MINISTERIO DE TRANSPORTES Y COMUNICACIONES Proyecto Especial de Infraestructura de Transporte Rural PROVIAS RURAL VALORIZACION DE OBRA Nº 03 DEPARTAMENTO HUANCAVELICA CONTRATISTA : C & C CONSULTORES EJECUTORES CONTRATISTAS GENERALES SRL N° DE CONTRATO : SUPERVISOR EXTERNO : Ing. JUAN A. MEDINA CORTEGANA FECHA : MONTO DEL CONTRATO : 1,088,667.53 (CON IGV) S/. 914,846.66 (SIN IGV) PROVINCIA : MONTO DEL ADELANTO : 217,733.51 (CON IGV) S/. 184,519.92 (SIN IGV) DISTRITO : REHABILITACION DEL CAMINO VECIN TRAMO : QUINUAPATA-CCOTCCOY-PACCAY-MARAYPATA-ACCO-ALTARPATA-HUANCAVELICA META FISICA: 25+430 Km. ITEM DESCRIPCION PRESUPUESTO CONTRACTUAL AVANCE ACTUAL AVANCE ACUMUL. ANT. AVANCE ACUMUL. ACTUAL SAL UND. CANT. P.U. PARCIAL METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO 1.00.00 OBRAS PRELIMINARES 1.01.00 CAMPAMENTO UND 1.00 6,000.00 6,000.00 0.00 0.00 0.00 0.80 4,800.00 80.00 0.80 4,800.00 80.00 0.20 1.02.00 CARTEL DE OBRA UND 2.00 1,658.74 3,317.48 0.00 0.00 0.00 2.00 3,317.48 100.00 2.00 3,317.48 100.00 0.00 1.03.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO MECANICO GLB 1.00 8,000.00 8,000.00 0.00 0.00 0.00 0.50 4,000.00 50.00 0.50 4,000.00 50.00 0.50 1.04.00 TRAZO Y REPLANTEO KM 25.43 240.97 6,127.87 0.00 0.00 0.00 17.14 4,130.95 67.41 17.14 4,130.95 67.41 8.29 2.00.00 MOVIMIENTO DE TIERRAS 2.01.00 EXCAVACION NO CLASIFICADA PARA EXPLANACIONES M3 28,326.64 2.21 62,601.87 695.88 1,537.89 2.46 24,033.99 53,115.12 84.85 24,729.87 54,653.01 87.30 3,596.77 2.02.00 CONFORMACION DE TERRAPLENES M3 13,606.13 4.02 54,696.64 6,995.66 28,122.55 51.42 5,263.38 21,158.77 38.68 12,259.04 49,281.32 90.10 1,347.10 2.03.00 ELIMINACION LATERAL DE EXCED.SIN TRANSPORTE M3 12,139.40 1.98 24,036.01 53.74 106.41 0.44 10,325.92 20,445.32 85.06 10,379.66 20,551.73 85.50 1,759.74 3.00.00 PAVIMENTOS 3.01.00 MEJORAMIENTO DE LA SUBRASANTE (e= 0,20m) M2 6,027.00 5.36 32,304.72 0.00 0.00 0.00 2,439.50 13,075.72 40.48 2,439.50 13,075.72 40.48 3,587.50 3.02.00 PERFILADO Y COMPACTADO DE LA SUBRASANTE M2 45,538.85 1.07 48,726.57 17,296.00 18,506.72 37.98 24,302.75 26,003.94 53.37 41,598.75 44,510.66 91.35 3,940.10 EN ZONA DE CORTE 3.03.00 AFIRMADO (e=0.15m) M3 13,954.94 11.34 158,249.02 3,938.63 44,664.06 28.22 3,933.60 44,607.02 28.19 7,872.23 89,271.09 56.41 6,082.71 4.00.00 OBRAS DE ARTE 4.01.00 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS M3 1,415.41 7.10 10,049.41 284.00 2,016.40 20.06 515.66 3,661.21 36.43 799.66 5,677.61 56.50 615.75 4.02.00 RELLENO ESTRUCTURAL M3 641.86 6.85 4,396.74 123.40 845.29 19.23 219.18 1,501.36 34.15 342.58 2,346.65 53.37 299.28 4.03.00 CONCRETO CICLOPEO F'C=140KG/CM2+30%PM M3 57.93 150.41 8,713.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.93 4.04.00 CONCRETO CICLOPEO F'C=175KG/CM2+30%PM M3 586.33 170.31 99,857.86 126.75 21,586.79 21.62 203.96 34,735.69 34.79 330.71 56,322.48 56.40 255.62 4.05.00 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS M2 1,463.38 16.17 23,662.85 287.71 4,652.27 19.66 485.33 7,847.72 33.16 773.04 12,499.99 52.83 690.34 4.06.00 ENCOFRADO PERDIDO DE ALCANTARILLAS M 288.90 56.78 16,403.74 81.77 4,642.90 28.30 141.28 8,021.88 48.90 223.05 12,664.78 77.21 65.85 4.07.00 EMBOQUILLADO DE PIEDRA M3 179.60 155.15 27,864.94 9.17 1,422.73 5.11 19.78 3,069.30 11.01 28.95 4,492.03 16.12 150.65 4.08.00 MURO DE MAMPOSTERIA DE PIEDRA M3 105.97 94.84 10,050.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 105.97 4.09.00 CONFORMACION DE CUNETAS EN MATERIAL M 20,770.00 1.80 37,386.00 820.00 1,476.00 3.95 13,690.00 24,642.00 65.91 14,510.00 26,118.00 69.86 6,260.00 NO CLASIFICADO 5.00.00 TRANSPORTES 5.01.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 10,251.64 4.13 42,339.27 1,738.16 7,178.60 16.95 2,368.48 9,781.81 23.10 4,106.64 16,960.41 40.06 6,145.00 D <= 1KM

