28 - - - - - 21.00 - - - -
3.40 Kg 1.00 16.00 3/8 2.33 - 37.28 - - - - - 21.00 - - - -
3.43 Kg 1.00 17.00 3/8 2.33 - 39.61 - - - - - 22.00 - - - -
31/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"Nº DE
ELEMENTOS
VIGA CORONAb Kg 1.00 10.00 1/2 21.65 - - 216.50 - - - - - 215.00 - - -
3.43 Kg 1.00 17.00 3/8 2.33 - 39.61 - - - - - 22.00 - - - -
3.40 Kg 1.00 16.00 3/8 2.33 - 37.28 - - - - - 21.00 - - - -
3.40 Kg 1.00 16.00 3/8 2.33 - 37.28 - - - - - 21.00 - - - -
3.43 Kg 1.00 17.00 3/8 2.33 - 39.61 - - - - - 22.00 - - - -
2.05 Kg 1.00 10.00 3/8 2.33 - 23.30 - - - - - 13.00 - - - -
3.05 Kg 1.00 15.00 3/8 2.33 - 34.95 - - - - - 20.00 - - - -
VIGA CORONAc Kg 1.00 10.00 1/2 5.25 - - 52.50 - - - - - 52.00 - - -
3.80 Kg 1.00 18.00 3/8 2.33 - 41.94 - - - - - 23.00 - - - -
0.80 Kg 1.00 3.00 3/8 2.33 - 6.99 - - - - - 4.00 - - - -
04.03.06.00 VIGAS DE AMARRE
04.03.06.03 ACERO EN VIGAS DE AMARRE fy=4200 kg/cm2 Kg 25.00 184.00 0.00 0.00 0.00 0.00
VA Kg 16.00 2.00 3/8 3.08 - 98.56 - - - - - 55.00 - - - -
Kg 32.00 2.00 3/8 3.05 - 195.20 - - - - - 109.00 - - - -
2.23 Kg 16.00 11.00 1/4 0.21 36.96 - - - - - 8.00 - - - - -
2.20 Kg 32.00 10.00 1/4 0.21 67.20 - - - - - 15.00 - - - - -
VA (Pasadiso) Kg 11.00 2.00 3/8 1.61 - 35.42 - - - - - 20.00 - - - -
0.76 Kg 11.00 3.00 1/4 0.21 6.93 - - - - - 2.00 - - - - -
04.03.07.00 LOSA ALIGERADA
04.03.07.03 ACERO EN LOSA ALIGERADA fy=4200 kg/cm2 Kg 748.00 0.00 4203.00 0.00 0.00 0.00
Aulas As (-) Kg 14.00 2.00 1/2 1.58 - - 44.10 - - - - - 44.00 - - -
Kg 14.00 3.00 1/2 2.65 - - 111.30 - - - - - 111.00 - - -
Aulas As (+) Kg 14.00 2.00 1/2 15.35 - - 429.80 - - - - - 427.00 - - -
Voladizo As (-) Kg 4.00 2.00 1/2 1.58 - - 12.60 - - - - - 13.00 - - -
Kg 4.00 3.00 1/2 2.65 - - 31.80 - - - - - 32.00 - - -
Voladizo As (+) Kg 4.00 2.00 1/2 15.35 - - 122.80 - - - - - 122.00 - - -
As Temperatura Kg 4.00 13.00 1/4 8.45 439.40 - - - - - 97.00 - - - - -
Aulas As (-) Kg 14.00 2.00 1/2 1.58 - - 44.10 - - - - - 44.00 - - -
Kg 14.00 5.00 1/2 2.65 - - 185.50 - - - - - 184.00 - - -
Aulas As (+) Kg 14.00 2.00 1/2 21.45 - - 600.60 - - - - - 597.00 - - -
Voladizo As (-) Kg 4.00 2.00 1/2 1.58 - - 12.60 - - - - - 13.00 - - -
Kg 4.00 5.00 1/2 2.65 - - 53.00 - - - - - 53.00 - - -
Voladizo As (+) Kg 4.00 2.00 1/2 21.45 - - 171.60 - - - - - 171.00 - - -
Voladizo As (-) Kg 4.00 5.00 1/2 1.67 - - 33.50 - - - - - 33.00 - - -
Voladizo As (+) Kg 4.00 2.00 1/2 4.25 - - 34.00 - - - - - 34.00 - - -
