cronograma fisico financiero agua potable

Post on 04-Feb-2018

217 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    1/18

    MEJORAMIENTO Y AMPLIACION DEL SAP Y ALCANTARILLADO TEMBLADERA

    01.00.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL

    01.01.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL S/. 1,279.38

    02.00.00 CAJA DE CAPTACIN DE FONDO

    02.01.00 TRABAJOS PRELIMINARES

    02.01.01 DEMOLICION DE CONCRETO ARMADO EN TECHO DE CAPTACION S/. 3,840.41

    02.01.02 LIMPIEZA DE TERRENO, CAPTACIN S/. 109.20

    02.01.03 TRAZO Y REPLANTEO S/. 6.85

    02.02.00 MOVIMIENTO DE TIERRAS

    02.02.01 EXCAVACIN MANUAL CAJA DE VALVULAS S/. 28.81

    02.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 21.36

    02.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 1.6202.03.00 OBRAS DE CONCRETO SIMPLE

    02.03.01 CONCRETO FC=140 KG/CM2 (CAJA VLVULAS) S/. 9,893.62

    02.03.02 PIEDRA 4" ASENTADA CON MORTERO 1:8 EN CAPTACION S/. 572.48

    02.03.03 ENCOFRADO Y DESENCOFRADO S/. 43.43

    02.04.00 OBRAS DE CONCRETO ARMADO

    02.04.01 CONCRETO FC=175 KG/CM2 S/. 4,968.85

    02.04.02 ACERO FY = 4200 KG/CM2. S/. 331.64

    02.04.03 ENCOFRADO Y DESENCOFRADO S/. 1,787.14

    02.05.00 REVOQUES Y ENLUCIDOS

    02.05.01 TARRAJEO EXTERIOR S/. 1,015.11

    02.05.02 TARRAJEO INTERIOR S/. 1,695.04

    02.06.00 VALVULAS Y ACCESORIOS

    02.06.01 VALVULAS Y ACCESORIOS 8" S/. 768.53

    02.07.00 VARIOS

    02.07.01 PINTADO DE ESTRUCTURAS S/. 534.32

    02.07.02 TAPA SANITARIA 0.60X0.60 S/. 271.72

    03.00.00 LINEA DE CONDUCCIN A R1

    03.01.00 TRABAJOS PRELIMINARES

    03.01.01 TRAZO Y REPLANTEO S/. 2,132.47

    03.02.00 EXCAVACIN DE ZANJAS

    03.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 15,376.10

    03.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA S/. 88,011.78

    03.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS. S/. 5,764.59

    03.02.04 CAMA DE APOYO PARA TUBERA S/. 472.99 S/. 236.50

    03.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 65,036.40

    03.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS

    03.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5 S/. 155,742.47 S/. 155,742.47

    03.04.00 PRUEBA HIDRAULICA

    03.04.01 PRUEBA HIDRULICA + DESINFECCIN S/. 3,153.28

    04.00.00 LINEA DE CONDUCCIN A R2

    04.01.00 TRABAJOS PRELIMINARES

    04.01.01 TRAZO Y REPLANTEO S/. 2,270.89

    04.02.00 EXCAVACIN DE ZANJAS

    04.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 15,376.10

    04.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA S/. 95,293.49

    04.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS. S/. 6,142.50

    04.02.04 CAMA DE APOYO PARA TUBERA S/. 504.00 S/. 252.00

    04.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 69,300.00

    04.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS

    04.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5 S/. 165,952.50 S/. 165,952.50

    04.04.00 PRUEBA HIDRAULICA

    04.04.01 PRUEBA HIDRULICA + DESINFECCIN S/. 3,360.00

    05.00.00 RESERVORIO CIRCULAR APOYADO: 100 M3

    05.01.00 TRABAJOS PRELIMINARES

    05.01.01 LIMPIEZA DE TERRENO MANUAL S/. 58.83

    05.01.02 TRAZO Y REPLANTEO S/. 115.96

    05.02.00 MOVIMIENTO DE TIERRAS

    05.02.01 EXCAVACION MANUAL S/. 499.90

    05.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 464.77

    05.02.03 NIVELACION Y COMPACTACION MANUAL S/. 91.74

    05.02.04 AFIRMADO S/. 244.65

    M1 M2 M3 M4 M5 M6 M7 M8

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 1

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    2/18

    05.03.00 OBRAS DE CONCRETO SIMPLE

    05.03.01 SOLADO DE CONCRETO FC=100 KG/CM2 S/. 131.78

    05.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO S/. 364.54

    05.03.03 OBRAS DE CONCRETO ARMADO

    05.03.04 CONCRETO FC = 210 KG/CM2 S/. 42,636.38

    05.03.05 ENCOFRADO Y DESENCOFRADO S/. 568.45 S/. 3,410.68

    05.03.06 ACERO FY = 4200 KG/CM2. S/. 1,388.62 S/. 8,331.71

    05.04.00 REVOQUES Y ENLUCIDOS

    05.04.01 TARRAJEO EXTERIOR S/. 3,332.14

    05.04.02 TARRAJEO INTERIOR S/. 2,850.49

    05.04.03 PENDIENTE DE FONDO, MORTERO 1:5 S/. 1,385.27

    05.05.00 VALVULAS Y ACCESORIOS05.06.01 ACCESORIOS PARA VENTILACIN S/. 625.92

    05.07.00 VARIOS

    05.07.01 PINTURA EN EXTERIORES S/. 1,047.95

    05.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR S/. 3,543.03

    05.07.03 TAPA SANITARIA METLICA S/. 165.86

    06.00.00 RESERVORIO CIRCULAR APOYADO: 75 M3

    06.01.00 TRABAJOS PRELIMINARES

    06.01.01 LIMPIEZA DE TERRENO MANUAL S/. 52.80

    06.01.02 TRAZO Y REPLANTEO S/. 101.39

    06.02.00 MOVIMIENTO DE TIERRAS

    06.02.01 EXCAVACION MANUAL S/. 437.09

    06.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 406.39

    06.02.03 NIVELACION Y COMPACTACION MANUAL S/. 80.22

    06.02.04 AFIRMADO S/. 427.96

    06.03.00 OBRAS DE CONCRETO SIMPLE

    06.03.01 SOLADO DE CONCRETO FC=100 KG/CM2 S/. 115.36

    06.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO S/. 12,794.25

    06.03.03 OBRAS DE CONCRETO ARMADO

    06.03.04 CONCRETO FC = 210 KG/CM2 S/. 17,578.49

    06.03.05 ENCOFRADO Y DESENCOFRADO S/. 525.61 S/. 3,153.66

    06.03.06 ACERO FY = 4200 KG/CM2. S/. 1,231.30 S/. 7,387.79

    06.04.00 REVOQUES Y ENLUCIDOS

    06.04.01 TARRAJEO EXTERIOR S/. 3,183.93

    06.04.02 TARRAJEO INTERIOR S/. 2,575.35

    06.04.03 PENDIENTE DE FONDO, MORTERO 1:5 S/. 1,180.27

    06.05.00 VALVULAS Y ACCESORIOS

    06.06.00 ACCESORIOS PARA VENTILACIN S/. 625.92

    06.07.00 VARIOS

    06.07.01 PINTURA EN EXTERIORES S/. 652.63

    06.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR S/. 3,543.03

    06.07.03 TAPA SANITARIA METLICA S/. 165.86

    07.00.00 CASETA DE VALVULAS

    07.01.00 TRABAJOS PRELIMINARES

    07.01.01 LIMPIEZA DE TERRENO MANUAL S/. 23.39

    07.01.02 TRAZO Y REPLANTEO S/. 37.65

    07.02.00 MOVIMIENTO DE TIERRAS

    07.02.01 EXCAVACION MANUAL S/. 188.69

    07.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 175.45

    07.02.03 NIVELACION Y COMPACTACION MANUAL S/. 29.7907.02.04 LECHO DE GRAVA S/. 132.91

    07.03.00 OBRAS DE CONCRETO SIMPLE

    07.03.01 CONCRETO FC=175 KG/CM2 S/. 1,293.78

    07.03.02 ENCOFRADO Y DESENCOFRADO S/. 738.82

    07.04.00 OBRAS DE CONCRETO ARMADO

    07.04.01 CONCRETO FC=175 KG/CM2 S/. 406.70

    07.04.02 ACERO FY = 4200 KG/CM2. S/. 381.62

    07.04.03 ENCOFRADO Y DESENCOFRADO DE LOSA S/. 328.02

    07.05.00 REVOQUES Y ENLUCIDOS

    07.05.01 TARRAJEO EXTERIOR S/. 743.74

    07.05.02 TARRAJEO INTERIOR S/. 506.09

    07.06.03 VALVULAS Y ACCESORIOS DE 8" (INGRESO CASETA)

    M1 M2 M3 M4 M5 M6 M7 M8

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 2

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    3/18

    07.06.03.1 VALVULAS Y ACCESORIOS 8" (INGRESO CAS. VALVULAS) S/. 768.53

    07.07.00 VARIOS

    07.07.01 TAPA SANITARIA METLICA S/. 331.72

    07.07.02 PINTURA EN EXTERIORES S/. 364.74 S/. 91.18

    08.00.00 RED DE DISTRIBUCIN R1 Y R2

    08.01.00 TRABAJOS PRELIMINARES

    08.01.01 TRAZO Y REPLANTEO S/. 651.95 S/. 630.92 S/. 651.95 S/. 630.92 S/. 651.95 S/. 651.95 S/. 609.89

    08.02.00 MOVIMIENTO DE TIERRAS

    08.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 22,988.74 S/. 22,247.17 S/. 22,988.74 S/. 22,247.17 S/. 22,988.74 S/. 22,988.74 S/. 21,505.60

    08.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 805.48 S/. 779.50 S/. 805.48 S/. 779.50 S/. 805.48 S/. 805.48 S/. 753.51

    08.02.03 REFINE Y CONFORMACIN DE FONDOS S/. 1,656.56 S/. 1,656.56 S/. 1,711.78 S/. 1,656.56 S/. 1,711.78 S/. 1,711.78 S/. 1,601.34

    08.02.04 CAMA DE APOYO PARA TUBERA S/. 1,057.18 S/. 1,132.69 S/. 1,170.44 S/. 1,132.69 S/. 1,170.44 S/. 1,170.44 S/. 1,094.9308.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 1,868.94 S/. 18,689.36 S/. 19,312.34 S/. 18,689.36 S/. 19,312.34 S/. 19,312.34 S/. 18,066.38

    08.02.06 OBRAS DE CONCRETO SIMPLE

    08.02.06.1 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 9,318.58 S/. 12,559.83 S/. 12,154.67 S/. 12,559.83 S/. 12,559.83 S/. 11,749.52

    08.03.00 TUBERA Y ACCESORIOS

    08.03.01 SUMINISTRO E INSTALACION TUBERA U.F. 160 MM. C-7.5 S/. 6,180.54 S/. 10,300.89 S/. 10,644.26 S/. 10,300.89 S/. 10,644.26 S/. 10,644.26 S/. 9,957.53

    08.03.02 SUMINISTRO TUBERA U.F. 110 MM. C-7.5 S/. 4,187.31 S/. 6,978.84 S/. 7,211.47 S/. 6,978.84 S/. 7,211.47 S/. 7,211.47 S/. 6,746.21