Upload: cortabrazoleonandersonvladimir

Post on 21-Dec-2015

9 views

Category:

Documents


0 download

DESCRIPTION

baden

TRANSCRIPT

Page 1: 03.01 Obras de Arte Badén Navan

MINISTERIO DE TRANSPORTES Y COMUNICACIONES

Proyecto Especial de Infraestructura de Transporte Rural

PROVIAS RURAL

VALORIZACION DE OBRA Nº 03DEPARTAMENTO HUANCAVELICA

CONTRATISTA : C & C CONSULTORES EJECUTORES CONTRATISTAS GENERALES SRL N° DE CONTRATO : 909-2004-MTC/21

SUPERVISOR EXTERNO : Ing. JUAN A. MEDINA CORTEGANA FECHA : 5-Dec-04

MONTO DEL CONTRATO : 1,088,667.53 (CON IGV) S/. 914,846.66 (SIN IGV) PROVINCIA : CHURCAMPA

MONTO DEL ADELANTO : 217,733.51 (CON IGV) S/. 184,519.92 (SIN IGV) DISTRITO : CHURCAMPA

REHABILITACION DEL CAMINO VECITRAMO : QUINUAPATA-CCOTCCOY-PACCAY-MARAYPATA-ACCO-ALTARPATA-HUANCAVELICA

META FISICA: 25+430 Km.

ITEM DESCRIPCION PRESUPUESTO CONTRACTUAL AVANCE ACTUAL AVANCE ACUMUL. ANT. AVANCE ACUMUL. ACTUAL SALDO POR VALORIZAR

UND. CANT. P.U. PARCIAL METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO %

1.00.00 OBRAS PRELIMINARES

1.01.00 CAMPAMENTO UND 1.00 6,000.00 6,000.00 0.00 0.00 0.00 0.80 4,800.00 80.00 0.80 4,800.00 80.00 0.20 1,200.00 20.00

1.02.00 CARTEL DE OBRA UND 2.00 1,658.74 3,317.48 0.00 0.00 0.00 2.00 3,317.48 100.00 2.00 3,317.48 100.00 0.00 0.00 0.00

1.03.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO MECANICO GLB 1.00 8,000.00 8,000.00 0.00 0.00 0.00 0.50 4,000.00 50.00 0.50 4,000.00 50.00 0.50 4,000.00 50.00

1.04.00 TRAZO Y REPLANTEO KM 25.43 240.97 6,127.87 0.00 0.00 0.00 17.14 4,130.95 67.41 17.14 4,130.95 67.41 8.29 1,996.92 32.59

2.00.00 MOVIMIENTO DE TIERRAS

2.01.00 EXCAVACION NO CLASIFICADA PARA EXPLANACIONES M3 28,326.64 2.21 62,601.87 695.88 1,537.89 2.46 24,033.99 53,115.12 84.85 24,729.87 54,653.01 87.30 3,596.77 7,948.86 12.70

2.02.00 CONFORMACION DE TERRAPLENES M3 13,606.13 4.02 54,696.64 6,995.66 28,122.55 51.42 5,263.38 21,158.77 38.68 12,259.04 49,281.32 90.10 1,347.09 5,415.32 9.90

2.03.00 ELIMINACION LATERAL DE EXCED.SIN TRANSPORTE M3 12,139.40 1.98 24,036.01 53.74 106.41 0.44 10,325.92 20,445.32 85.06 10,379.66 20,551.73 85.50 1,759.74 3,484.28 14.50

3.00.00 PAVIMENTOS

3.01.00 MEJORAMIENTO DE LA SUBRASANTE (e= 0,20m) M2 6,027.00 5.36 32,304.72 0.00 0.00 0.00 2,439.50 13,075.72 40.48 2,439.50 13,075.72 40.48 3,587.50 19,229.00 59.52

3.02.00 PERFILADO Y COMPACTADO DE LA SUBRASANTE M2 45,538.85 1.07 48,726.57 17,296.00 18,506.72 37.98 24,302.75 26,003.94 53.37 41,598.75 44,510.66 91.35 3,940.10 4,215.91 8.65

EN ZONA DE CORTE

3.03.00 AFIRMADO (e=0.15m) M3 13,954.94 11.34 158,249.02 3,938.63 44,664.06 28.22 3,933.60 44,607.02 28.19 7,872.23 89,271.09 56.41 6,082.71 68,977.93 43.59

4.00.00 OBRAS DE ARTE

4.01.00 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS M3 1,415.41 7.10 10,049.41 284.00 2,016.40 20.06 515.66 3,661.21 36.43 799.66 5,677.61 56.50 615.75 4,371.80 43.50

4.02.00 RELLENO ESTRUCTURAL M3 641.86 6.85 4,396.74 123.40 845.29 19.23 219.18 1,501.36 34.15 342.58 2,346.65 53.37 299.28 2,050.09 46.63