As Temperatura Kg 6.20 13.00 1/4 8.45 681.07 - - - - - 150.00 - - - - -
Aulas As (-) Kg 12.00 2.00 1/2 2.38 - - 57.00 - - - - - 57.00 - - -
Kg 12.00 3.00 1/2 2.65 - - 95.40 - - - - - 95.00 - - -
Aulas As (+) Kg 12.00 2.00 1/2 17.75 - - 426.00 - - - - - 423.00 - - -
Voladizo As (-) Kg 6.00 2.00 1/2 2.38 - - 28.50 - - - - - 28.00 - - -
Kg 6.00 3.00 1/2 2.65 - - 47.70 - - - - - 47.00 - - -
Voladizo As (+) Kg 6.00 2.00 1/2 17.75 - - 213.00 - - - - - 212.00 - - -
As Temperatura Kg 6.00 13.00 1/4 9.75 760.50 - - - - - 167.00 - - - - -
Aulas As (-) Kg 12.00 2.00 1/2 1.58 - - 37.80 - - - - - 38.00 - - -
Kg 12.00 5.00 1/2 2.65 - - 159.00 - - - - - 158.00 - - -
Aulas As (+) Kg 12.00 2.00 1/2 23.05 - - 553.20 - - - - - 550.00 - - -
Voladizo As (-) Kg 6.00 2.00 1/2 2.38 - - 28.50 - - - - - 28.00 - - -
Kg 6.00 5.00 1/2 2.65 - - 79.50 - - - - - 79.00 - - -
Voladizo As (+) Kg 6.00 2.00 1/2 23.05 - - 276.60 - - - - - 275.00 - - -
As Temperatura Kg 6.00 13.00 1/4 9.75 760.50 - - - - - 167.00 - - - - -
Aulas As (-) Kg 12.00 2.00 1/2 2.38 - - 57.00 - - - - - 57.00 - - -
Aulas As (+) Kg 12.00 2.00 1/2 7.15 - - 171.60 - - - - - 171.00 - - -
Voladizo As (-) Kg 6.00 2.00 1/2 2.38 - - 28.50 - - - - - 28.00 - - -
Voladizo As (+) Kg 6.00 2.00 1/2 6.65 - - 79.80 - - - - - 79.00 - - -
As Temperatura Kg 6.00 13.00 1/4 9.75 760.50 - - - - - 167.00 - - - - -
04.03.08.00 ESCALERA
04.03.08.03 ACERO EN ESCALERA fy = 4,200 kg/cm2 Kg 0.00 140.00 260.00 0.00 0.00 0.00
1° Tramo
Kg 1.00 11.00 1/2 4.68 - - 51.48 - - - - - 51.00 - - -
Kg 1.00 20.00 3/8 1.68 - 33.60 - - - - - 19.00 - - - -
Kg 1.00 11.00 3/8 1.92 - 21.12 - - - - - 12.00 - - - -
Kg 1.00 11.00 3/8 1.68 - 18.48 - - - - - 10.00 - - - -
Kg 1.00 11.00 3/8 1.35 - 14.85 - - - - - 8.00 - - - -
Kg 1.00 4.00 3/8 1.68 - 6.72 - - - - - 4.00 - - - -
Kg 1.00 11.00 1/2 3.54 - - 38.94 - - - - - 39.00 - - -
Kg 1.00 18.00 3/8 1.76 - 31.68 - - - - - 18.00 - - - -
Kg 1.00 11.00 1/2 3.00 - - 33.00 - - - - - 33.00 - - -
Kg 1.00 11.00 3/8 1.76 - 19.36 - - - - - 11.00 - - - -
2° Tramo
.101.20
2.24
3.57 .68
.43
1.20
0.55.17
.17
.450.73
.10.45
2.45
1.68
1.68
1.68
1.76
1.76
32/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 2
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"Nº DE
ELEMENTOS
Kg 1.00 11.00 1/2 2.55 - - 28.05 - - - - - 28.00 - - -
Kg 1.00 10.00 3/8 1.76 - 17.60 - - - - - 10.00 - - - -
Kg 1.00 11.00 1/2 3.70 - - 40.70 - - - - - 40.00 - - -