    08.03.03 SUMINISTRO TUBERA U.F. 90 MM. C-7.5 S/. 86.49 S/. 144.16 S/. 148.96 S/. 144.16 S/. 148.96 S/. 148.96 S/. 139.35

    08.03.04 SUMINISTRO TUBERA U.F. 63 MM. C-7.5 S/. 665.18 S/. 1,108.63 S/. 1,145.58 S/. 1,108.63 S/. 1,145.58 S/. 1,145.58 S/. 1,071.67

    08.03.05 TUBERA PVC SAP 1/2" C-7.5 S/. 8,235.13 S/. 13,725.21 S/. 14,182.72 S/. 13,725.21 S/. 14,182.72 S/. 14,182.72 S/. 13,267.70

    08.05.00 ACCESORIOS DE RED DE DISTRIBUCION

    08.05.01 TEE PVC 6"X6" S/. 1.53 S/. 2.55 S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.64 S/. 2.47

    08.05.02 TEE PVC 6"X4" S/. 1.53 S/. 2.55 S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.64 S/. 2.47

    08.05.03 TEE PVC 4"X4" S/. 0.59 S/. 0.98 S/. 1.02 S/. 0.98 S/. 1.02 S/. 1.02 S/. 0.95

    08.05.04 TEE PVC 2"X2" S/. 0.12 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.19

    08.05.05 TEE PVC 6"X2" S/. 1.06 S/. 1.77 S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.83 S/. 1.71

    08.05.06 REDUC. PVC 6"-2" S/. 1.06 S/. 1.77 S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.83 S/. 1.71

    08.05.07 CODO. PVC 4"X 90 S/. 0.12 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.19

    08.05.08 CODO. PVC 6"X 90 S/. 0.35 S/. 0.59 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.61 S/. 0.57

    08.05.09 CRUZ PVC 6"X6" S/. 1.30 S/. 2.16 S/. 2.23 S/. 2.16 S/. 2.23 S/. 2.23 S/. 2.09

    08.05.10 CRUZ PVC 6"X4" S/. 2.24 S/. 3.73 S/. 3.86 S/. 3.73 S/. 3.86 S/. 3.86 S/. 3.61

    08.05.11 CRUZ PVC 6"X2" S/. 0.35 S/. 0.59 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.61 S/. 0.57

    08.05.12 CRUZ PVC 4"X4" S/. 0.47 S/. 0.79 S/. 0.81 S/. 0.79 S/. 0.81 S/. 0.81 S/. 0.76

    08.05.13 CRUZ PVC 4"X2" S/. 0.12 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.19

    08.06.00 PRUEBA HIDRAULICA

    08.06.01 PRUEBA HIDRAULICA+DESINFECCION S/. 549.02 S/. 915.03 S/. 945.54 S/. 915.03 S/. 945.54 S/. 945.54 S/. 884.53

    09.00.00 CAJA DE VALVULAS DE CONTROL

    09.01.00 TRABAJOS PRELIMINARES

    09.01.01 LIMPIEZA DE TERRENO MANUAL S/. 7.05 S/. 6.82 S/. 7.05 S/. 6.82 S/. 7.05 S/. 7.05 S/. 6.59

    09.01.02 TRAZO Y REPLANTEO S/. 3,555.05 S/. 3,555.05 S/. 3,673.55 S/. 3,555.05 S/. 3,673.55 S/. 3,673.55 S/. 3,436.55

    09.02.00 MOVIMIENTO DE TIERRAS

    09.02.01 EXCAVACION MANUAL S/. 320.50 S/. 384.60 S/. 397.42 S/. 384.60 S/. 397.42 S/. 397.42 S/. 371.78

    09.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 577.85 S/. 559.21 S/. 577.85 S/. 559.21 S/. 577.85 S/. 577.85 S/. 540.57

    09.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 14.44 S/. 13.97 S/. 14.44 S/. 13.97 S/. 14.44 S/. 14.44 S/. 13.51

    09.03.00 CONCRETO SIMPLE

    09.03.01 CONCRETO FC=140 KG/CM2 S/. 218.47 S/. 211.43 S/. 218.47 S/. 211.43 S/. 218.47 S/. 218.47 S/. 204.38

    09.03.02 ENCOFRADO Y DESENCOFRADO S/. 269.74 S/. 261.04 S/. 269.74 S/. 261.04 S/. 269.74 S/. 269.74 S/. 252.33

    09.04.00 TARRAJEO

    09.04.01 TARRAJEO EXTERIOR S/. 91.39 S/. 88.44 S/. 91.39 S/. 88.44 S/. 91.39 S/. 91.39 S/. 85.49

    09.05.00 VALVULAS Y ACCESORIOS09.05.01 VALVULAS Y ACCESORIOS 4" S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.62 S/. 1.52

    09.05.02 VALVULAS Y ACCESORIOS 6" S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.62 S/. 1.52

    09.05.03 VALVULAS Y ACCESORIOS 2" S/. 2.03 S/. 1.96 S/. 2.03 S/. 1.96 S/. 2.03 S/. 2.03 S/. 1.90

    09.06.00 VARIOS

    09.06.01 TAPA SANITARIA METLICA

    10.00.00 CAJA DE VALVULAS DE PURGA

    10.01.00 TRABAJOS PRELIMIINARES

    10.01.01 LIMPIEZA DE TERRENO MANUAL

    10.01.02 TRAZO Y REPLANTEO

    10.02.00 MOVIMIENTO DE TIERRAS

    10.02.01 EXCAVACION MANUAL

    10.02.02 ELIMINACION DE MATERIAL EXCEDENTE

    M1 M2 M3 M4 M5 M6 M7 M8

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 3

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    4/18

    10.03.00 OBRAS DE CONCRETO SIMPLE

    10.03.01 CONCRETO FC=140 KG/CM2

    10.03.02 ENCOFRADO Y DESENCOFRADO

    10.04.00 TARRAJEO

    10.04.01 TARRAJEO EXTERIOR

    10.05.00 VALVULAS Y ACCESORIOS PURGA

    10.06.00 VARIOS

    10.06.01 TAPA SANITARIA METLICA

    11.00.00 CONEXIONES DOMICILIARIAS

    11.01.00 TRABAJOS PRELIMIINARES

    11.01.01 LIMPIEZA DE TERRENO MANUAL S/. 406.11 S/. 393.01 S/. 406.11 S/. 393.01 S/. 406.11 S/. 406.11 S/. 379.91

    11.01.02 TRAZO Y REPLANTEO S/. 700.73 S/. 724.89 S/. 749.05 S/. 724.89 S/. 749.05 S/. 749.05 S/. 700.7311.02.00 MOVIMIENTO DE TIERRAS

    11.02.01 EXCAVACION MANUAL S/. 1,875.28 S/. 2,344.10 S/. 2,422.23 S/. 2,344.10 S/. 2,422.23 S/. 2,422.23 S/. 2,265.96

    11.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 194.51 S/. 243.14 S/. 251.25 S/. 243.14 S/. 251.25 S/. 251.25 S/. 235.04

    11.02.03 RELLENO Y COMPACTACIN DE ZANJAS S/. 160,116.00

    11.03.00 OBRAS DE CONCRETO SIMPLE

    11.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 1,186.06 S/. 3,953.52 S/. 4,085.31 S/. 3,953.52 S/. 4,085.31 S/. 4,085.31 S/. 3,821.74

    11.03.02 CONCRETO FC=140 KG/CM2 S/. 120.97 S/. 403.23 S/. 416.67 S/. 403.23 S/. 416.67 S/. 416.67 S/. 389.79

    11.03.03 ENCOFRADO Y DESENCOFRADO S/. 186.02 S/. 620.07 S/. 640.74 S/. 620.07 S/. 640.74 S/. 640.74 S/. 599.40

    11.04.00 OBRAS DE CONCRETO ARMADO

    11.04.01 CONCRETO FC=175 KG/CM2 S/. 38.62 S/. 128.73 S/. 133.02 S/. 128.73 S/. 133.02 S/. 133.02 S/. 124.44

    11.04.02 ACERO FY = 4200 KG/CM2. S/. 25.62 S/. 85.41 S/. 88.26 S/. 85.41 S/. 88.26 S/. 88.26 S/. 82.56

    11.04.03 ENCOFRADO Y DESENCOFRADO S/. 28.34 S/. 94.46 S/. 97.61 S/. 94.46 S/. 97.61 S/. 97.61 S/. 91.31

    11.05.00 CONEXIONES DOMICILIARIAS

    11.05.01 CONEXIN DOMICILIARIA DE AGUA 6" S/. 39.28 S/. 84.17 S/. 86.97 S/. 84.17 S/. 86.97 S/. 86.97 S/. 81.36

    11.05.02 CONEXIN DOMICILIARIA DE AGUA 4" S/. 44.89 S/. 96.19 S/. 99.40 S/. 96.19 S/. 99.40 S/. 99.40 S/. 92.99

    11.05.03 CONEXIN DOMICILIARIA DE AGUA 3" S/. 3.09 S/. 6.61 S/. 6.83 S/. 6.61 S/. 6.83 S/. 6.83 S/. 6.39

    11.05.04 CONEXIN DOMICILIARIA DE AGUA 2" S/. 26.19 S/. 56.11 S/. 57.98 S/. 56.11 S/. 57.98 S/. 57.98 S/. 54.24

    11.05.05 SUMINISTRO E INSTALACION DE MEDIDORES S/. 4,593.97 S/. 9,844.22 S/. 10,172.36 S/. 9,844.22 S/. 10,172.36 S/. 10,172.36 S/. 9,516.08

    12.00.00 CASETA DE CLORACIN

    12.01.00 MUROS DE LADRILLOS DE SOGA S/. 177.99 S/. 489.47

    12.02.00 COBERTURA DE CALAMINA S/. 16.35

    12.03.00 CARPINTERIA METALICA S/. 1,305.21

    12.04.00 TARRAJEO EM MUROS S/. 215.03

    12.05.00 CERRAJERIA S/. 13.20 S/. 5.66

    12.06.00 PINTURA EN MUROS S/. 169.07 S/. 72.46

    12.07.00 VIDRIOS S/. 163.62

    13.00.00 EDUCACIN SANITARIA Y CAPACITACION EN AOM.

    13.01.00 EDUCACIN SANITARIA S/. 4,960.00 S/. 4,800.00 S/. 4,960.00 S/. 4,800.00 S/. 4,960.00 S/. 4,320.00

    13.03.00 CAPACITACIN EN A+O+M S/. 26,401.15 S/. 25,549.50 S/. 26,401.15 S/. 25,549.50 S/. 26,401.15 S/. 22,994.55

    14.00.00 FLETE

    14.01.00 FLETE TERRESTRE S/. 238.46 S/. 230.77 S/. 238.46 S/. 230.77 S/. 238.46 S/. 238.46 S/. 223.08

    14.02.00 FLETE RURAL S/. 238.46 S/. 230.77 S/. 238.46 S/. 230.77 S/. 238.46 S/. 238.46 S/. 223.08

    15.00.00 CONTROL DE CALIDAD

    15.01.00 DISE O DE MEZCLAS DE CONCRETO S/. 31.30 S/. 30.29 S/. 31.30 S/. 30.29 S/. 31.30 S/. 31.30 S/. 29.28

    15.02.00 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 10.78 S/. 10.43 S/. 10.78 S/. 10.43 S/. 10.78 S/. 10.78 S/. 10.08

