NOMBRE DE LA ENTIDAD: GOBIERNO AUTONOMO DESCENTRALIZADO MUNICIPAL DE PAQUISHA PROYECTO: CONSTRUCCION DE LA CUBIERTA PARA LA CANCHA DE USO MULTIPLE DEL BARRIO SANTA ROSA, PARROQUIA PAQUISHA, CANTON PAQUISHA CRONOGRAMA VALORADO DE TRABAJOS RUBRO Unid. CANTIDAD PRECIO PRECIO TIEMPO EN MESES UNITARIO TOTAL M1 M2 01 - CUBIERTA DE ESTRUCTURA METALICA 1 EXCAVACION A MANO CIMIENTOS Y PLINTOS + DESALOJO M3 85.96 11.22 964.47 85.96 $ 964.47 2 EMPEDRADO BASE ESPESOR=20CM M2 27.00 7.98 215.46 27.00 $ 215.46 3 REPLANTILLO DE Ho.So F`c=180kg/cm2. ESP.=5cms. M3 1.35 149.23 201.46 1.35 $ 201.46 4 HORMIGÓN SIMPLE EN ZAPATAS F 'C= 210 KG/CM2 INCLUYE ENCOFRADO M3 8.10 183.69 1,487.89 8.10 $ 1,487.89 5 HORMIGON SIMPLE EN COLUMNAS FC=210 KG/CM2 INCLUYE ENCOFRADO M3 5.00 247.06 1,235.30 5.00 $ 1,235.30 6 ACERO ESTRUCTURAL EN PERFILES FY=2100 KG/CM2 (PROVISIÓN Y MONTAJE) KG 10,041.86 3.19 32,033.53 3,012.56 7,029.30 $ 9,610.06 $ 22,423.47 7 PLACA BASE COLUMNAS 660X300X6mm + PLACA SUPERIOR 640X280X6mm + ANCLAJE UN 12.00 106.03 1,272.36 12.00 $ 1,272.36 8 RELLENO COMP. MECAN. (MATERIAL DE MEJORAMIENTO) M3 84.76 16.45 1,394.30 84.76 $ 1,394.30 9 CUBIERTA DE GALVALUMEN PREPINTADA e=0,40mm M2 698.87 19.63 13,718.82 698.87 $ 13,718.82

Upload: jose-quilambaqui

Post on 16-Jan-2016

18 views

Category:

Documents


0 download

DESCRIPTION

presupuesto

TRANSCRIPT

Page 1: 3-Presupuesto y Cronograma Valorado

NOMBRE DE LA ENTIDAD: GOBIERNO AUTONOMO DESCENTRALIZADO MUNICIPAL DE PAQUISHA PROYECTO: CONSTRUCCION DE LA CUBIERTA PARA LA CANCHA DE USO MULTIPLE DEL BARRIO SANTA ROSA, PARROQUIA PAQUISHA, CANTON PAQUISHA

CRONOGRAMA VALORADO DE TRABAJOS

RUBRO Unid. CANTIDAD PRECIO PRECIO TIEMPO EN MESES

UNITARIO TOTAL M1 M2

01 - CUBIERTA DE ESTRUCTURA METALICA

1 EXCAVACION A MANO CIMIENTOS Y PLINTOS + DESALOJO

M3 85.96 11.22 964.47 85.96

$ 964.47

2 EMPEDRADO BASE ESPESOR=20CM M2 27.00 7.98 215.46 27.00

$ 215.46

3 REPLANTILLO DE Ho.So F`c=180kg/cm2. ESP.=5cms. M3 1.35 149.23 201.46 1.35

$ 201.46

4 HORMIGÓN SIMPLE EN ZAPATAS F 'C= 210 KG/CM2 INCLUYE ENCOFRADO

M3 8.10 183.69 1,487.89 8.10

$ 1,487.89

5

HORMIGON SIMPLE EN COLUMNAS FC=210 KG/CM2 INCLUYE ENCOFRADO

M3 5.00 247.06 1,235.30 5.00

$ 1,235.30

6 ACERO ESTRUCTURAL EN PERFILES FY=2100 KG/CM2 (PROVISIÓN Y MONTAJE)

KG 10,041.86 3.19 32,033.53 3,012.56 7,029.30

$ 9,610.06 $ 22,423.47

7

PLACA BASE COLUMNAS 660X300X6mm + PLACA SUPERIOR 640X280X6mm + ANCLAJE

UN 12.00 106.03 1,272.36 12.00

$ 1,272.36

8 RELLENO COMP. MECAN. (MATERIAL DE MEJORAMIENTO)

M3 84.76 16.45 1,394.30 84.76

$ 1,394.30

9 CUBIERTA DE GALVALUMEN PREPINTADA e=0,40mm

M2 698.87 19.63 13,718.82 698.87

$ 13,718.82

Page 2: 3-Presupuesto y Cronograma Valorado

10

CUBIERTA DE POLICARBONATO TIPO ONDULADO

M2 25.92 26.14 677.55 25.92

$ 677.55

11

CAJAS DE REVISIÓN 60X60X60CM INCL. TAPA H. ARMADO

U 6.00 82.13 492.78 6.00

$ 492.78

12 PINTURA ESMALTE M2 80.73 3.58 289.01 80.73

$ 289.01

13

CANAL TOL GALV. H=15 CM, A=20CM, DESARR. 60CM PINTADO

M 64.30 11.74 754.88 64.30

$ 754.88

14 ACERO DE REFUERZO KG 1,248.93 2.66 3,322.15 1,248.93

$ 3,322.15

15

BAJANTE DE AGUAS LLUVIAS PVC 110 MM M 34.80 7.63 265.52 34.80

$ 265.52

16

TUBERÍA PVC 4" Y ACCESORIOS M 65.00 6.77 440.05 26.00 39.00

$ 176.02 $ 264.03

17 TENSOR 5/8" U 24.00 10.02 240.48 24.00

$ 240.48

02 - SISTEMA ELECTRICO EN ILUMINACION

18

LUMINARIA DE ALUMINIO TIPO CAMPANA + FOCO OVOIDE DE 400 WATT, PARA CANCHA

PTO 9.00 247.63 2,228.67 9.00

$ 2,228.67

19

TABLERO DE DISTRIBUCION 4-8 PTOS.

U 1.00 89.62 89.62 1.00

$ 89.62

20

CONDUCTOR DE COBRE, TIPO TW, 12 AWG, doble hilo + manguera anillada

M 120.00 5.14 616.80 120.00

$ 616.80

21

ACOMETIDA DE ENERGÍA ELECTRICA

M 30.00 4.81 144.30 30.00

$ 144.30

62,085.40

Valores Parciales 19879.47 42,205.93

Valores Acumulados 19879.47 62085.4

Porcentajes Parciales 32.02% 67.98%

Porcentajes Acumulados 32.02% 100.00%