Kg 1.00 10.00 3/8 1.76 - 17.60 - - - - - 10.00 - - - -
Kg 1.00 11.00 3/8 2.01 - 22.11 - - - - - 12.00 - - - -
Kg 1.00 9.00 3/8 1.76 - 15.84 - - - - - 9.00 - - - -
Kg 1.00 11.00 1/2 4.36 - - 47.96 - - - - - 48.00 - - -
Kg 1.00 11.00 3/8 1.68 - 18.48 - - - - - 10.00 - - - -
Kg 1.00 11.00 1/2 1.96 - - 21.56 - - - - - 21.00 - - -
Kg 1.00 7.00 3/8 1.68 - 11.76 - - - - - 7.00 - - - -
04.03.09.00 MURO INTERMEDIO DE ESCALERA
04.03.09.03 ACERO EN MURO INTERMEDIO DE ESCALERA fy=4200 kg/cm2 Kg 0.00 0.00 310.00 0.00 0.00 0.00
Kg 1.00 15.00 1/2 6.56 - - 98.32 - - - - - 98.00 - - -
Kg 1.00 6.00 1/2 6.56 - - 39.33 - - - - - 39.00 - - -
6.31 Kg 1.00 33.00 1/2 1.68 - - 55.44 - - - - - 55.00 - - -
6.31 Kg 1.00 33.00 1/2 3.59 - - 118.47 - - - - - 118.00 - - -
04.03.10.00 GARGOLAS
04.03.10.03 ACERO EN GARGOLAS fy=4200 kg/cm2 Kg 1.09 0.00 0.00 0.00 0.00 0.00
Kg 3.00 2.00 1/4 0.46 2.78 - - - - - 0.62 - - - - -
Kg 3.00 2.00 1/4 0.35 2.10 - - - - - 0.47 - - - - -
04.03.11.00 MESON PARA LAVATORIOS OVALINES
04.03.11.03 ACERO EN MESON fy=4200 kg/cm2 Kg 0.00 56.00 0.00 0.00 0.00 0.00
2.85 Kg 2.00 14.00 3/8 3.15 - 88.20 - - - - - 49.00 - - - -
0.58 Kg 2.00 3.00 3/8 0.73 - 4.35 - - - - - 2.00 - - - -
1.05 Kg 1.00 5.00 3/8 1.35 - 6.75 - - - - - 4.00 - - - -
0.58 Kg 1.00 3.00 3/8 0.73 - 2.18 - - - - - 1.00 - - - -
.60
3.0.10
4.010.35
1.460.50
.102.45
1.76
1.76
1.31
0.7
1.76
1.68
1.68
33/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 3
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
04.01.00.00 MOVIMIENTO DE TIERRAS
04.01.01.00 EXCAVACIONES DE ZANJAS EN ZAPATAS-CIMIENTOS CORRIDOS 44.77
Exc. Zapatas
Zapatas (Z-1) 2.00 1.00 8.33 1.50 1.40 34.97
Zapatas (Z-2) 2.00 1.00 3.50 1.00 1.40 9.80
04.01.02.00 RELLENO COMPACTADO DE MATERIAL PROPIO, C/EQUIPO 17.83
Volumen de Excavación 44.77
Volumen de Concreto 26.94
Volumen de Concreto de Solado 3.20
Volumen de Concreto de Zapata 19.19
Volumen de Concreto de Viga de Cimentación 4.55
04.01.03.00 RELLENO COMPACTADO DE MATERIAL DE PRESTAMO, ARENILLA, C/EQUIPO 17.87
EJE X-X, W-W 2.00 2.00 8.33 0.60 0.60 11.99
EJE Y-Y, Z-Z 2.00 2.00 3.50 0.70 0.60 5.88
04.01.04.00 RELLENO COMPACTADO DE MATERIAL DE PRESTAMO, AFIRMADO, C/EQUIPO 5.41
1.00 1.00 8.33 6.50 0.10 5.41
04.01.05.00 ACARREO DE MATERIAL PROCEDENTE DE EXCAVACIONES 44.77
04.01.06.00 ELIMINACION MATERIAL EXCEDENTE 29.63
Volumen de Excavación 44.77
Volumen de Relleno Compactado con Material Propio 17.83