    16.00.00 DESAGE

    16.01.00 OBRAS PRELIMINARES

    16.01.01 LIMPIEZA DE TERRENO MANUAL S/. 8,950.41

    16.01.02 TRAZO Y REPLANTEO S/. 10,393.6316.01.03 CINTA DE PELIGRO S/. 17,333.58 S/. 20,000.28 S/. 2,666.70

    16.02.00 MOVIMIENTO DE TIERRAS

    16.02.01 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 69,399.49 S/. 10,676.84

    16.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 11,056.75 S/. 1,701.04

    16.02.03 EXCAVACION C/MAQ EN TERRENO CONGLOMERADO HASTA 2.40 MPROF. S/. 2,756.37

    16.02.04 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 45,728.75 S/. 53,045.35

    16.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA S/. 3,334.95

    16.03.00 OBRAS DE CONCRETO SIMPLE

    16.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 41,487.95 S/. 80,210.05

    16.04.00 SUMINISTRO E INSTALACION DE TUBERIA

    16.04.01 SUMINISTRO E INSTALACION TUBERIA PVC 200 mm.x 6m S26 S/. 186,671.20 S/. 251,600.32 S/. 48,696.84

    16.04.02 REFINE, NIVELACION Y CONF. DE FONDO T.C. S/. 37,283.41 S/. 50,251.55 S/. 9,726.11

    M1 M2 M3 M4 M5 M6 M7 M8

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 4

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    5/18

    16.04.03 PREPARACION DE CAMA DE APOYO P/TUBERIA S/. 5,480.40 S/. 7,386.62 S/. 1,429.67

    16.04.04 INSTALACION TUBERIA PVC 200 MM.X 6M S25 S/. 18,662.81 S/. 44,503.63 S/. 43,068.03 S/. 1,435.60

    16.04.05 CONEXION DE TUBERIA PVC A CONCRETO DE BUZON S/. 634.57 S/. 6,557.22 S/. 6,345.70 S/. 2,326.76

    16.04.06 PRUEBA HIDRAULICA EN TUBERIA PVC S/. 4,281.04 S/. 3,210.78

    16.05.00 CONSTRUCCION DE BUZONES

    16.05.01 BUZON ESTANDAR HASTA 0.70M DE PROF. S/. 900.37 S/. 2,147.03 S/. 1,108.14

    16.05.02 BUZON ESTANDAR HASTA 0.80M DE PROF. S/. 1,350.55 S/. 3,220.54 S/. 1,662.22

    16.05.03 BUZON ESTANDAR HASTA 0.90M DE PROF. S/. 450.18 S/. 1,073.51 S/. 554.07

    16.05.04 BUZON ESTANDAR HASTA 1.20M DE PROF. S/. 65,561.50 S/. 156,338.95 S/. 80,691.07

    16.05.05 BUZON ESTANDAR HASTA 2.40M DE PROF. S/. 1,098.56 S/. 2,619.64 S/. 1,352.07

    16.06.00 CONEXIONES DOMICILIARIAS

    16.06.01 MOVIMIENTO DE TIERRAS16.06.01.1 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 9,875.60 S/. 11,774.75 S/. 11,394.92 S/. 11,774.75 S/. 11,774.75 S/. 11,015.09

    16.06.01.2 CORTE DE PAVIMENTO CON MOLADORA S/. 914.60 S/. 1,090.49 S/. 1,055.31 S/. 1,090.49 S/. 1,090.49 S/. 1,020.13

    16.06.01.3 RELLENO CON MATERIAL PROPIO S/. 5,658.65 S/. 6,287.38 S/. 6,496.96 S/. 6,496.96 S/. 6,077.80

    16.06.01.4 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 64,583.15 S/. 71,759.06 S/. 74,151.03 S/. 74,151.03 S/. 69,367.09

    16.06.02 TENDIDO E INSTALACION DE TUBERIAS

    16.06.02.1 CONEXION DOMICILIARIA 200M T. CONGLOMERADO S/. 25,765.74 S/. 72,612.54 S/. 70,270.20 S/. 72,612.54 S/. 72,612.54 S/. 67,927.86

    16.06.02.2 CONEXION DOMICILIARIA 160M T. CONGLOMERADO S/. 818.77 S/. 2,307.43 S/. 2,233.00 S/. 2,307.43 S/. 2,307.43 S/. 2,158.57

    16.06.03 FLETE

    16.06.03.1 FLETE TERRESTRE ALCANTARILLADO S/. 86.67 S/. 103.33 S/. 100.00 S/. 103.33 S/. 103.33 S/. 96.67

    16.06.04 CONTROL DE CALIDAD

    16.06.04.1 DISEO DE MEZCLAS DE CONCRETO S/. 6.42 S/. 16.92

    16.06.04.2 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 1.88 S/. 54.62

    16.06.05 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES

    16.06.05.1 CONSTRUCCION DE 2 LAGUNAS FACULTATIVAS EN PARALELO. AREA TOTAL=2.2HA S/. 17,198.47 S/. 38,082.32 S/. 38,082.32 S/. 35,625.40

    16.06.05.2 CONSTRUCCION DE CERCO PERIMETRICO

    17.00.00 TANQUE IMHOFF - CAMARAS DE REJAS Y DESARENADOR

    17.01.00 OBRAS PRELIMINARES

    17.01.01 TRAZO Y REPLANTEO S/. 39.84

    17.01.02 LIMPIEZA DE TERRENO MANUAL S/. 21.06

    17.02.00 MOVIMIENTO DE TIERRAS

    17.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 61.42

    17.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 104.86

    17.03.00 OBRAS DE CONCRETO SIMPLE

    17.03.01 CONCRETO FC=140 KG/CM2 S/. 1,203.44

    17.03.02 ACERO FY = 4200 KG/CM2. S/. 680.24

    17.03.03 ENCOFRADO Y DESENCOFRADO S/. 877.93

    17.04.00 REVOQUES Y ENLUCIDOS

    17.04.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 1,113.16

    17.04.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA S/. 102.71

    17.05.00 EQUIPAMIENTO

    17.05.01 COMPUERTA METALICA DE 0.30X0.50 E=3/16 S/. 470.84

    17.05.02 PLANCHA METALICA 0.65X0.4 DE E=1/2 S/. 840.21

    17.05.03 REJA P/RETENCION DE SOLIDOS PLAT. 11/2X3/8 MARCO L 11/2X11/2X1/4 S/. 73.54

    18.00.00 TANQUE IMHOFF

    18.01.00 OBRAS PRELIMINARES

    18.01.01 TRAZO Y REPLANTEO S/. 91.68

    18.01.02 LIMPIEZA DE TERRENO MANUAL S/. 43.88

    18.02.00 MOVIMIENTO DE TIERRAS

    18.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 1,858.8318.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 4,293.94

    18.03.00 OBRAS DE CONCRETO SIMPLE

    18.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2 S/. 44.34

    18.04.00 OBRAS DE CONCRETO ARMADO

    18.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2 S/. 13,039.81

    18.04.02 ACERO FY = 4200 KG/CM2. S/. 14,438.31

    18.04.03 ENCOFRADO Y DESENCOFRADO S/. 5,391.86

    18.05.00 REVOQUES Y ENLUCIDOS

    18.05.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 3,421.12

    18.05.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA S/. 220.89

    19.00.00 LECHO DE SECADO

    19.01.00 OBRAS PRELIMINARES

    M1 M2 M3 M4 M5 M6 M7 M8

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 5

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    6/18

    19.01.01 TRAZO Y REPLANTEO S/. 249.00

    19.01.02 LIMPIEZA DE TERRENO MANUAL S/. 135.00

    19.02.00 MOVIMIENTO DE TIERRAS

    19.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 671.90

    19.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 11,176.38

    19.03.00 OBRAS DE CONCRETO SIMPLE

    19.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2 S/. 149.04

    19.04.00 OBRAS DE CONCRETO ARMADO

    19.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2 S/. 4,213.07

    19.04.02 ACERO FY = 4200 KG/CM2. S/. 97.30

    19.04.03 ENCOFRADO Y DESENCOFRADO S/. 7,365.86

    19.05.00 MUROS DE MAMPOSTERIA

    19.05.01 MURO DE SOGA LADRILLO PANDERETA CON CEMENTO - CAL - ARENA S/. 646.24

    19.05.02 CUBIERTA DE LADRILLO PASTELERO ASENTADO Y FRAGUADO S/. 8,856.95 S/. 11,809.27

    19.06.00 REVOQUES Y ENLUCIDOS

    19.06.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 2,292.86

    19.07.00 SUMINISTRO Y COLOCACION

    19.07.01 ARENA GRUESA SELECCIONADA S/. 998.25

    19.07.02 PIEDRA CLASIFICADA DE 3/4 - 2 S/. 1,250.85

    19.07.03 PIEDRA CLASIFICADA DE 1/4 - 3/4 S/. 312.48

    19.07.04 PIEDRA CLASIFICADA DE 1/16 - 1/4 S/. 468.72

    20.00.00 MITIGACION AMBIENTAL

    20.01.00 MITIGACION AMBIENTAL S/. 563.64 S/. 545.45 S/. 563.64 S/. 545.45 S/. 563.64 S/. 563.64 S/. 527.27

    Total S/. 969,370.72 S/. 1,120,584.96 S/. 837,739.50 S/. 525,314.92 S/. 448,550.37 S/. 455,727.83 S/. 438,452.06

    M1 M2 M3 M4 M5 M6 M7 M8

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 6

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    7/18

    MEJORAMIENTO Y AMPLIACION DEL SAP Y ALCANTARILLADO TEMBLADERA

    01.00.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL

    01.01.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL

    02.00.00 CAJA DE CAPTACIN DE FONDO

    02.01.00 TRABAJOS PRELIMINARES

    02.01.01 DEMOLICION DE CONCRETO ARMADO EN TECHO DE CAPTACION

    02.01.02 LIMPIEZA DE TERRENO, CAPTACIN

    02.01.03 TRAZO Y REPLANTEO

    02.02.00 MOVIMIENTO DE TIERRAS

    02.02.01 EXCAVACIN MANUAL CAJA DE VALVULAS

    02.02.02 ELIMINACION DE MATERIAL EXCEDENTE

    02.02.03 NIVELACION INTERIOR APISONADO MANUAL

    02.03.00 OBRAS DE CONCRETO SIMPLE

    02.03.01 CONCRETO FC=140 KG/CM2 (CAJA VLVULAS)

    02.03.02 PIEDRA 4" ASENTADA CON MORTERO 1:8 EN CAPTACION

    02.03.03 ENCOFRADO Y DESENCOFRADO

    02.04.00 OBRAS DE CONCRETO ARMADO

    02.04.01 CONCRETO FC=175 KG/CM2

    02.04.02 ACERO FY = 4200 KG/CM2.

    02.04.03 ENCOFRADO Y DESENCOFRADO

    02.05.00 REVOQUES Y ENLUCIDOS

    02.05.01 TARRAJEO EXTERIOR

    02.05.02 TARRAJEO INTERIOR

    02.06.00 VALVULAS Y ACCESORIOS

    02.06.01 VALVULAS Y ACCESORIOS 8"

    02.07.00 VARIOS

    02.07.01 PINTADO DE ESTRUCTURAS

    02.07.02 TAPA SANITARIA 0.60X0.60

    03.00.00 LINEA DE CONDUCCIN A R1

    03.01.00 TRABAJOS PRELIMINARES

    03.01.01 TRAZO Y REPLANTEO

    03.02.00 EXCAVACIN DE ZANJAS03.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO

    03.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA

    03.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS.