4.03.00 CONCRETO CICLOPEO F'C=140KG/CM2+30%PM M3 57.93 150.41 8,713.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.93 8,713.25 100.00

4.04.00 CONCRETO CICLOPEO F'C=175KG/CM2+30%PM M3 586.33 170.31 99,857.86 126.75 21,586.79 21.62 203.96 34,735.69 34.79 330.71 56,322.48 56.40 255.62 43,535.38 43.60

4.05.00 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS M2 1,463.38 16.17 23,662.85 287.71 4,652.27 19.66 485.33 7,847.72 33.16 773.04 12,499.99 52.83 690.34 11,162.86 47.17

4.06.00 ENCOFRADO PERDIDO DE ALCANTARILLAS M 288.90 56.78 16,403.74 81.77 4,642.90 28.30 141.28 8,021.88 48.90 223.05 12,664.78 77.21 65.85 3,738.96 22.79

4.07.00 EMBOQUILLADO DE PIEDRA M3 179.60 155.15 27,864.94 9.17 1,422.73 5.11 19.78 3,069.30 11.01 28.95 4,492.03 16.12 150.65 23,372.91 83.88

4.08.00 MURO DE MAMPOSTERIA DE PIEDRA M3 105.97 94.84 10,050.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 105.97 10,050.19 100.00

4.09.00 CONFORMACION DE CUNETAS EN MATERIAL M 20,770.00 1.80 37,386.00 820.00 1,476.00 3.95 13,690.00 24,642.00 65.91 14,510.00 26,118.00 69.86 6,260.00 11,268.00 30.14

NO CLASIFICADO

5.00.00 TRANSPORTES

5.01.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 10,251.64 4.13 42,339.27 1,738.16 7,178.60 16.95 2,368.48 9,781.81 23.10 4,106.64 16,960.41 40.06 6,145.00 25,378.86 59.94

D <= 1KM

Page 2: 03.01 Obras de Arte Badén Navan

MINISTERIO DE TRANSPORTES Y COMUNICACIONES

Proyecto Especial de Infraestructura de Transporte Rural

PROVIAS RURAL

VALORIZACION DE OBRA Nº 03DEPARTAMENTO HUANCAVELICA

CONTRATISTA : C & C CONSULTORES EJECUTORES CONTRATISTAS GENERALES SRL N° DE CONTRATO : 909-2004-MTC/21

SUPERVISOR EXTERNO : Ing. JUAN A. MEDINA CORTEGANA FECHA : 5-Dec-04

MONTO DEL CONTRATO : 1,088,667.53 (CON IGV) S/. 914,846.66 (SIN IGV) PROVINCIA : CHURCAMPA

MONTO DEL ADELANTO : 217,733.51 (CON IGV) S/. 184,519.92 (SIN IGV) DISTRITO : CHURCAMPA

REHABILITACION DEL CAMINO VECITRAMO : QUINUAPATA-CCOTCCOY-PACCAY-MARAYPATA-ACCO-ALTARPATA-HUANCAVELICA

META FISICA: 25+430 Km.

ITEM DESCRIPCION PRESUPUESTO CONTRACTUAL AVANCE ACTUAL AVANCE ACUMUL. ANT. AVANCE ACUMUL. ACTUAL SALDO POR VALORIZAR

UND. CANT. P.U. PARCIAL METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO %

5.02.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 24,329.80 1.93 46,956.51 3,906.80 7,540.12 16.06 8,943.60 17,261.15 36.76 12,850.40 24,801.27 52.82 11,479.40 22,155.24 47.18

D > 1KM

Page 3: 03.01 Obras de Arte Badén Navan

MINISTERIO DE TRANSPORTES Y COMUNICACIONES

Proyecto Especial de Infraestructura de Transporte Rural

PROVIAS RURAL

VALORIZACION DE OBRA Nº 03DEPARTAMENTO HUANCAVELICA

CONTRATISTA : C & C CONSULTORES EJECUTORES CONTRATISTAS GENERALES SRL N° DE CONTRATO : 909-2004-MTC/21

SUPERVISOR EXTERNO : Ing. JUAN A. MEDINA CORTEGANA FECHA : 5-Dec-04

MONTO DEL CONTRATO : 1,088,667.53 (CON IGV) S/. 914,846.66 (SIN IGV) PROVINCIA : CHURCAMPA

MONTO DEL ADELANTO : 217,733.51 (CON IGV) S/. 184,519.92 (SIN IGV) DISTRITO : CHURCAMPA

REHABILITACION DEL CAMINO VECITRAMO : QUINUAPATA-CCOTCCOY-PACCAY-MARAYPATA-ACCO-ALTARPATA-HUANCAVELICA

META FISICA: 25+430 Km.