Factor de Esponjamiento 1.10
04.02.00.00 CONCRETO SIMPLE
04.02.01.00 SOLADO e=4" PARA ZAPATAS Y VIGAS DE CIMENTACION f'c=100 kg/cm2 M² 31.98
Zapatas
Zapatas (Z-1) M² 2.00 1.00 8.33 1.50 24.98
Zapatas (Z-2) M² 2.00 1.00 3.50 1.00 7.00
04.02.02.00 CONCRETO EN CIMIENTOS CORRIDOS f'c=120 kg/cm2 + 30% P.G. 0.00
04.02.03.00 ENCOFRADO Y DESENCOFRADO DE CIMIENTOS CORRIDOS M² 0.00
04.02.04.00 CONCRETO EN SOBRECIMIENTOS f'c=120 kg/cm2 + 25% P.M. 0.00
04.02.05.00 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS M² 0.00
04.02.06.00 FALSO PISO f'c=140 kg/cm2 M² 54.11
M² 1.00 1.00 8.33 6.50 54.11
04.03.00.00 CONCRETO ARMADO
04.03.01.00 ZAPATAS
04.03.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 19.19
Zapatas (Z-1) M² 2.00 1.00 8.33 1.50 0.60 14.99
Zapatas (Z-2) M² 2.00 1.00 3.50 1.00 0.60 4.20
04.03.01.02 ACERO EN ZAPATAS fy=4200 kg/cm2 Kg 641.00
04.03.02.00 VIGAS DE CIMENTACION
04.03.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 kg/cm2 9.42
EJE X-X, W-W 2.00 1.00 6.13 0.30 1.45 5.33
EJE Y-Y, Z-Z 2.00 1.00 4.70 0.30 1.45 4.09
04.03.02.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS DE CIMENTACION M² 62.79
EJE X-X, W-W 2.00 2.00 6.13 1.45 35.53
EJE Y-Y, Z-Z 2.00 2.00 4.70 1.45 27.26
04.03.02.03 ACERO EN VIGAS DE CIMENTACION fy=4200 kg/cm2 Kg 716.00
04.03.03.00 COLUMNAS
04.03.03.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 10.19
C-1 4.00 1.00 0.60 0.30 7.80 5.62
4.00 1.00 0.60 0.30 6.35 4.57
04.03.03.02 ENCOFRADO Y DESCENCOFRADO DE COLUMNAS M² 47.00
CANT.REP.
N°ELEM.
M³
M³M³
M³
M³
M³
M³M³M³
M³
M³M³
M³
M³
M³
M³
M³M³
M³
M³
M³
M³
M³M³
M³M³
M³
M³M³
34/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 3
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
COLUMNA 0.60x0.30 2.00 1.00 0.60 7.68 9.21
2.00 2.00 0.60 3.44 8.25
2.00 1.00 0.60 6.03 7.23
2.00 2.00 0.60 2.86 6.86
2.00 1.00 0.30 7.84 4.70
2.00 2.00 0.30 3.30 3.96
2.00 1.00 0.30 6.28 3.77
2.00 2.00 0.30 2.52 3.02
04.03.03.03 ACERO EN COLUMNAS fy=4200 kg/cm2 Kg 876.00
04.03.04.00 COLUMNETAS
04.03.04.01 CONCRETO EN COLUMNETAS f'c=210 kg/cm2 0.30
PARAPETOS 1.00 8.00 0.25 0.15 1.00 0.30
04.03.04.02 ENCOFRADO Y DESCENCOFRADO DE COLUMNETAS M² 4.00
PARAPETOS 8.00 2.00 0.25 1.00 4.00
04.03.04.03 ACERO EN COLUMNETAS fy=4200 kg/cm2 Kg 31.00
04.03.05.00 VIGAS
04.03.05.01 CONCRETO EN VIGAS f'c=210 kg/cm2 10.33
EJE X-X, W-W 2.00 1.00 6.13 0.30 0.65 2.39
2.00 1.00 0.55 0.30 0.30 0.10