    03.02.04 CAMA DE APOYO PARA TUBERA

    03.02.05 RELLENO Y COMPACTACIN DE ZANJAS

    03.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS

    03.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5

    03.04.00 PRUEBA HIDRAULICA

    03.04.01 PRUEBA HIDRULICA + DESINFECCIN

    04.00.00 LINEA DE CONDUCCIN A R2

    04.01.00 TRABAJOS PRELIMINARES

    04.01.01 TRAZO Y REPLANTEO

    04.02.00 EXCAVACIN DE ZANJAS

    04.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO

    04.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA

    04.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS.

    04.02.04 CAMA DE APOYO PARA TUBERA

    04.02.05 RELLENO Y COMPACTACIN DE ZANJAS

    04.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS04.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5

    04.04.00 PRUEBA HIDRAULICA

    04.04.01 PRUEBA HIDRULICA + DESINFECCIN

    05.00.00 RESERVORIO CIRCULAR APOYADO: 100 M3

    05.01.00 TRABAJOS PRELIMINARES

    05.01.01 LIMPIEZA DE TERRENO MANUAL

    05.01.02 TRAZO Y REPLANTEO

    05.02.00 MOVIMIENTO DE TIERRAS

    05.02.01 EXCAVACION MANUAL

    05.02.02 ELIMINACION DE MATERIAL EXCEDENTE

    05.02.03 NIVELACION Y COMPACTACION MANUAL

    05.02.04 AFIRMADO

    M8 M9 M10 M11 M12 M13 M14 M15

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 7

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    8/18

    05.03.00 OBRAS DE CONCRETO SIMPLE

    05.03.01 SOLADO DE CONCRETO FC=100 KG/CM2

    05.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO

    05.03.03 OBRAS DE CONCRETO ARMADO

    05.03.04 CONCRETO FC = 210 KG/CM2

    05.03.05 ENCOFRADO Y DESENCOFRADO

    05.03.06 ACERO FY = 4200 KG/CM2.

    05.04.00 REVOQUES Y ENLUCIDOS

    05.04.01 TARRAJEO EXTERIOR

    05.04.02 TARRAJEO INTERIOR

    05.04.03 PENDIENTE DE FONDO, MORTERO 1:5

    05.05.00 VALVULAS Y ACCESORIOS

    05.06.01 ACCESORIOS PARA VENTILACIN

    05.07.00 VARIOS

    05.07.01 PINTURA EN EXTERIORES

    05.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR

    05.07.03 TAPA SANITARIA METLICA

    06.00.00 RESERVORIO CIRCULAR APOYADO: 75 M3

    06.01.00 TRABAJOS PRELIMINARES

    06.01.01 LIMPIEZA DE TERRENO MANUAL

    06.01.02 TRAZO Y REPLANTEO

    06.02.00 MOVIMIENTO DE TIERRAS

    06.02.01 EXCAVACION MANUAL

    06.02.02 ELIMINACION DE MATERIAL EXCEDENTE

    06.02.03 NIVELACION Y COMPACTACION MANUAL

    06.02.04 AFIRMADO

    06.03.00 OBRAS DE CONCRETO SIMPLE

    06.03.01 SOLADO DE CONCRETO FC=100 KG/CM2

    06.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO

    06.03.03 OBRAS DE CONCRETO ARMADO

    06.03.04 CONCRETO FC = 210 KG/CM2

    06.03.05 ENCOFRADO Y DESENCOFRADO06.03.06 ACERO FY = 4200 KG/CM2.

    06.04.00 REVOQUES Y ENLUCIDOS

    06.04.01 TARRAJEO EXTERIOR

    06.04.02 TARRAJEO INTERIOR

    06.04.03 PENDIENTE DE FONDO, MORTERO 1:5

    06.05.00 VALVULAS Y ACCESORIOS

    06.06.00 ACCESORIOS PARA VENTILACIN

    06.07.00 VARIOS

    06.07.01 PINTURA EN EXTERIORES

    06.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR

    06.07.03 TAPA SANITARIA METLICA

    07.00.00 CASETA DE VALVULAS

    07.01.00 TRABAJOS PRELIMINARES

    07.01.01 LIMPIEZA DE TERRENO MANUAL

    07.01.02 TRAZO Y REPLANTEO

    07.02.00 MOVIMIENTO DE TIERRAS

    07.02.01 EXCAVACION MANUAL

    07.02.02 ELIMINACION DE MATERIAL EXCEDENTE

    07.02.03 NIVELACION Y COMPACTACION MANUAL07.02.04 LECHO DE GRAVA

    07.03.00 OBRAS DE CONCRETO SIMPLE

    07.03.01 CONCRETO FC=175 KG/CM2

    07.03.02 ENCOFRADO Y DESENCOFRADO

    07.04.00 OBRAS DE CONCRETO ARMADO

    07.04.01 CONCRETO FC=175 KG/CM2

    07.04.02 ACERO FY = 4200 KG/CM2.

    07.04.03 ENCOFRADO Y DESENCOFRADO DE LOSA

    07.05.00 REVOQUES Y ENLUCIDOS

    07.05.01 TARRAJEO EXTERIOR

    07.05.02 TARRAJEO INTERIOR

    07.06.03 VALVULAS Y ACCESORIOS DE 8" (INGRESO CASETA)

    M8 M9 M10 M11 M12 M13 M14 M15

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 8

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    9/18

    07.06.03.1 VALVULAS Y ACCESORIOS 8" (INGRESO CAS. VALVULAS)

    07.07.00 VARIOS

    07.07.01 TAPA SANITARIA METLICA

    07.07.02 PINTURA EN EXTERIORES

    08.00.00 RED DE DISTRIBUCIN R1 Y R2

    08.01.00 TRABAJOS PRELIMINARES

    08.01.01 TRAZO Y REPLANTEO S/. 651.95 S/. 630.92 S/. 651.95 S/. 630.92 S/. 651.95 S/. 651.95 S/. 630.92

    08.02.00 MOVIMIENTO DE TIERRAS

    08.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 22,988.74 S/. 22,247.17 S/. 22,988.74 S/. 22,247.17 S/. 22,988.74 S/. 22,988.74 S/. 22,247.17

    08.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 805.48 S/. 779.50 S/. 805.48 S/. 779.50 S/. 805.48 S/. 805.48 S/. 779.50

    08.02.03 REFINE Y CONFORMACIN DE FONDOS S/. 1,711.78 S/. 1,656.56 S/. 1,711.78 S/. 1,656.56 S/. 1,711.78 S/. 1,711.78 S/. 1,656.56

    08.02.04 CAMA DE APOYO PARA TUBERA S/. 1,170.44 S/. 1,132.69 S/. 1,170.44 S/. 1,132.69 S/. 1,170.44 S/. 1,170.44 S/. 1,132.69

    08.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 19,312.34 S/. 18,689.36 S/. 19,312.34 S/. 18,689.36 S/. 19,312.34 S/. 19,312.34 S/. 18,689.36

    08.02.06 OBRAS DE CONCRETO SIMPLE

    08.02.06.1 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 12,559.83 S/. 12,154.67 S/. 12,559.83 S/. 12,154.67 S/. 12,559.83 S/. 12,559.83 S/. 12,154.67

    08.03.00 TUBERA Y ACCESORIOS

    08.03.01 SUMINISTRO E INSTALACION TUBERA U.F. 160 MM. C-7.5 S/. 10,644.26 S/. 10,300.89 S/. 10,644.26 S/. 10,300.89 S/. 10,644.26 S/. 10,644.26 S/. 10,300.89

    08.03.02 SUMINISTRO TUBERA U.F. 110 MM. C-7.5 S/. 7,211.47 S/. 6,978.84 S/. 7,211.47 S/. 6,978.84 S/. 7,211.47 S/. 7,211.47 S/. 6,978.84

    08.03.03 SUMINISTRO TUBERA U.F. 90 MM. C-7.5 S/. 148.96 S/. 144.16 S/. 148.96 S/. 144.16 S/. 148.96 S/. 148.96 S/. 144.16

    08.03.04 SUMINISTRO TUBERA U.F. 63 MM. C-7.5 S/. 1,145.58 S/. 1,108.63 S/. 1,145.58 S/. 1,108.63 S/. 1,145.58 S/. 1,145.58 S/. 1,108.63

    08.03.05 TUBERA PVC SAP 1/2" C-7.5 S/. 14,182.72 S/. 13,725.21 S/. 14,182.72 S/. 13,725.21 S/. 14,182.72 S/. 14,182.72 S/. 13,725.21

    08.05.00 ACCESORIOS DE RED DE DISTRIBUCION

    08.05.01 TEE PVC 6"X6" S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.64 S/. 2.55

    08.05.02 TEE PVC 6"X4" S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.55 S/. 2.64 S/. 2.64 S/. 2.55

    08.05.03 TEE PVC 4"X4" S/. 1.02 S/. 0.98 S/. 1.02 S/. 0.98 S/. 1.02 S/. 1.02 S/. 0.98

    08.05.04 TEE PVC 2"X2" S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20

    08.05.05 TEE PVC 6"X2" S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.83 S/. 1.77

    08.05.06 REDUC. PVC 6"-2" S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.77 S/. 1.83 S/. 1.83 S/. 1.77

    08.05.07 CODO. PVC 4"X 90 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20

    08.05.08 CODO. PVC 6"X 90 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.61 S/. 0.59

    08.05.09 CRUZ PVC 6"X6" S/. 2.23 S/. 2.16 S/. 2.23 S/. 2.16 S/. 2.23 S/. 2.23 S/. 2.16

    08.05.10 CRUZ PVC 6"X4" S/. 3.86 S/. 3.73 S/. 3.86 S/. 3.73 S/. 3.86 S/. 3.86 S/. 3.7308.05.11 CRUZ PVC 6"X2" S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.61 S/. 0.59

    08.05.12 CRUZ PVC 4"X4" S/. 0.81 S/. 0.79 S/. 0.81 S/. 0.79 S/. 0.81 S/. 0.81 S/. 0.79

    08.05.13 CRUZ PVC 4"X2" S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.20

    08.06.00 PRUEBA HIDRAULICA

    08.06.01 PRUEBA HIDRAULICA+DESINFECCION S/. 945.54 S/. 915.03 S/. 945.54 S/. 915.03 S/. 945.54 S/. 945.54 S/. 915.03

    09.00.00 CAJA DE VALVULAS DE CONTROL

    09.01.00 TRABAJOS PRELIMINARES

    09.01.01 LIMPIEZA DE TERRENO MANUAL S/. 7.05 S/. 6.82 S/. 7.05 S/. 6.82 S/. 7.05 S/. 7.05 S/. 6.82

    09.01.02 TRAZO Y REPLANTEO S/. 3,673.55 S/. 3,555.05 S/. 3,673.55 S/. 3,555.05 S/. 3,673.55 S/. 3,673.55 S/. 3,555.05

    09.02.00 MOVIMIENTO DE TIERRAS

    09.02.01 EXCAVACION MANUAL S/. 397.42 S/. 384.60 S/. 397.42 S/. 384.60 S/. 397.42 S/. 397.42 S/. 384.60

    09.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 577.85 S/. 559.21 S/. 577.85 S/. 559.21 S/. 577.85 S/. 577.85 S/. 559.21