ITEM DESCRIPCION PRESUPUESTO CONTRACTUAL AVANCE ACTUAL AVANCE ACUMUL. ANT. AVANCE ACUMUL. ACTUAL SALDO POR VALORIZAR

UND. CANT. P.U. PARCIAL METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO %

6.00.00 SEÑALIZACION

6.01.00 SEÑALES PREVENTIVAS UND 14.00 235.23 3,293.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.00 3,293.22 100.00

6.02.00 SEÑALES INFORMATIVAS UND 10.00 508.87 5,088.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 5,088.70 100.00

6.03.00 POSTES KILOMETRICOS UND 23.00 95.63 2,199.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.00 2,199.49 100.00

7.00.00 MEDIO AMBIENTE

7.01.00 ACONDICIONAMIENTOS DE BOTADEROS M3 11,890.33 3.65 43,399.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11,890.33 43,399.70 100.00

7.02.00 RESTAURACION EN AREAS DE CAMPAMENTO Y PATIO M2 450.00 1.73 778.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 450.00 778.50 100.00

DE MAQUINAS

7.03.00 RESTAURACION DE AREAS AFECTADAS HA 3.00 3,503.89 10,511.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 10,511.67 100.00

7.04.00 REVEGETACION DE AREAS CRITICAS HA 1.64 12,082.41 19,815.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.64 19,815.15 100.00

###

COSTO DIRECTO S/. 816,827.37 144,298.74 305,176.45 449,475.18 367,352.19

GASTOS GENERALES

GASTOS VARIABLES 5.00%) 5.00% S/. 40,841.37 7,214.94 15,258.82 22,473.76 18,367.61

GASTOS FIJOS 2,00% 2.00% S/. 16,336.55 2,885.97 6,103.53 8,989.50 7,347.04

UTILIDADES 5,00% 5.00% S/. 40,841.37 7,214.94 15,258.82 22,473.76 18,367.61

SUB-TOTAL S/. 914,846.66 161,614.59 341,797.62 503,412.20 411,434.45

IGV (19%) 19% S/. 173,820.87 30,706.77 64,941.55 95,648.32 78,172.55

TOTAL PRESUPUESTO S/. 1,088,667.53 192,321.36 406,739.17 599,060.52 489,607.00

% Avance Mensual 17.67% Acum. Ant. 37.36% Acum. Act. 55.03% % Saldo por Valoriz. 44.97%

Aprobaciones:

SUPERVISOR EXTERNO SUPERVISOR DE PLANTA JEFE UNIDAD ZONAL

UNIDAD ZONAL

Page 4: 03.01 Obras de Arte Badén Navan

MINISTERIO DE TRANSPORTES Y COMUNICACIONES

Proyecto Especial de Infraestructura de Transporte Rural

PROVIAS RURAL

VALORIZACION DE OBRA Nº 02DEPARTAMENTO HUANCAVELICA

CONTRATISTA : C & C CONSULTORES EJECUTORES CONTRATISTAS GENERALES SRL N° DE CONTRATO : 909-2004-MTC/21

SUPERVISOR EXTERNO : Ing. JUAN A. MEDINA CORTEGANA FECHA : 15-Mar-05

MONTO DEL CONTRATO : 1,088,667.53 (CON IGV) S/. 914,846.66 (SIN IGV) PROVINCIA : CHURCAMPA

MONTO DEL ADELANTO : 217,733.51 (CON IGV) S/. 184,519.92 (SIN IGV) DISTRITO : CHURCAMPA

REHABILITACION DEL CAMINO VECINAL : TRAMO : QUINUAPATA-CCOTCCOY-PACCAY-MARAYPATA-ACCO-ALTARPATA-HUANCAVELICA

META FISICA: 25+430 Km.

ITEM DESCRIPCION PRESUPUESTO CONTRACTUAL AVANCE ACTUAL AVANCE ACUMUL. ANT. AVANCE ACUMUL. ACTUAL SALDO POR VALORIZAR

UND. CANT. P.U. PARCIAL METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO %

1.00.00 OBRAS PRELIMINARES 2.87%

1.01.00 CAMPAMENTO UND 1.00 6,000.00 6,000.00 0.00 0.00 0.00 0.80 4,800.00 80.00 0.80 4,800.00 80.00 0.20 1,200.00 20.00

1.02.00 CARTEL DE OBRA UND 2.00 1,658.74 3,317.48 0.00 0.00 0.00 2.00 3,317.48 100.00 2.00 3,317.48 100.00 0.00 0.00 0.00

1.03.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO MECANICO GLB 1.00 8,000.00 8,000.00 0.00 0.00 0.00 0.50 4,000.00 50.00 0.50 4,000.00 50.00 0.50 4,000.00 50.00

1.04.00 TRAZO Y REPLANTEO KM 25.43 240.97 6,127.87 0.00 0.00 0.00 17.14 4,130.95 67.41 17.14 4,130.95 67.41 8.29 1,996.92 32.59

2.00.00 MOVIMIENTO DE TIERRAS 17.30%

2.01.00 EXCAVACION NO CLASIFICADA PARA EXPLANACIONES M3 28,326.64 2.21 62,601.87 6,815.19 15,061.57 24.06 17,218.80 38,053.55 60.79 24,033.99 53,115.12 84.85 4,292.65 9,486.75 15.15

2.02.00 CONFORMACION DE TERRAPLENES M3 13,606.13 4.02 54,696.64 617.93 2,484.08 4.54 4,645.45 18,674.70 34.14 5,263.38 21,158.78 38.68 8,342.75 33,537.86 61.32

2.03.00 ELIMINACION LATERAL DE EXCED.SIN TRANSPORTE M3 12,139.40 1.98 24,036.01 2,888.77 5,719.76 23.80 7,437.15 14,725.55 61.26 10,325.92 20,445.32 85.06 1,813.48 3,590.69 14.94