EJE Y-Y, Z-Z 2.00 1.00 4.70 0.30 0.50 1.41
1.00 1.00 4.70 0.25 0.25 0.29
EJE X-X, W-W 2.00 1.00 6.13 0.30 0.70 2.55
2.00 1.00 0.55 0.30 0.35 0.12
EJE Y-Y, Z-Z 2.00 1.00 4.70 0.30 0.50 1.41
1.00 1.00 4.70 0.30 0.30 0.42
POSTERIOR 1.00 1.00 7.88 0.20 0.17 0.27
VIGAS EN TECHO 1.00 1.00 6.53 0.80 0.17 0.89
VS-203 1.00 1.00 6.50 0.44 0.17 0.49
04.03.05.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS M² 69.03
VP-1 M² 2.00 1.00 6.10 1.40 17.08
M² 1.00 1.00 6.10 1.27 7.76
M² 1.00 1.00 6.10 1.48 9.04
VS M² 2.00 1.00 4.55 1.05 9.56
M² 2.00 1.00 5.12 1.14 11.61
VA-1 M² 1.00 1.00 6.10 0.45 2.75
M² 1.00 1.00 0.25 0.20 0.05
VA-2 M² 2.00 1.00 0.60 0.75 0.90
M² 1.00 1.00 4.55 0.40 1.82
VIGAS EN TECHO 1.00 1.00 6.53 0.80 5.22
VS-203 1.00 1.00 6.50 0.50 3.25
04.03.05.03 ACERO EN VIGAS fy=4200 kg/cm2 Kg 1,835.00
04.03.06.00 VIGAS DE AMARRES
04.03.06.01 CONCRETO EN VIGAS DE AMARRES f'c=210 kg/cm2 0.51
PARAPETOS 1.00 3.00 5.30 0.15 0.10 0.24
1.00 3.00 5.30 0.15 0.10 0.24
2.00 2.00 0.60 0.15 0.10 0.04
04.03.06.02 ENCOFRADO Y DESCENCOFRADO DE VIGAS DE AMARRES M² 5.98
M² 1.00 3.00 5.30 0.18 2.78
M² 1.00 3.00 5.30 0.18 2.78
M² 2.00 2.00 0.60 0.18 0.42
04.03.06.03 ACERO EN VIGAS DE AMARRES fy=4200 kg/cm2 Kg 61.00
04.03.07.00 LOSA ALIGERADA
04.03.07.01 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2 9.75
1.00 1.00 6.70 4.55 0.25 7.62
1.00 1.00 6.70 5.12 0.25 8.58
1.00 1.00 6.70 0.75 0.25 1.26
1.00 1.00 0.30 4.55 0.25 0.34
1.00 1.00 0.30 5.12 0.25 0.38
1.00 1.00 0.30 0.75 0.25 0.06
M²M²M²M²M²M²M²M²
M³
M²
M²
M³
M³M³M³M³M³M³M³M³M³M³M³
M³M³
M³
M³M³M³
M³
M³M³M³M³M³M³
35/38HOJA DE METRADOS DE ESTRUCTURAS - MODULO 3
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.MEDIDAS
TOTALLARGO ANCHO ALTURA
CANT.REP.
N°ELEM.
04.03.07.02 ENCOFRADO Y DESCENCOFRADO DE LOSA ALIGERADA M² 75.28
1.00 1.00 6.70 4.70 31.49
1.00 1.00 6.70 5.30 35.51
1.00 1.00 6.70 0.75 5.05
1.00 1.00 0.30 4.70 1.41
1.00 1.00 0.30 5.30 1.59
1.00 1.00 0.30 0.75 0.23
04.03.07.03 ACERO EN LOSA ALIGERADA fy=4200 kg/cm2 Kg 1,158.00
04.03.07.04 LADRILLO DE ARCILLA 15x30x30 CM PARA LOSA ALIGERADA Und 472.00
04.03.08.00 ESCALERA
04.03.08.01 CONCRETO EN ESCALERA f'c=210 kg/cm2 0.00
04.03.08.02 ENCOFRADO Y DESCENCOFRADO DE ESCALERA M² 0.00
04.03.08.03 ACERO EN ESCALERA fy=4200 kg/cm2 Kg 0.00
04.03.09.00 MURO INTERMEDIO DE ESCALERA
04.03.09.01 CONCRETO EN MURO INTERMEDIO DE ESCALERA f'c=210 kg/cm2 0.00
04.03.09.02 ENCOFRADO Y DESCENCOFRADO DE MURO INTERMEDIO DE ESCALERA M² 0.00