    09.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 14.44 S/. 13.97 S/. 14.44 S/. 13.97 S/. 14.44 S/. 14.44 S/. 13.97

    09.03.00 CONCRETO SIMPLE

    09.03.01 CONCRETO FC=140 KG/CM2 S/. 218.47 S/. 211.43 S/. 218.47 S/. 211.43 S/. 218.47 S/. 218.47 S/. 211.43

    09.03.02 ENCOFRADO Y DESENCOFRADO S/. 269.74 S/. 261.04 S/. 269.74 S/. 261.04 S/. 269.74 S/. 269.74 S/. 261.04

    09.04.00 TARRAJEO

    09.04.01 TARRAJEO EXTERIOR S/. 91.39 S/. 88.44 S/. 91.39 S/. 88.44 S/. 91.39 S/. 91.39 S/. 88.44

    09.05.00 VALVULAS Y ACCESORIOS09.05.01 VALVULAS Y ACCESORIOS 4" S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.62 S/. 1.57

    09.05.02 VALVULAS Y ACCESORIOS 6" S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.57 S/. 1.62 S/. 1.62 S/. 1.57

    09.05.03 VALVULAS Y ACCESORIOS 2" S/. 2.03 S/. 1.96 S/. 2.03 S/. 1.96 S/. 2.03 S/. 2.03 S/. 1.96

    09.06.00 VARIOS

    09.06.01 TAPA SANITARIA METLICA

    10.00.00 CAJA DE VALVULAS DE PURGA

    10.01.00 TRABAJOS PRELIMIINARES

    10.01.01 LIMPIEZA DE TERRENO MANUAL

    10.01.02 TRAZO Y REPLANTEO

    10.02.00 MOVIMIENTO DE TIERRAS

    10.02.01 EXCAVACION MANUAL

    10.02.02 ELIMINACION DE MATERIAL EXCEDENTE

    M8 M9 M10 M11 M12 M13 M14 M15

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 9

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    10/18

    10.03.00 OBRAS DE CONCRETO SIMPLE

    10.03.01 CONCRETO FC=140 KG/CM2

    10.03.02 ENCOFRADO Y DESENCOFRADO

    10.04.00 TARRAJEO

    10.04.01 TARRAJEO EXTERIOR

    10.05.00 VALVULAS Y ACCESORIOS PURGA

    10.06.00 VARIOS

    10.06.01 TAPA SANITARIA METLICA

    11.00.00 CONEXIONES DOMICILIARIAS

    11.01.00 TRABAJOS PRELIMIINARES

    11.01.01 LIMPIEZA DE TERRENO MANUAL S/. 406.11 S/. 393.01 S/. 406.11 S/. 393.01 S/. 406.11 S/. 406.11 S/. 393.01

    11.01.02 TRAZO Y REPLANTEO S/. 749.05 S/. 724.89 S/. 749.05 S/. 724.89 S/. 749.05 S/. 749.05 S/. 724.89

    11.02.00 MOVIMIENTO DE TIERRAS

    11.02.01 EXCAVACION MANUAL S/. 2,422.23 S/. 2,344.10 S/. 2,422.23 S/. 2,344.10 S/. 2,422.23 S/. 2,422.23 S/. 2,344.10

    11.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 251.25 S/. 243.14 S/. 251.25 S/. 243.14 S/. 251.25 S/. 251.25 S/. 243.14

    11.02.03 RELLENO Y COMPACTACIN DE ZANJAS

    11.03.00 OBRAS DE CONCRETO SIMPLE

    11.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 4,085.31 S/. 3,953.52 S/. 4,085.31 S/. 3,953.52 S/. 4,085.31 S/. 4,085.31 S/. 3,953.52

    11.03.02 CONCRETO FC=140 KG/CM2 S/. 416.67 S/. 403.23 S/. 416.67 S/. 403.23 S/. 416.67 S/. 416.67 S/. 403.23

    11.03.03 ENCOFRADO Y DESENCOFRADO S/. 640.74 S/. 620.07 S/. 640.74 S/. 620.07 S/. 640.74 S/. 640.74 S/. 620.07

    11.04.00 OBRAS DE CONCRETO ARMADO

    11.04.01 CONCRETO FC=175 KG/CM2 S/. 133.02 S/. 128.73 S/. 133.02 S/. 128.73 S/. 133.02 S/. 133.02 S/. 128.73

    11.04.02 ACERO FY = 4200 KG/CM2. S/. 88.26 S/. 85.41 S/. 88.26 S/. 85.41 S/. 88.26 S/. 88.26 S/. 85.41

    11.04.03 ENCOFRADO Y DESENCOFRADO S/. 97.61 S/. 94.46 S/. 97.61 S/. 94.46 S/. 97.61 S/. 97.61 S/. 94.46

    11.05.00 CONEXIONES DOMICILIARIAS

    11.05.01 CONEXIN DOMICILIARIA DE AGUA 6" S/. 86.97 S/. 84.17 S/. 86.97 S/. 84.17 S/. 86.97 S/. 86.97 S/. 84.17

    11.05.02 CONEXIN DOMICILIARIA DE AGUA 4" S/. 99.40 S/. 96.19 S/. 99.40 S/. 96.19 S/. 99.40 S/. 99.40 S/. 96.19

    11.05.03 CONEXIN DOMICILIARIA DE AGUA 3" S/. 6.83 S/. 6.61 S/. 6.83 S/. 6.61 S/. 6.83 S/. 6.83 S/. 6.61

    11.05.04 CONEXIN DOMICILIARIA DE AGUA 2" S/. 57.98 S/. 56.11 S/. 57.98 S/. 56.11 S/. 57.98 S/. 57.98 S/. 56.11

    11.05.05 SUMINISTRO E INSTALACION DE MEDIDORES S/. 10,172.36 S/. 9,844.22 S/. 10,172.36 S/. 9,844.22 S/. 10,172.36 S/. 10,172.36 S/. 9,844.22

    12.00.00 CASETA DE CLORACIN

    12.01.00 MUROS DE LADRILLOS DE SOGA12.02.00 COBERTURA DE CALAMINA

    12.03.00 CARPINTERIA METALICA

    12.04.00 TARRAJEO EM MUROS

    12.05.00 CERRAJERIA

    12.06.00 PINTURA EN MUROS

    12.07.00 VIDRIOS

    13.00.00 EDUCACIN SANITARIA Y CAPACITACION EN AOM.

    13.01.00 EDUCACIN SANITARIA

    13.03.00 CAPACITACIN EN A+O+M

    14.00.00 FLETE

    14.01.00 FLETE TERRESTRE S/. 238.46 S/. 230.77 S/. 238.46 S/. 230.77 S/. 238.46 S/. 238.46 S/. 230.77

    14.02.00 FLETE RURAL S/. 238.46 S/. 230.77 S/. 238.46 S/. 230.77 S/. 238.46 S/. 238.46 S/. 230.77

    15.00.00 CONTROL DE CALIDAD

    15.01.00 DISE O DE MEZCLAS DE CONCRETO S/. 31.30 S/. 30.29 S/. 31.30 S/. 30.29 S/. 31.30 S/. 31.30 S/. 30.29

    15.02.00 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 10.78 S/. 10.43 S/. 10.78 S/. 10.43 S/. 10.78 S/. 10.78 S/. 10.43

    16.00.00 DESAGE

    16.01.00 OBRAS PRELIMINARES

    16.01.01 LIMPIEZA DE TERRENO MANUAL

    16.01.02 TRAZO Y REPLANTEO16.01.03 CINTA DE PELIGRO

    16.02.00 MOVIMIENTO DE TIERRAS

    16.02.01 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO

    16.02.02 CORTE DE PAVIMENTO CON MOLADORA

    16.02.03 EXCAVACION C/MAQ EN TERRENO CONGLOMERADO HASTA 2.40 MPROF.

    16.02.04 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 10,974.90

    16.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA

    16.03.00 OBRAS DE CONCRETO SIMPLE

    16.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 85,741.77

    16.04.00 SUMINISTRO E INSTALACION DE TUBERIA

    16.04.01 SUMINISTRO E INSTALACION TUBERIA PVC 200 mm.x 6m S26

    16.04.02 REFINE, NIVELACION Y CONF. DE FONDO T.C.

    M8 M9 M10 M11 M12 M13 M14 M15

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 10

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    11/18

    16.04.03 PREPARACION DE CAMA DE APOYO P/TUBERIA

    16.04.04 INSTALACION TUBERIA PVC 200 MM.X 6M S25

    16.04.05 CONEXION DE TUBERIA PVC A CONCRETO DE BUZON

    16.04.06 PRUEBA HIDRAULICA EN TUBERIA PVC

    16.05.00 CONSTRUCCION DE BUZONES

    16.05.01 BUZON ESTANDAR HASTA 0.70M DE PROF.

    16.05.02 BUZON ESTANDAR HASTA 0.80M DE PROF.

    16.05.03 BUZON ESTANDAR HASTA 0.90M DE PROF.

    16.05.04 BUZON ESTANDAR HASTA 1.20M DE PROF.

    16.05.05 BUZON ESTANDAR HASTA 2.40M DE PROF.

    16.06.00 CONEXIONES DOMICILIARIAS

    16.06.01 MOVIMIENTO DE TIERRAS

    16.06.01.1 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 759.66

    16.06.01.2 CORTE DE PAVIMENTO CON MOLADORA S/. 70.35

    16.06.01.3 RELLENO CON MATERIAL PROPIO S/. 6,496.96 S/. 209.58

    16.06 .01.4 RELLEN O Y COMPAC TACI ON D E ZANJAS C ON MAT ER IAL PR OPIO SELEC CION AD O S/. 74,151.03 S /. 2 ,391 .97

    16.06.02 TENDIDO E INSTALACION DE TUBERIAS

    16.06.02.1 CONEXION DOMICILIARIA 200M T. CONGLOMERADO S/. 39,819.78

    16.06.02.2 CONEXION DOMICILIARIA 160M T. CONGLOMERADO S/. 1,265.37

    16.06.03 FLETE

    16.06.03.1 FLETE TERRESTRE ALCANTARILLADO S/. 6.67

    16.06.04 CONTROL DE CALIDAD

    16.06.04.1 DISEO DE MEZCLAS DE CONCRETO S/. 18.08 S/. 17.50 S/. 18.08 S/. 17.50 S/. 10.50

    16.06.04.2 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 58.38 S/. 56.50 S/. 58.38 S/. 56.50 S/. 52.73