3.00.00 PAVIMENTOS 29.29%

3.01.00 MEJORAMIENTO DE LA SUBRASANTE (e= 0,20m) M2 6,027.00 5.36 32,304.72 0.00 0.00 0.00 2,439.50 13,075.72 40.48 2,439.50 13,075.72 40.48 3,587.50 19,229.00 59.52

3.02.00 PERFILADO Y COMPACTADO DE LA SUBRASANTE M2 45,538.85 1.07 48,726.57 4,561.25 4,880.54 10.02 19,741.50 21,123.41 43.35 24,302.75 26,003.94 53.37 21,236.10 22,722.63 46.63

EN ZONA DE CORTE

3.03.00 AFIRMADO (e=0.15m) M3 13,954.94 11.34 158,249.02 3,352.50 38,017.35 24.02 581.10 6,589.67 4.16 3,933.60 44,607.02 28.19 10,021.34 113,642.00 71.81

4.00.00 OBRAS DE ARTE 29.18%

4.01.00 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS M3 1,415.41 7.10 10,049.41 394.18 2,798.68 27.85 121.48 862.54 8.58 515.66 3,661.21 36.43 899.75 6,388.20 63.57

4.02.00 RELLENO ESTRUCTURAL M3 641.86 6.85 4,396.74 175.16 1,199.85 27.29 44.02 301.51 6.86 219.18 1,501.36 34.15 422.68 2,895.38 65.85

4.03.00 CONCRETO CICLOPEO F'C=140KG/CM2+30%PM M3 57.93 150.41 8,713.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.93 8,713.25 100.00

4.04.00 CONCRETO CICLOPEO F'C=175KG/CM2+30%PM M3 586.33 170.31 99,857.86 162.18 27,620.88 27.66 41.78 7,114.81 7.12 203.96 34,735.69 34.79 382.37 65,122.17 65.21

4.05.00 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS M2 1,463.38 16.17 23,662.85 362.09 5,855.00 24.74 123.24 1,992.73 8.42 485.33 7,847.72 33.16 978.05 15,815.13 66.84

4.06.00 ENCOFRADO PERDIDO DE ALCANTARILLAS M 288.90 56.78 16,403.74 113.00 6,416.14 39.11 28.28 1,605.74 9.79 141.28 8,021.88 48.90 147.62 8,381.86 51.10

4.07.00 EMBOQUILLADO DE PIEDRA M3 179.60 155.15 27,864.94 15.77 2,446.72 8.78 4.01 622.59 2.23 19.78 3,069.30 11.01 159.82 24,795.64 88.99

4.08.00 MURO DE MAMPOSTERIA DE PIEDRA M3 105.97 94.84 10,050.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 105.97 10,050.19 100.00

4.09.00 CONFORMACION DE CUNETAS EN MATERIAL M 20,770.00 1.80 37,386.00 3,900.00 7,020.00 18.78 9,790.00 17,622.00 47.14 13,690.00 24,642.00 65.91 7,080.00 12,744.00 34.09

NO CLASIFICADO

5.00.00 TRANSPORTES 10.93%

5.01.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 10,251.64 4.13 42,339.27 852.98 3,522.81 8.32 1,515.50 6,259.01 14.78 2,368.48 9,781.81 23.10 7,883.16 32,557.46 76.90

D <= 1KM

5.02.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 24,329.80 1.93 46,956.51 4,640.50 8,956.16 19.07 4,303.10 8,304.98 17.69 8,943.60 17,261.15 36.76 15,386.20 29,695.36 63.24

D > 1KM

Page 5: 03.01 Obras de Arte Badén Navan

MINISTERIO DE TRANSPORTES Y COMUNICACIONES

Proyecto Especial de Infraestructura de Transporte Rural

PROVIAS RURAL

VALORIZACION DE OBRA Nº 02DEPARTAMENTO HUANCAVELICA

CONTRATISTA : C & C CONSULTORES EJECUTORES CONTRATISTAS GENERALES SRL N° DE CONTRATO : 909-2004-MTC/21

SUPERVISOR EXTERNO : Ing. JUAN A. MEDINA CORTEGANA FECHA : 15-Mar-05

MONTO DEL CONTRATO : 1,088,667.53 (CON IGV) S/. 914,846.66 (SIN IGV) PROVINCIA : CHURCAMPA

MONTO DEL ADELANTO : 217,733.51 (CON IGV) S/. 184,519.92 (SIN IGV) DISTRITO : CHURCAMPA

REHABILITACION DEL CAMINO VECINAL : TRAMO : QUINUAPATA-CCOTCCOY-PACCAY-MARAYPATA-ACCO-ALTARPATA-HUANCAVELICA

META FISICA: 25+430 Km.