04.03.09.03 ACERO EN MURO INTERMEDIO DE ESCALERA fy=4200 kg/cm2 Kg 0.00
04.03.10.00 GARGOLAS
04.03.10.01 CONCRETO EN GARGOLAS f'c=175 kg/cm2 0.00
04.03.10.02 ENCOFRADO Y DESCENCOFRADO DE GARGOLAS M² 0.00
04.03.10.03 ACERO EN GARGOLAS fy=4200 kg/cm2 Kg 0.00
04.03.11.00 MESON PARA LAVATORIOS OVALINES
04.03.11.01 CONCRETO EN MESON f'c=210 kg/cm2 0.00
04.03.11.02 ENCOFRADO Y DESCENCOFRADO DE MESON M² 0.00
04.03.11.03 ACERO EN MESON fy=4200 kg/cm2 Kg 0.00
M³M³M³M³M³M³
M³
M³
M³
M³
36/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 3
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"
04.03.00.00 OBRAS DE CONCRETO ARMADO
04.03.01.00 ZAPATAS
04.03.01.02 ACERO EN ZAPATAS fy=4200 kg/cm2 Kg 0.00 0.00 0.00 641.00 0.00 0.00
Z-1 (1.50) Kg 2.00 6.00 5/8 8.17 - - - 98.10 - - - - - 152.00 - -
6.13 Kg 2.00 37.00 5/8 1.35 - - - 99.90 - - - - - 155.00 - -
Z-2 (1.00) Kg 2.00 4.00 5/8 22.65 - - - 181.20 - - - - - 281.00 - -
3.50 Kg 2.00 20.00 5/8 0.85 - - - 34.00 - - - - - 53.00 - -
04.03.02.00 VIGAS DE CIMENTACION
04.03.02.03 ACERO EN VIGAS DE CIMENTACIÓN: f'y = 4,200 kg/cm² Kg 0.00 408.00 0.00 308.00 0.00 0.00
VC (7.325) Kg 2.00 12.00 3/8 7.67 - 183.96 - - - - - 103.00 - - - -
Kg 2.00 6.00 5/8 7.67 - - - 91.98 - - - - - 143.00 - -
6.13 Kg 2.00 27.00 3/8 3.46 - 186.84 - - - - - 105.00 - - - -
VC (5.30) Kg 2.00 12.00 3/8 8.87 - 212.76 - - - - - 119.00 - - - -
Kg 2.00 6.00 5/8 8.87 - - - 106.38 - - - - - 165.00 - -
4.70 Kg 2.00 21.00 3/8 3.46 - 145.32 - - - - - 81.00 - - - -
04.03.03.00 COLUMNAS
04.03.03.03 ACERO EN COLUMNAS fy=4200 kg/cm2 Kg 0.00 334.00 0.00 0.00 542.00 0.00
C-1 Kg 2.00 8.00 3/4 8.30 - - - - 132.80 - - - - - 297.00 -
7.68 Kg 2.00 57.00 3/8 1.72 - 196.08 - - - - - 110.00 - - - -
3.44 Kg 2.00 34.00 3/8 1.72 - 116.96 - - - - - 65.00 - - - -
C-1 Kg 2.00 8.00 3/4 6.85 - - - - 109.60 - - - - - 245.00 -
6.03 Kg 2.00 49.00 3/8 1.72 - 168.56 - - - - - 94.00 - - - -
2.86 Kg 2.00 34.00 3/8 1.72 - 116.96 - - - - - 65.00 - - - -
04.03.04.00 COLUMNETAS
04.03.04.03 ACERO EN COLUMNETAS fy=4200 kg/cm2 Kg 10.00 21.00 0.00 0.00 0.00 0.00
C-9 (Pasadiso) Kg 8.00 4.00 3/8 1.15 - 36.80 - - - - - 21.00 - - - -
0.90 Kg 8.00 7.00 1/4 0.79 44.24 - - - - - 10.00 - - - - -
04.03.05.00 VIGAS
04.03.05.03 ACERO EN VIGAS fy=4200 kg/cm2 Kg 0.00 586.00 381.00 110.00 374.00 384.00
1° NIVEL
VP-1 Kg 2.00 3.00 1 8.07 - - - - - 48.39 - - - - - 192.00
Kg 2.00 3.00 1 8.07 - - - - - 48.39 - - - - - 192.00