    16.06.05 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES

    16.06.05.1 CONSTRUCCION DE 2 LAGUNAS FACULTATIVAS EN PARALELO. AREA TOTAL=2.2HA S/. 18,426.93

    16.06.05.2 CONSTRUCCION DE CERCO PERIMETRICO S/. 2,513.13

    17.00.00 TANQUE IMHOFF - CAMARAS DE REJAS Y DESARENADOR

    17.01.00 OBRAS PRELIMINARES

    17.01.01 TRAZO Y REPLANTEO

    17.01.02 LIMPIEZA DE TERRENO MANUAL

    17.02.00 MOVIMIENTO DE TIERRAS17.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M

    17.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO

    17.03.00 OBRAS DE CONCRETO SIMPLE

    17.03.01 CONCRETO FC=140 KG/CM2

    17.03.02 ACERO FY = 4200 KG/CM2.

    17.03.03 ENCOFRADO Y DESENCOFRADO

    17.04.00 REVOQUES Y ENLUCIDOS

    17.04.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR

    17.04.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA

    17.05.00 EQUIPAMIENTO

    17.05.01 COMPUERTA METALICA DE 0.30X0.50 E=3/16

    17.05.02 PLANCHA METALICA 0.65X0.4 DE E=1/2

    17.05.03 REJA P/RETENCION DE SO LIDOS PLAT. 11/2X3/8 MARCO L 11/2X11/2X1/4

    18.00.00 TANQUE IMHOFF

    18.01.00 OBRAS PRELIMINARES

    18.01.01 TRAZO Y REPLANTEO

    18.01.02 LIMPIEZA DE TERRENO MANUAL

    18.02.00 MOVIMIENTO DE TIERRAS

    18.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M18.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO

    18.03.00 OBRAS DE CONCRETO SIMPLE

    18.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2

    18.04.00 OBRAS DE CONCRETO ARMADO

    18.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2

    18.04.02 ACERO FY = 4200 KG/CM2.

    18.04.03 ENCOFRADO Y DESENCOFRADO

    18.05.00 REVOQUES Y ENLUCIDOS

    18.05.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR

    18.05.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA

    19.00.00 LECHO DE SECADO

    19.01.00 OBRAS PRELIMINARES

    M8 M9 M10 M11 M12 M13 M14 M15

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 11

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    12/18

    19.01.01 TRAZO Y REPLANTEO

    19.01.02 LIMPIEZA DE TERRENO MANUAL

    19.02.00 MOVIMIENTO DE TIERRAS

    19.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M

    19.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO

    19.03.00 OBRAS DE CONCRETO SIMPLE

    19.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2

    19.04.00 OBRAS DE CONCRETO ARMADO

    19.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2

    19.04.02 ACERO FY = 4200 KG/CM2.

    19.04.03 ENCOFRADO Y DESENCOFRADO

    19.05.00 MUROS DE MAMPOSTERIA

    19.05.01 MURO DE SOGA LADRILLO PANDERETA CON CEMENTO - CAL - ARENA19.05.02 CUBIERTA DE LADRILLO PASTELERO ASENTADO Y FRAGUADO

    19.06.00 REVOQUES Y ENLUCIDOS

    19.06.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR

    19.07.00 SUMINISTRO Y COLOCACION

    19.07.01 ARENA GRUESA SELECCIONADA

    19.07.02 PIEDRA CLASIFICADA DE 3/4 - 2

    19.07.03 PIEDRA CLASIFICADA DE 1/4 - 3/4

    19.07.04 PIEDRA CLASIFICADA DE 1/16 - 1/4

    20.00.00 MITIGACION AMBIENTAL

    20.01.00 MITIGACION AMBIENTAL S/. 563.64 S/. 545.45 S/. 563.64 S/. 545.45 S/. 563.64 S/. 563.64 S/. 545.45

    Total S/. 359,852.39 S/. 118,368.49 S/. 119,625.84 S/. 115,766.94 S/. 119,612.61 S/. 119,549.38 S/. 115,692.94

    M8 M9 M10 M11 M12 M13 M14 M15

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 12

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    13/18

    MEJORAMIENTO Y AMPLIACION DEL SAP Y ALCANTARILLADO TEMBLADERA

    01.00.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL

    01.01.00 CARTEL DE OBRA CON GIGANTOGRAFA DIGITAL S/. 1,279.38

    02.00.00 CAJA DE CAPTACIN DE FONDO

    02.01.00 TRABAJOS PRELIMINARES

    02.01.01 DEMOLICION DE CONCRETO ARMADO EN TECHO DE CAPTACION S/. 3,840.41

    02.01.02 LIMPIEZA DE TERRENO, CAPTACIN S/. 109.20

    02.01.03 TRAZO Y REPLANTEO S/. 6.85

    02.02.00 MOVIMIENTO DE TIERRAS

    02.02.01 EXCAVACIN MANUAL CAJA DE VALVULAS S/. 28.81

    02.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 21.36

    02.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 1.62

    02.03.00 OBRAS DE CONCRETO SIMPLE02.03.01 CONCRETO FC=140 KG/CM2 (CAJA VLVULAS) S/. 9,893.62

    02.03.02 PIEDRA 4" ASENTADA CON MORTERO 1:8 EN CAPTACION S/. 572.48

    02.03.03 ENCOFRADO Y DESENCOFRADO S/. 43.43

    02.04.00 OBRAS DE CONCRETO ARMADO

    02.04.01 CONCRETO FC=175 KG/CM2 S/. 4,968.85

    02.04.02 ACERO FY = 4200 KG/CM2. S/. 331.64

    02.04.03 ENCOFRADO Y DESENCOFRADO S/. 1,787.14

    02.05.00 REVOQUES Y ENLUCIDOS

    02.05.01 TARRAJEO EXTERIOR S/. 1,015.11

    02.05.02 TARRAJEO INTERIOR S/. 1,695.04

    02.06.00 VALVULAS Y ACCESORIOS

    02.06.01 VALVULAS Y ACCESORIOS 8" S/. 768.53

    02.07.00 VARIOS

    02.07.01 PINTADO DE ESTRUCTURAS S/. 534.32

    02.07.02 TAPA SANITARIA 0.60X0.60 S/. 271.72

    03.00.00 LINEA DE CONDUCCIN A R1

    03.01.00 TRABAJOS PRELIMINARES

    03.01.01 TRAZO Y REPLANTEO S/. 2,132.47

    03.02.00 EXCAVACIN DE ZANJAS03.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 15,376.10

    03.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA S/. 88,011.78

    03.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS. S/. 5,764.59

    03.02.04 CAMA DE APOYO PARA TUBERA S/. 709.49

    03.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 65,036.40

    03.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS

    03.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5 S/. 311,484.94

    03.04.00 PRUEBA HIDRAULICA

    03.04.01 PRUEBA HIDRULICA + DESINFECCIN S/. 3,153.28

    04.00.00 LINEA DE CONDUCCIN A R2

    04.01.00 TRABAJOS PRELIMINARES

    04.01.01 TRAZO Y REPLANTEO S/. 2,270.89

    04.02.00 EXCAVACIN DE ZANJAS

    04.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 15,376.10

    04.02.02 EXCAVACION DE ZANJAS EN ROCA FISURADA S/. 95,293.49

    04.02.03 REFINE, NIVELACIN Y COMPACTACIN DE FONDOS. S/. 6,142.50

    04.02.04 CAMA DE APOYO PARA TUBERA S/. 756.00

    04.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 69,300.00

    04.03.00 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS04.03.01 SUMINISTRO E INSTALACION DE TUBERIA U.F. =200 MM. C-5 S/. 331,905.00