6.00.00 SEÑALIZACION 1.30%

6.01.00 SEÑALES PREVENTIVAS UND 14.00 235.23 3,293.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.00 3,293.22 100.00

6.02.00 SEÑALES INFORMATIVAS UND 10.00 508.87 5,088.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.00 5,088.70 100.00

6.03.00 POSTES KILOMETRICOS UND 23.00 95.63 2,199.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.00 2,199.49 100.00

7.00.00 MEDIO AMBIENTE 9.12%

7.01.00 ACONDICIONAMIENTOS DE BOTADEROS M3 11,890.33 3.65 43,399.70 7,417.89 27,075.31 62.39 7,417.89 27,075.31 62.39 14,835.78 54,150.61 124.77 -2,945.45 -10,750.91 -24.77

7.02.00 RESTAURACION EN AREAS DE CAMPAMENTO Y PATIO M2 450.00 1.73 778.50 450.00 778.50 100.00 450.00 778.50 100.00 900.00 1,557.00 200.00 -450.00 -778.50 -100.00

DE MAQUINAS

7.03.00 RESTAURACION DE AREAS AFECTADAS HA 3.00 3,503.89 10,511.67 3.00 10,511.67 100.00 3.00 10,511.67 100.00 6.00 21,023.34 200.00 -3.00 -10,511.67 -100.00

7.04.00 REVEGETACION DE AREAS CRITICAS HA 1.64 12,082.41 19,815.15 1.64 19,778.91 99.82 1.64 19,778.91 99.82 3.27 39,557.81 199.63 -1.63 -19,742.66 -99.63

COSTO DIRECTO S/. 816,827.37 190,143.90 231,321.32 421,465.21 395,362.16

GASTOS GENERALES

GASTOS VARIABLES 5.00%) 5.00% S/. 40,841.37 9,507.20 11,566.07 21,073.26 19,768.11

GASTOS FIJOS 2,00% 2.00% S/. 16,336.55 3,802.88 4,626.43 8,429.30 7,907.24

UTILIDADES 5,00% 5.00% S/. 40,841.37 9,507.20 11,566.07 21,073.26 19,768.11

SUB-TOTAL S/. 914,846.66 212,961.18 259,079.89 472,041.03 442,805.62

IGV (19%) 19% S/. 173,820.87 40,462.63 49,225.18 89,687.80 84,133.07

TOTAL PRESUPUESTO S/. 1,088,667.53 253,423.81 308,305.07 561,728.83 526,938.69

% Avance Mensual 23.28% Acum. Ant. 28.32% Acum. Act. 51.60% % Saldo por Valoriz. 48.40%

Aprobaciones:

SUPERVISOR EXTERNO SUPERVISOR DE PLANTA JEFE UNIDAD ZONAL

UNIDAD ZONAL

Page 6: 03.01 Obras de Arte Badén Navan

CUADRO DE AVANCESDEPARTAMENTO HUANCAVELICA

SUPERVISOR : Ing. JUAN A. MEDINA CORTEGANACAMINO RURAL TRAMO: QUINUAPATA-CCOTCCOY-PACCAY-

MARAYPATA-ACCO-ALTARPATA

Partida Descripción Uni. Metrado Metrado Metrado Metrado Porcentaje PorcentajeContratado Anterior Actual acumulado avanzado por ejecutar

1.00.00 OBRAS PRELIMINARES1.01.00 CAMPAMENTO Y OFICINA PROVISIONAL DE OBRA UND 1.00 0.80 0.00 0.80 80.00% 20.00%1.02.00 CARTEL DE IDENTIFICACION DE OBRA UND 2.00 2.00 0.00 2.00 100.00% 0.00%1.03.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 0.50 0.00 0.50 50.00% 50.00%1.04.00 TRAZO Y REPLANTEO KM 25.43 17.14 0.00 17.14 67.41% 32.59%

2.00.00 MOVIMIENTO DE TIERRAS2.01.00 EXCAVACION NO CLASIFICADA PARA EXPLANACIONES M3 28,326.64 17,218.80 6,815.19 24,033.99 84.85% 15.15%2.02.00 CONFORMACION DE TERRAPLENES M3 13,606.13 4,645.45 617.93 5,263.38 38.68% 61.32%2.03.00 ELIMINACION LATERAL DE EXCED.SIN TRANSPORTE M3 12,139.40 7,437.15 2,888.77 10,325.92 85.06% 14.94%

3.00.00 PAVIMENTOS3.01.00 MEJORAMIENTO DE LA SUBRASANTE (e= 0,20m) M2 6,027.00 2,439.50 0.00 2,439.50 40.48% 59.52%3.02.00 PERFILADO Y COMPACTADO DE LA SUBRASANTE M2 45,538.85 19,741.50 4,561.25 24,302.75 53.37% 46.63%

EN ZONA DE CORTE3.03.00 AFIRMADO (e=0.15m) M3 13,954.94 581.10 3,352.50 3,933.60 28.19% 71.81%

4.00.00 OBRAS DE ARTE4.01.00 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS M3 1,415.41 121.48 362.23 483.71 34.17% 65.83%4.02.00 RELLENO ESTRUCTURAL M3 641.86 44.02 161.00 205.02 31.94% 68.06%4.03.00 CONCRETO CICLOPEO F'C=140KG/CM2+30%PM M3 57.93 0.00 0.00 0.00 0.00% 100.00%4.04.00 CONCRETO CICLOPEO F'C=175KG/CM2+30%PM M3 586.33 41.78 151.77 193.55 33.01% 66.99%4.05.00 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS M2 1,463.38 123.24 340.49 463.73 31.69% 68.31%4.06.00 ENCOFRADO PERDIDO DE ALCANTARILLAS M 288.90 28.28 104.00 132.28 45.79% 54.21%4.07.00 EMBOQUILLADO DE PIEDRA M3 179.60 4.01 15.77 19.78 11.01% 88.99%4.08.00 MURO DE MAMPOSTERIA DE PIEDRA M3 105.97 0.00 0.00 0.00 0.00% 100.00%4.09.00 CONFORMACION DE CUNETAS EN MATERIAL M 20,770.00 9,790.00 3,900.00 13,690.00 65.91% 34.09%