Kg 2.00 2.00 1/2 7.27 - - 29.06 - - - - - 29.00 - - -
Kg 2.00 4.00 1/2 1.77 - - 14.16 - - - - - 14.00 - - -
6.13 Kg 2.00 44.00 3/8 1.82 - 160.16 - - - - - 90.00 - - - -
0.55 Kg 2.00 5.00 3/8 1.14 - 11.40 - - - - - 6.00 - - - -
VP-2 Kg 2.00 6.00 3/4 5.89 - - - - 70.68 - - - - - 158.00 -
Kg 2.00 2.00 1/2 5.24 - - 20.96 - - - - - 21.00 - - -
4.70 Kg 2.00 35.00 3/8 1.52 - 106.40 - - - - - 60.00 - - - -
VS2 Kg 1.00 4.00 1/2 5.89 - - 23.56 - - - - - 23.00 - - -
4.70 Kg 1.00 33.00 3/8 1.52 - 50.16 - - - - - 28.00 - - - -
TECHO
VP-1 Kg 2.00 3.00 3/4 8.07 - - - - 48.39 - - - - - 108.00 -
Kg 2.00 3.00 3/4 8.07 - - - - 48.39 - - - - - 108.00 -
Kg 2.00 2.00 1/2 7.27 - - 29.06 - - - - - 29.00 - - -
Kg 2.00 4.00 1/2 1.77 - - 14.16 - - - - - 14.00 - - -
6.13 Kg 2.00 44.00 3/8 1.92 - 168.96 - - - - - 95.00 - - - -
0.55 Kg 2.00 5.00 3/8 1.24 - 12.40 - - - - - 7.00 - - - -
VP-2 Kg 2.00 6.00 5/8 5.89 - - - 70.68 - - - - - 110.00 - -
Kg 2.00 2.00 1/2 5.24 - - 20.96 - - - - - 21.00 - - -
4.70 Kg 2.00 35.00 3/8 1.52 - 106.40 - - - - - 60.00 - - - -
VS2 Kg 1.00 4.00 1/2 5.89 - - 23.56 - - - - - 23.00 - - -
4.70 Kg 1.00 33.00 3/8 1.52 - 50.16 - - - - - 28.00 - - - -
VS3 Kg 2.00 4.00 1/2 2.02 - - 16.16 - - - - - 16.00 - - -
4.70 Kg 2.00 33.00 3/8 1.52 - 100.32 - - - - - 56.00 - - - -
VS Kg 2.00 4.00 1/2 8.02 - - 64.12 - - - - - 64.00 - - -
6.73 Kg 2.00 38.00 3/8 1.92 - 145.92 - - - - - 82.00 - - - -
0.40 Kg 2.00 4.00 3/8 1.24 - 9.92 - - - - - 6.00 - - - -
VIGA CORONA Kg 1.00 10.00 1/2 8.03 - - 80.25 - - - - - 80.00 - - -
6.13 Kg 1.00 33.00 3/8 2.00 - 66.00 - - - - - 37.00 - - - -
0.40 Kg 1.00 4.00 3/8 2.00 - 8.00 - - - - - 4.00 - - - -
VS-203 Kg 1.00 6.00 1/2 7.82 - - 46.92 - - - - - 47.00 - - -
6.13 Kg 1.00 33.00 3/8 1.28 - 42.24 - - - - - 24.00 - - - -
0.40 Kg 1.00 4.00 3/8 1.28 - 5.12 - - - - - 3.00 - - - -
04.03.06.00 VIGAS DE AMARRE
04.03.06.03 ACERO EN VIGAS DE AMARRE fy=4200 kg/cm2 Kg 8.00 53.00 0.00 0.00 0.00 0.00
VA (Pasadiso) Kg 6.00 2.00 3/8 6.40 - 76.80 - - - - - 43.00 - - - -
5.55 Kg 6.00 27.00 1/4 0.21 34.02 - - - - - 7.00 - - - - -
VA (Pasadiso) Kg 6.00 2.00 3/8 1.50 - 18.00 - - - - - 10.00 - - - -
0.65 Kg 6.00 3.00 1/4 0.21 3.78 - - - - - 1.00 - - - - -
04.03.07.00 LOSA ALIGERADA
04.03.07.03 ACERO EN LOSA ALIGERADA fy=4200 kg/cm2 Kg 294.00 143.00 255.00 466.00 0.00 0.00
HALL As (-) Kg 11.00 1.00 5/8 2.68 - - - 29.42 - - - - - 46.00 - -