    04.04.00 PRUEBA HIDRAULICA

    04.04.01 PRUEBA HIDRULICA + DESINFECCIN S/. 3,360.00

    05.00.00 RESERVORIO CIRCULAR APOYADO: 100 M3

    05.01.00 TRABAJOS PRELIMINARES

    05.01.01 LIMPIEZA DE TERRENO MANUAL S/. 58.83

    05.01.02 TRAZO Y REPLANTEO S/. 115.96

    05.02.00 MOVIMIENTO DE TIERRAS

    05.02.01 EXCAVACION MANUAL S/. 499.90

    05.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 464.77

    05.02.03 NIVELACION Y COMPACTACION MANUAL S/. 91.74

    05.02.04 AFIRMADO S/. 244.65

    TotalM15 M16 M17 M18 M19 M20

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 13

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    14/18

    05.03.00 OBRAS DE CONCRETO SIMPLE

    05.03.01 SOLADO DE CONCRETO FC=100 KG/CM2 S/. 131.78

    05.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO S/. 364.54

    05.03.03 OBRAS DE CONCRETO ARMADO

    05.03.04 CONCRETO FC = 210 KG/CM2 S/. 42,636.38

    05.03.05 ENCOFRADO Y DESENCOFRADO S/. 3,979.13

    05.03.06 ACERO FY = 4200 KG/CM2. S/. 9,720.33

    05.04.00 REVOQUES Y ENLUCIDOS

    05.04.01 TARRAJEO EXTERIOR S/. 3,332.14

    05.04.02 TARRAJEO INTERIOR S/. 2,850.49

    05.04.03 PENDIENTE DE FONDO, MORTERO 1:5 S/. 1,385.27

    05.05.00 VALVULAS Y ACCESORIOS

    05.06.01 ACCESORIOS PARA VENTILACIN S/. 625.9205.07.00 VARIOS

    05.07.01 PINTURA EN EXTERIORES S/. 1,047.95

    05.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR S/. 3,543.03

    05.07.03 TAPA SANITARIA METLICA S/. 165.86

    06.00.00 RESERVORIO CIRCULAR APOYADO: 75 M3

    06.01.00 TRABAJOS PRELIMINARES

    06.01.01 LIMPIEZA DE TERRENO MANUAL S/. 52.80

    06.01.02 TRAZO Y REPLANTEO S/. 101.39

    06.02.00 MOVIMIENTO DE TIERRAS

    06.02.01 EXCAVACION MANUAL S/. 437.09

    06.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 406.39

    06.02.03 NIVELACION Y COMPACTACION MANUAL S/. 80.22

    06.02.04 AFIRMADO S/. 427.96

    06.03.00 OBRAS DE CONCRETO SIMPLE

    06.03.01 SOLADO DE CONCRETO FC=100 KG/CM2 S/. 115.36

    06.03.02 EMBOQUILLADO PERIMETRAL RESERVORIO S/. 12,794.25

    06.03.03 OBRAS DE CONCRETO ARMADO

    06.03.04 CONCRETO FC = 210 KG/CM2 S/. 17,578.49

    06.03.05 ENCOFRADO Y DESENCOFRADO S/. 3,679.2706.03.06 ACERO FY = 4200 KG/CM2. S/. 8,619.09

    06.04.00 REVOQUES Y ENLUCIDOS

    06.04.01 TARRAJEO EXTERIOR S/. 3,183.93

    06.04.02 TARRAJEO INTERIOR S/. 2,575.35

    06.04.03 PENDIENTE DE FONDO, MORTERO 1:5 S/. 1,180.27

    06.05.00 VALVULAS Y ACCESORIOS

    06.06.00 ACCESORIOS PARA VENTILACIN S/. 625.92

    06.07.00 VARIOS

    06.07.01 PINTURA EN EXTERIORES S/. 652.63

    06.07.02 SUMINISTRO Y COLOCACIN DE DOSIFICADOR S/. 3,543.03

    06.07.03 TAPA SANITARIA METLICA S/. 165.86

    07.00.00 CASETA DE VALVULAS

    07.01.00 TRABAJOS PRELIMINARES

    07.01.01 LIMPIEZA DE TERRENO MANUAL S/. 23.39

    07.01.02 TRAZO Y REPLANTEO S/. 37.65

    07.02.00 MOVIMIENTO DE TIERRAS

    07.02.01 EXCAVACION MANUAL S/. 188.69

    07.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 175.45

    07.02.03 NIVELACION Y COMPACTACION MANUAL S/. 29.7907.02.04 LECHO DE GRAVA S/. 132.91

    07.03.00 OBRAS DE CONCRETO SIMPLE

    07.03.01 CONCRETO FC=175 KG/CM2 S/. 1,293.78

    07.03.02 ENCOFRADO Y DESENCOFRADO S/. 738.82

    07.04.00 OBRAS DE CONCRETO ARMADO

    07.04.01 CONCRETO FC=175 KG/CM2 S/. 406.70

    07.04.02 ACERO FY = 4200 KG/CM2. S/. 381.62

    07.04.03 ENCOFRADO Y DESENCOFRADO DE LOSA S/. 328.02

    07.05.00 REVOQUES Y ENLUCIDOS

    07.05.01 TARRAJEO EXTERIOR S/. 743.74

    07.05.02 TARRAJEO INTERIOR S/. 506.09

    07.06.03 VALVULAS Y ACCESORIOS DE 8" (INGRESO CASETA)

    TotalM15 M16 M17 M18 M19 M20

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 14

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    15/18

    07.06.03.1 VALVULAS Y ACCESORIOS 8" (INGRESO CAS. VALVULAS) S/. 768.53

    07.07.00 VARIOS

    07.07.01 TAPA SANITARIA METLICA S/. 331.72

    07.07.02 PINTURA EN EXTERIORES S/. 455.92

    08.00.00 RED DE DISTRIBUCIN R1 Y R2

    08.01.00 TRABAJOS PRELIMINARES

    08.01.01 TRAZO Y REPLANTEO S/. 651.95 S/. 630.92 S/. 252.37 S/. 10,515.33

    08.02.00 MOVIMIENTO DE TIERRAS

    08.02.01 EXCAVACION DE ZANJAS EN TERRENO CONGLOMERADO S/. 22,988.74 S/. 22,247.17 S/. 2,966.29 S/. 364,853.57

    08.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 805.48 S/. 779.50 S/. 77.95 S/. 12,757.78

    08.02.03 REFINE Y CONFORMACIN DE FONDOS S/. 1,711.78 S/. 1,656.56 S/. 1,546.12 S/. 28,437.62

    08.02.04 CAMA DE APOYO PARA TUBERA S/. 1,170.44 S/. 1,132.69 S/. 1,132.69 S/. 19,444.46

    08.02.05 RELLENO Y COMPACTACIN DE ZANJAS S/. 19,312.34 S/. 18,689.36 S/. 19,312.34 S/. 14,951.49 S/. 320,834.0308.02.06 OBRAS DE CONCRETO SIMPLE

    08.02.06.1 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 12,559.83 S/. 12,154.67 S/. 12,559.83 S/. 12,559.83 S/. 207,439.75

    08.03.00 TUBERA Y ACCESORIOS

    08.03.01 SUMINISTRO E INSTALACION TUBERA U.F. 160 MM. C-7.5 S/. 10,644.26 S/. 10,300.89 S/. 10,644.26 S/. 8,240.71 S/. 181,982.46

    08.03.02 SUMINISTRO TUBERA U.F. 110 MM. C-7.5 S/. 7,211.47 S/. 6,978.84 S/. 7,211.47 S/. 5,583.07 S/. 123,292.86

    08.03.03 SUMINISTRO TUBERA U.F. 90 MM. C-7.5 S/. 148.96 S/. 144.16 S/. 148.96 S/. 115.32 S/. 2,546.76

    08.03.04 SUMINISTRO TUBERA U.F. 63 MM. C-7.5 S/. 1,145.58 S/. 1,108.63 S/. 1,145.58 S/. 886.90 S/. 19,585.75

    08.03.05 TUBERA PVC SAP 1/2" C-7.5 S/. 14,182.72 S/. 13,725.21 S/. 14,182.72 S/. 10,980.17 S/. 242,478.74

    08.05.00 ACCESORIOS DE RED DE DISTRIBUCION

    08.05.01 TEE PVC 6"X6" S/. 2.64 S/. 2.55 S/. 2.64 S/. 0.34 S/. 43.40

    08.05.02 TEE PVC 6"X4" S/. 2.64 S/. 2.55 S/. 2.64 S/. 0.34 S/. 43.40

    08.05.03 TEE PVC 4"X4" S/. 1.02 S/. 0.98 S/. 1.02 S/. 0.13 S/. 16.73

    08.05.04 TEE PVC 2"X2" S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.03 S/. 3.34

    08.05.05 TEE PVC 6"X2" S/. 1.83 S/. 1.77 S/. 1.83 S/. 0.24 S/. 30.10

    08.05.06 REDUC. PVC 6"-2" S/. 1.83 S/. 1.77 S/. 1.83 S/. 0.24 S/. 30.10

    08.05.07 CODO. PVC 4"X 90 S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.03 S/. 3.34

    08.05.08 CODO. PVC 6"X 90 S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.08 S/. 10.03

    08.05.09 CRUZ PVC 6"X6" S/. 2.23 S/. 2.16 S/. 2.23 S/. 0.29 S/. 36.71

    08.05.10 CRUZ PVC 6"X4" S/. 3.86 S/. 3.73 S/. 3.86 S/. 0.50 S/. 63.4708.05.11 CRUZ PVC 6"X2" S/. 0.61 S/. 0.59 S/. 0.61 S/. 0.08 S/. 10.03

    08.05.12 CRUZ PVC 4"X4" S/. 0.81 S/. 0.79 S/. 0.81 S/. 0.10 S/. 13.36

    08.05.13 CRUZ PVC 4"X2" S/. 0.20 S/. 0.20 S/. 0.20 S/. 0.03 S/. 3.34

    08.06.00 PRUEBA HIDRAULICA

    08.06.01 PRUEBA HIDRAULICA+DESINFECCION S/. 945.54 S/. 915.03 S/. 945.54 S/. 122.00 S/. 15,555.59

    09.00.00 CAJA DE VALVULAS DE CONTROL

    09.01.00 TRABAJOS PRELIMINARES

    09.01.01 LIMPIEZA DE TERRENO MANUAL S/. 7.05 S/. 6.82 S/. 5.00 S/. 115.96

    09.01.02 TRAZO Y REPLANTEO S/. 3,673.55 S/. 3,555.05 S/. 2,725.54 S/. 60,435.84

    09.02.00 MOVIMIENTO DE TIERRAS

    09.02.01 EXCAVACION MANUAL S/. 397.42 S/. 384.60 S/. 358.96 S/. 6,538.20

    09.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 577.85 S/. 559.21 S/. 410.08 S/. 9,506.56

    09.02.03 NIVELACION INTERIOR APISONADO MANUAL S/. 14.44 S/. 13.97 S/. 10.25 S/. 237.54

    09.03.00 CONCRETO SIMPLE

    09.03.01 CONCRETO FC=140 KG/CM2 S/. 218.47 S/. 211.43 S/. 155.05 S/. 3,594.24

    09.03.02 ENCOFRADO Y DESENCOFRADO S/. 269.74 S/. 261.04 S/. 191.43 S/. 4,437.66

    09.04.00 TARRAJEO

    09.04.01 TARRAJEO EXTERIOR S/. 91.39 S/. 88.44 S/. 64.85 S/. 1,503.49

    09.05.00 VALVULAS Y ACCESORIOS09.05.01 VALVULAS Y ACCESORIOS 4" S/. 1.62 S/. 1.57 S/. 1.15 S/. 26.67

    09.05.02 VALVULAS Y ACCESORIOS 6" S/. 1.62 S/. 1.57 S/. 1.15 S/. 26.67

    09.05.03 VALVULAS Y ACCESORIOS 2" S/. 2.03 S/. 1.96 S/. 1.44 S/. 33.37

    09.06.00 VARIOS

    09.06.01 TAPA SANITARIA METLICA S/. 165.86 S/. 165.86

    10.00.00 CAJA DE VALVULAS DE PURGA

    10.01.00 TRABAJOS PRELIMIINARES

    10.01.01 LIMPIEZA DE TERRENO MANUAL S/. 20.50 S/. 17.94 S/. 38.44

    10.01.02 TRAZO Y REPLANTEO S/. 70.89 S/. 70.89

    10.02.00 MOVIMIENTO DE TIERRAS

    10.02.01 EXCAVACION MANUAL S/. 479.36 S/. 479.36

    10.02.02 ELIMINACION DE MATERIAL EXCEDENTE S/. 133.71 S/. 311.99 S/. 445.70

    TotalM15 M16 M17 M18 M19 M20

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 15

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    16/18

    10.03.00 OBRAS DE CONCRETO SIMPLE

    10.03.01 CONCRETO FC=140 KG/CM2 S/. 1,208.78 S/. 1,208.78

    10.03.02 ENCOFRADO Y DESENCOFRADO S/. 1,104.90 S/. 1,104.90

    10.04.00 TARRAJEO

    10.04.01 TARRAJEO EXTERIOR S/. 698.03 S/. 698.03

    10.05.00 VALVULAS Y ACCESORIOS PURGA S/. 10.69 S/. 16.03 S/. 26.72

    10.06.00 VARIOS

    10.06.01 TAPA SANITARIA METLICA S/. 431.24 S/. 1,724.94 S/. 2,156.18

    11.00.00 CONEXIONES DOMICILIARIAS

    11.01.00 TRABAJOS PRELIMIINARES

    11.01.01 LIMPIEZA DE TERRENO MANUAL S/. 406.11 S/. 393.01 S/. 157.20 S/. 6,550.16

    11.01.02 TRAZO Y REPLANTEO S/. 749.05 S/. 724.89 S/. 338.28 S/. 12,081.48

    11.02.00 MOVIMIENTO DE TIERRAS11.02.01 EXCAVACION MANUAL S/. 2,422.23 S/. 2,344.10 S/. 1,484.60 S/. 39,068.28

    11.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 251.25 S/. 243.14 S/. 153.99 S/. 4,052.38

    11.02.03 RELLENO Y COMPACTACIN DE ZANJAS S/. 160,116.00

    11.03.00 OBRAS DE CONCRETO SIMPLE

    11.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 4,085.31 S/. 3,953.52 S/. 4,085.31 S/. 395.35 S/. 65,892.06