NO CLASIFICADO

5.00.00 TRANSPORTES5.01.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 10,251.64 1,515.50 852.98 2,368.48 23.10% 76.90%

D <= 1KM5.02.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 24,329.80 4,303.10 4,640.50 8,943.60 36.76% 63.24%

D > 1KM

6.00.00 SEÑALIZACION6.01.00 SEÑALES PREVENTIVAS UND 14.00 0.00 0.00 0.00 0.00% 100.00%6.02.00 SEÑALES INFORMATIVAS UND 10.00 0.00 0.00 0.00 0.00% 100.00%6.03.00 POSTES KILOMETRICOS UND 23.00 0.00 0.00 0.00 0.00% 100.00%

7.00.00 MEDIO AMBIENTE7.01.00 ACONDICIONAMIENTOS DE BOTADEROS M3 11,890.33 7,417.89 7,417.89 14,835.78 124.77% -24.77%7.02.00 RESTAURACION EN AREAS DE CAMPAMENTO Y PATIO M2 450.00 450.00 450.00 900.00 200.00% -100.00%

DE MAQUINAS7.03.00 RESTAURACION DE AREAS AFECTADAS HA 3.00 3.00 3.00 6.00 200.00% -100.00%7.04.00 REVEGETACION DE AREAS CRITICAS HA 1.64 1.64 1.64 3.27 199.63% -99.63%

Page 7: 03.01 Obras de Arte Badén Navan

RESUMEN DE METRADOSDEPARTAMENTO HUANCAVELICA

SUPERVISOR : Ing. JUAN A. MEDINA CORTEGANACAMINO RURAL TRAMO: QUINUAPATA-CCOTCCOY-PACCAY-MARAYPATA-ACCO-ALTARPATA

Partida Descripción Uni. Metrado Metrado Metrado Metrado % %Contrat. Acum. Anter. Actual Acumulado Acum. x Ejecut.

1.00.00 OBRAS PRELIMINARES1.01.00 CAMPAMENTO Y OFICINA PROVISIONAL DE OBRA UND 1.00 0.80 0.00 0.80 80.00% 20.00%1.02.00 CARTEL DE IDENTIFICACION DE OBRA UND 2.00 2.00 0.00 2.00 100.00% 0.00%1.03.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 0.50 0.00 0.50 50.00% 50.00%1.04.00 TRAZO Y REPLANTEO KM 25.43 17.14 0.00 17.14 67.40% 32.60%

2.00.00 MOVIMIENTO DE TIERRAS2.01.00 EXCAVACION NO CLASIFICADA PARA EXPLANACIONES M3 28,326.64 24,033.99 695.88 24,729.87 87.30% 12.70%2.02.00 CONFORMACION DE TERRAPLENES M3 13,606.13 5,263.38 6,995.66 12,259.04 90.10% 9.90%2.03.00 ELIMINACION LATERAL DE EXCED.SIN TRANSPORTE M3 12,139.40 10,325.92 53.74 10,379.66 85.50% 14.50%

3.00.00 PAVIMENTOS3.01.00 MEJORAMIENTO DE LA SUBRASANTE (e= 0,20m) M2 6,027.00 2,439.50 0.00 2,439.50 40.48% 59.52%3.02.00 PERFILADO Y COMPACTADO DE LA SUBRASANTE M2 45,538.85 24,302.75 17,296.00 41,598.75 91.35% 8.65%

EN ZONA DE CORTE3.03.00 AFIRMADO (e=0.15m) M3 13,954.94 3,933.60 3,938.63 7,872.23 56.41% 43.59%

4.00.00 OBRAS DE ARTE4.01.00 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS M3 1,415.41 515.66 284.00 799.66 56.50% 43.50%4.02.00 RELLENO ESTRUCTURAL M3 641.86 219.18 123.40 342.58 53.37% 46.63%4.03.00 CONCRETO CICLOPEO F'C=140KG/CM2+30%PM M3 57.93 0.00 0.00 0.00 0.00% 100.00%4.04.00 CONCRETO CICLOPEO F'C=175KG/CM2+30%PM M3 586.33 203.96 126.75 330.71 56.40% 43.60%4.05.00 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS M2 1,463.38 485.33 287.71 773.04 52.83% 47.17%4.06.00 ENCOFRADO PERDIDO DE ALCANTARILLAS M 288.90 141.28 81.77 223.05 77.21% 22.79%4.07.00 EMBOQUILLADO DE PIEDRA M3 179.60 19.78 9.17 28.95 16.12% 83.88%4.08.00 MURO DE MAMPOSTERIA DE PIEDRA M3 105.97 0.00 0.00 0.00 0.00% 100.00%4.09.00 CONFORMACION DE CUNETAS EN MATERIAL M 20,770.00 13,690.00 820.00 14,510.00 69.86% 30.14%

NO CLASIFICADO

5.00.00 TRANSPORTES5.01.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 10,251.64 2,368.48 1,738.16 4,106.64 40.06% 59.94%