Kg 11.00 1.00 5/8 3.23 - - - 35.48 - - - - - 55.00 - -
HALL As (+) Kg 11.00 1.00 5/8 7.83 - - - 86.13 - - - - - 134.00 - -
HALL As (-) Kg 16.00 2.00 5/8 2.03 - - - 64.80 - - - - - 101.00 - -
HALL As (+) Kg 16.00 1.00 5/8 5.25 - - - 84.00 - - - - - 130.00 - -
As Temperatura Kg 4.00 18.00 1/4 8.13 585.00 - - - - - 129.00 - - - - -
As Temperatura Kg 4.00 26.00 1/4 5.55 577.20 - - - - - 127.00 - - - - -
Aulas As (-) Kg 16.00 1.00 1/2 2.21 - - 35.36 - - - - - 35.00 - - -
Kg 16.00 1.00 1/2 3.71 - - 59.36 - - - - - 59.00 - - -
Aulas As (-) Kg 16.00 1.00 3/8 2.21 - 35.36 - - - - - 20.00 - - - -
Kg 16.00 1.00 3/8 3.71 - 59.36 - - - - - 33.00 - - - -
Aulas As (+) Kg 16.00 1.00 1/2 7.60 - - 121.60 - - - - - 121.00 - - -
Kg 16.00 1.00 1/2 2.50 - - 40.00 - - - - - 40.00 - - -
Aulas As (+) Kg 16.00 1.00 3/8 7.60 - 121.60 - - - - - 68.00 - - - -
Kg 16.00 1.00 3/8 2.50 - 40.00 - - - - - 22.00 - - - -
As Temperatura Kg 1.00 21.00 1/4 8.13 170.63 - - - - - 38.00 - - - - -
04.03.08.00 ESCALERA
04.03.08.03 ACERO EN ESCALERA fy = 4,200 kg/cm2 Kg 0.00 0.00 0.00 0.00 0.00 0.00
04.03.09.00 MURO INTERMEDIO DE ESCALERA
04.03.09.03 ACERO EN MURO INTERMEDIO DE ESCALERA fy=4200 kg/cm2 Kg 0.00 0.00 0.00 0.00 0.00 0.00
04.03.10.00 GARGOLAS
Nº DE ELEMENTOS
37/38
HOJA DE METRADOS DE ACERO DE ESTRUCTURAS - MODULO 3
OBRA : “RECONSTRUCCION I.E. Nº 82285 – CAJABAMBA - CAJAMARCA” FECHA
UBICACIÓN : CAJABAMBA - CAJABAMBA - CAJAMARCA HECHO
PROPIETARIO : GERENCIA SUBREGIONAL DE CONDORCANQUI - GERENCIA DE INFRAESTRUCTURA Y MEDIO AMBIENTE REVISADO
PARTIDA N° DESCRIPCIÓN UND.ELEMENTO LONGITUD EN METROS PESO EN KILOGRAMOS
CANT. DIAM. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1/4" 3/8" 1/2" 5/8" 3/4" 1"Nº DE
ELEMENTOS
04.03.10.03 ACERO EN GARGOLAS fy=4200 kg/cm2 Kg 0.00 0.00 0.00 0.00 0.00 0.00
04.03.11.00 MESON PARA LAVATORIOS OVALINES
04.03.11.03 ACERO EN MESON fy=4200 kg/cm2 Kg 0.00 0.00 0.00 0.00 0.00 0.00
LADRILLO DE TECHO / M2 ( 0.15 X 0.30 X 0.30 )
0.30 0.3 0.10 8.33
Vcl/m3 = Vlm1.00 m3 - Vld1.00 0.113 0.8875
Vcl/m3 = Volumen de concreto en losa por m3Vlm1.00m3 = Volumen de losa maciza de 1.00 m3Vld= Volumen que ocupan los ladrillos
LARGO ANCHO ALTO Vlm1.00 m31.00 1.00 0.17 0.171.00 1.00 0.20 0.201.00 1.00 0.25 0.251.00 1.00 0.30 0.30
Lad/ m2 ALTO LARGO ANCHO Vld8.33 0.12 0.30 0.30 0.0118.33 0.15 0.30 0.30 0.0148.33 0.20 0.30 0.30 0.0188.33 0.25 0.30 0.30 0.023
LONGITUDLADRILLO
ANCHOLADRILLO
ANCHOVIGUETA
CANTIDAD LAD / m2