    11.03.02 CONCRETO FC=140 KG/CM2 S/. 416.67 S/. 403.23 S/. 416.67 S/. 40.32 S/. 6,720.49

    11.03.03 ENCOFRADO Y DESENCOFRADO S/. 640.74 S/. 620.07 S/. 640.74 S/. 62.01 S/. 10,334.51

    11.04.00 OBRAS DE CONCRETO ARMADO

    11.04.01 CONCRETO FC=175 KG/CM2 S/. 133.02 S/. 128.73 S/. 133.02 S/. 12.87 S/. 2,145.49

    11.04.02 ACERO FY = 4200 KG/CM2. S/. 88.26 S/. 85.41 S/. 88.26 S/. 8.54 S/. 1,423.52

    11.04.03 ENCOFRADO Y DESENCOFRADO S/. 97.61 S/. 94.46 S/. 97.61 S/. 9.45 S/. 1,574.35

    11.05.00 CONEXIONES DOMICILIARIAS

    11.05.01 CONEXIN DOMICILIARIA DE AGUA 6" S/. 86.97 S/. 84.17 S/. 81.36 S/. 1,402.78

    11.05.02 CONEXIN DOMICILIARIA DE AGUA 4" S/. 99.40 S/. 96.19 S/. 92.99 S/. 1,603.21

    11.05.03 CONEXIN DOMICILIARIA DE AGUA 3" S/. 6.83 S/. 6.61 S/. 6.39 S/. 110.17

    11.05.04 CONEXIN DOMICILIARIA DE AGUA 2" S/. 57.98 S/. 56.11 S/. 54.24 S/. 935.17

    11.05.05 SUMINISTRO E INSTALACION DE MEDIDORES S/. 10,172.36 S/. 9,844.22 S/. 9,516.08 S/. 164,070.33

    12.00.00 CASETA DE CLORACIN

    12.01.00 MUROS DE LADRILLOS DE SOGA S/. 667.4612.02.00 COBERTURA DE CALAMINA S/. 16.35

    12.03.00 CARPINTERIA METALICA S/. 1,305.21

    12.04.00 TARRAJEO EM MUROS S/. 215.03

    12.05.00 CERRAJERIA S/. 18.86

    12.06.00 PINTURA EN MUROS S/. 241.53

    12.07.00 VIDRIOS S/. 163.62

    13.00.00 EDUCACIN SANITARIA Y CAPACITACION EN AOM.

    13.01.00 EDUCACIN SANITARIA S/. 28,800.00

    13.03.00 CAPACITACIN EN A+O+M S/. 153,297.00

    14.00.00 FLETE

    14.01.00 FLETE TERRESTRE S/. 238.46 S/. 230.77 S/. 238.46 S/. 7.69 S/. 3,999.99

    14.02.00 FLETE RURAL S/. 238.46 S/. 230.77 S/. 238.46 S/. 7.69 S/. 3,999.99

    15.00.00 CONTROL DE CALIDAD

    15.01.00 DISE O DE MEZCLAS DE CONCRETO S/. 31.30 S/. 30.29 S/. 31.30 S/. 1.01 S/. 525.03

    15.02.00 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 10.78 S/. 10.43 S/. 10.78 S/. 0.35 S/. 180.81

    16.00.00 DESAGE

    16.01.00 OBRAS PRELIMINARES

    16.01.01 LIMPIEZA DE TERRENO MANUAL S/. 8,950.41

    16.01.02 TRAZO Y REPLANTEO S/. 10,393.6316.01.03 CINTA DE PELIGRO S/. 40,000.56

    16.02.00 MOVIMIENTO DE TIERRAS

    16.02.01 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 80,076.33

    16.02.02 CORTE DE PAVIMENTO CON MOLADORA S/. 12,757.79

    16.02.03 EXCAVACION C/MAQ EN TERRENO CONGLOMERADO HASTA 2.40 MPROF. S/. 2,756.37

    16.02.04 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 109,749.00

    16.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA S/. 3,334.95

    16.03.00 OBRAS DE CONCRETO SIMPLE

    16.03.01 REPOSICION DE CONCRETO EN PAVIMENTO FC=210KG/CM2 S/. 207,439.77

    16.04.00 SUMINISTRO E INSTALACION DE TUBERIA

    16.04.01 SUMINISTRO E INSTALACION TUBERIA PVC 200 mm.x 6m S26 S/. 486,968.36

    16.04.02 REFINE, NIVELACION Y CONF. DE FONDO T.C. S/. 97,261.07

    TotalM15 M16 M17 M18 M19 M20

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 16

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    17/18

    16.04.03 PREPARACION DE CAMA DE APOYO P/TUBERIA S/. 14,296.69

    16.04.04 INSTALACION TUBERIA PVC 200 MM.X 6M S25 S/. 107,670.07

    16.04.05 CONEXION DE TUBERIA PVC A CONCRETO DE BUZON S/. 15,864.25

    16.04.06 PRUEBA HIDRAULICA EN TUBERIA PVC S/. 7,491.82

    16.05.00 CONSTRUCCION DE BUZONES

    16.05.01 BUZON ESTANDAR HASTA 0.70M DE PROF. S/. 4,155.54

    16.05.02 BUZON ESTANDAR HASTA 0.80M DE PROF. S/. 6,233.31

    16.05.03 BUZON ESTANDAR HASTA 0.90M DE PROF. S/. 2,077.76

    16.05.04 BUZON ESTANDAR HASTA 1.20M DE PROF. S/. 302,591.52

    16.05.05 BUZON ESTANDAR HASTA 2.40M DE PROF. S/. 5,070.27

    16.06.00 CONEXIONES DOMICILIARIAS

    16.06.01 MOVIMIENTO DE TIERRAS

    16.06.01.1 EXCAVACION MANUAL DE ZANJAS EN TERRENO CONGLOMERADO S/. 68,369.5216.06.01.2 CORTE DE PAVIMENTO CON MOLADORA S/. 6,331.86

    16.06.01.3 RELLENO CON MATERIAL PROPIO S/. 37,724.29

    16.06.01.4 RELLENO Y COMPACTACION DE ZANJAS CON MATERIAL PROPIO SELECCIONADO S/. 430,554.36

    16.06.02 TENDIDO E INSTALACION DE TUBERIAS

    16.06.02.1 CONEXION DOMICILIARIA 200M T. CONGLOMERADO S/. 421,621.20

    16.06.02.2 CONEXION DOMICILIARIA 160M T. CONGLOMERADO S/. 13,398.00

    16.06.03 FLETE

    16.06.03.1 FLETE TERRESTRE ALCANTARILLADO S/. 600.00

    16.06.04 CONTROL DE CALIDAD

    16.06.04.1 DISEO DE MEZCLAS DE CONCRETO S/. 105.00

    16.06.04.2 ENSAYO A LA COMPRESIN DE PROBETAS DE CONCRETO S/. 338.99

    16.06.05 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES

    16.06.05.1 CONSTRUCCION DE 2 LAGUNAS FACULTATIVAS EN PARALELO. AREA TOTAL=2.2HA S/. 147,415.44

    16.06.05.2 CONSTRUCCION DE CERCO PERIMETRICO S/. 2,513.13

    17.00.00 TANQUE IMHOFF - CAMARAS DE REJAS Y DESARENADOR

    17.01.00 OBRAS PRELIMINARES

    17.01.01 TRAZO Y REPLANTEO S/. 39.84

    17.01.02 LIMPIEZA DE TERRENO MANUAL S/. 21.06

    17.02.00 MOVIMIENTO DE TIERRAS17.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 61.42

    17.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 104.86

    17.03.00 OBRAS DE CONCRETO SIMPLE

    17.03.01 CONCRETO FC=140 KG/CM2 S/. 1,203.44

    17.03.02 ACERO FY = 4200 KG/CM2. S/. 680.24

    17.03.03 ENCOFRADO Y DESENCOFRADO S/. 877.93

    17.04.00 REVOQUES Y ENLUCIDOS

    17.04.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 1,113.16

    17.04.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA S/. 102.71

    17.05.00 EQUIPAMIENTO

    17.05.01 COMPUERTA METALICA DE 0.30X0.50 E=3/16 S/. 470.84

    17.05.02 PLANCHA METALICA 0.65X0.4 DE E=1/2 S/. 840.21

    17.05.03 REJA P/RETENCION DE SOLIDOS PLAT. 11/2X3/8 MARCO L 11/2X11/2X1/4 S/. 73.54

    18.00.00 TANQUE IMHOFF

    18.01.00 OBRAS PRELIMINARES

    18.01.01 TRAZO Y REPLANTEO S/. 91.68

    18.01.02 LIMPIEZA DE TERRENO MANUAL S/. 43.88

    18.02.00 MOVIMIENTO DE TIERRAS

    18.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 1,858.83

    18.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 4,293.94

    18.03.00 OBRAS DE CONCRETO SIMPLE

    18.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2 S/. 44.34

    18.04.00 OBRAS DE CONCRETO ARMADO

    18.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2 S/. 13,039.81

    18.04.02 ACERO FY = 4200 KG/CM2. S/. 14,438.31

    18.04.03 ENCOFRADO Y DESENCOFRADO S/. 5,391.86

    18.05.00 REVOQUES Y ENLUCIDOS

    18.05.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 3,421.12

    18.05.02 TARRAJEO EN EXTERIORES CON CEMENTO Y ARENA S/. 220.89

    19.00.00 LECHO DE SECADO

    19.01.00 OBRAS PRELIMINARES

    TotalM15 M16 M17 M18 M19 M20

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 17

  • 7/21/2019 Cronograma Fisico Financiero Agua Potable

    18/18

    19.01.01 TRAZO Y REPLANTEO S/. 249.00

    19.01.02 LIMPIEZA DE TERRENO MANUAL S/. 135.00

    19.02.00 MOVIMIENTO DE TIERRAS

    19.02.01 EXCAVACION DE ZANJAS MANUAL PARA CAMARA Y DESARENADOR H=1.8 M S/. 671.90

    19.02.02 NIVELACION INT. Y APISONADO FINAL DEL TERRENO PREVIO AL PISO S/. 11,176.38

    19.03.00 OBRAS DE CONCRETO SIMPLE

    19.03.01 FALSO PISO DE CONCRETO FC = 140 KG/CM2 S/. 149.04

    19.04.00 OBRAS DE CONCRETO ARMADO

    19.04.01 CONCRETO EN LOSA DE CIMENTACION FC = 175 KG/CM2 S/. 4,213.07

    19.04.02 ACERO FY = 4200 KG/CM2. S/. 97.30

    19.04.03 ENCOFRADO Y DESENCOFRADO S/. 7,365.86

    19.05.00 MUROS DE MAMPOSTERIA

    19.05.01 MURO DE SOGA LADRILLO PANDERETA CON CEMENTO - CAL - ARENA S/. 646.2419.05.02 CUBIERTA DE LADRILLO PASTELERO ASENTADO Y FRAGUADO S/. 20,666.22

    19.06.00 REVOQUES Y ENLUCIDOS

    19.06.01 TARRAJEO CON IMPERMEBILIZANTES INTERIOR S/. 2,292.86

    19.07.00 SUMINISTRO Y COLOCACION

    19.07.01 ARENA GRUESA SELECCIONADA S/. 998.25

    19.07.02 PIEDRA CLASIFICADA DE 3/4 - 2 S/. 1,250.85

    19.07.03 PIEDRA CLASIFICADA DE 1/4 - 3/4 S/. 312.48

    19.07.04 PIEDRA CLASIFICADA DE 1/16 - 1/4 S/. 468.72

    20.00.00 MITIGACION AMBIENTAL

    20.01.00 MITIGACION AMBIENTAL S/. 563.64 S/. 545.45 S/. 563.64 S/. 563.64 S/. 10,000.01

    Total S/. 119,569.88 S/. 116,394.84 S/. 98,430.57 S/. 56,291.81 S/. 6,254,896.05

    TotalM15 M16 M17 M18 M19 M20

    CRONOGRAMA DE AVANCE FISICO FINANCIERO

    Pgina 18

top related