D <= 1KM5.02.00 TRANSPORTE MATERIAL EXCEDENTE PARA DISTANCIAS M3K 24,329.80 8,943.60 3,906.80 12,850.40 52.82% 47.18%

D > 1KM

6.00.00 SEÑALIZACION6.01.00 SEÑALES PREVENTIVAS UND 14.00 0.00 0.00 0.00 0.00% 100.00%6.02.00 SEÑALES INFORMATIVAS UND 10.00 0.00 0.00 0.00 0.00% 100.00%6.03.00 POSTES KILOMETRICOS UND 23.00 0.00 0.00 0.00 0.00% 100.00%

7.00.00 MEDIO AMBIENTE7.01.00 ACONDICIONAMIENTOS DE BOTADEROS M3 11,890.33 7,417.89 7,417.89 14,835.78 124.77% -24.77%7.02.00 RESTAURACION EN AREAS DE CAMPAMENTO Y PATIO M2 450.00 450.00 450.00 900.00 200.00% -100.00%

DE MAQUINAS7.03.00 RESTAURACION DE AREAS AFECTADAS HA 3.00 3.00 3.00 6.00 200.00% -100.00%7.04.00 REVEGETACION DE AREAS CRITICAS HA 1.64 1.64 1.64 3.27 199.63% -99.63%

Page 8: 03.01 Obras de Arte Badén Navan

_____________________________________________________________VOL. 03 - METRADOS

PARTIDA 03.00 OBRAS COMPLEMENTARIAS

RESUMEN - BADENES

Item Partida Descripción Unidad Metrado

1 03.01.01 Excavación no Clasificada en Badenes m3 126.23

2 03.01.02 Relleno Compactado con Material Propio m3 45.00

3 03.01.03 Encofrado y Desencofrado para Estructuras m2 47.40

4 03.01.04 Concreto f´c = 175 kg/cm2 + 30% de P.G. m3 54.08

5 03.01.05 Emboquillado de Piedra e = 0.30 m m2 60.00

Page 9: 03.01 Obras de Arte Badén Navan

_______________________________________________________________________________________VOL.03 - METRADOS

PARTIDA 03.00 OBRAS DE ARTE Y DRENAJE

PARTIDA: 03.01.01 EXCAVACION NO CLASIFICADA EN BADENES

N° Tipo Descripcion

Dimensiones

Largo Ancho Alto

(Und) (m) (m) (m) (m3) (m3)

1 Típico

Losa 3 10.00 5.00 0.50 75.00

126.23

Uñas 6 5.00 0.55 0.55 9.08

Uñas 6 10.00 0.55 0.55 18.15

Emboquillado Ingreso 3 10.00 2.00 0.20 12.00

Emboquillado salida 3 10.00 2.00 0.20 12.00

TOTAL 126.23

Volumen Parcial

Volumen TotalN° de

Veces

Page 10: 03.01 Obras de Arte Badén Navan

________________________________________________________________________________________VOL. 03 - METRADOS

PARTIDA 03.00 OBRAS DE ARTE Y DRENAJE

PARTIDA: 03.01.02 RELLENO COMPACTADO CON MATERIAL PROPIO

N° Tipo Descripcion

Dimensiones

Largo Ancho Alto

(Und) (m) (m) (m) (m3) (m3)

1 Típico Losa 3 10.00 5.00 0.30 45.00 45.00

TOTAL 45.00

Volumen Parcial

Volumen TotalN° de

Veces

Page 11: 03.01 Obras de Arte Badén Navan

________________________________________________________________________________________VOL. 03 - METRADOS

PARTIDA 03.00 OBRAS DE ARTE Y DRENAJE

PARTIDA: 03.01.03 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS

N° Tipo Descripcion

DimensionesArea Parcial Area Total

Largo Alto

(Und) (m) (m) (m2) (m2)

1 Típico

Losa 6 10.00 0.30 18.00

47.40Losa 6 5.00 0.30 9.00

Emboquillado in 6 8.50 0.20 10.20

Emboquillado sal 6 8.50 0.20 10.20

TOTAL 47.40

N° de Veces

Page 12: 03.01 Obras de Arte Badén Navan

______________________________________________________________________________________VOL. 03 - METRADOS

PARTIDA 03.00 OBRAS DE ARTE Y DRENAJE

PARTIDA: 03.01.04 CONCRETO CICLOPEO F´C=175 KG/CM2 + 30% P.G.

N° Tipo Descripcion

Dimensiones

Largo Ancho Alto

(Und) (m) (m) (m) (m3) (m3)

1 Típico

Losa 3 10.00 5.00 0.30 45.00

54.08Uñas 3 5.00 0.55 0.55 4.54

Uñas 3 5.00 0.55 0.55 4.54

TOTAL 54.08

Volumen Parcial

Volumen TotalN° de

Veces

Page 13: 03.01 Obras de Arte Badén Navan

_______________________________________________________________________________________VOL. 03 - METRADOS

PARTIDA 03.00 OBRAS DE ARTE Y DRENAJE

PARTIDA: 03.01.05 EMBOQUILLADO DE PIEDRA E=0.30 M.

N° Tipo Descripcion

DimensionesArea Total

Largo Ancho

(Und) (m) (m) (m2) (m2)

1 TípicoEmboquillado ingreso 3 5.00 2.00 30.00

60.00Emboquillado salida 3 5.00 2.00 30.00

TOTAL 60.00

Area ParcialN° de

Veces