 PRESUPUESTO ESTIMADO CUBIERTA DE TECHO ALMACEN, CON ASBESTO SABANA DE LA MAR, PROV. SAMANA; REPUBLICA DOMINICANA COD PARTIDAS CANT. UNID P.U SUBTOTAL  1.0 TRABAJOS PRELIMINARES 1.1 LIMPIEZA Y ACONDICIONAMIENTO DEL AREA (120' X 40') 5011.96 P2 8.55 42,852.26 1.2 DESMONTE DE RESTO DE TECHO EXISTENTE (INSERVIBLE) (20' X 40') 5011.96 P2 22.43 112,418.26 155,270.52 2.0 CARPINTERIA 2.1 BASES PARA COLUMNAS DE SOPORTE DE PINO TRATADO (6" X 6" X 10' ) 7.00 UNID 754.28 5,279.96 2.2  TIJERILLA DE MADERA SOPORTE EN COLUMNA 6" X 6" (PINO TRATADO) 307.43 PL 327.18 100,584.95 2.3  TIJERILLA DE MADERA (PINO TRATADO) 438.86 PL 212.03 93,051.49 2.4 CARGADERAS DE MADERA 2" X 4" X 10' 1377.54 PL 54.49 75,062.15 2.5 CANALETAS DE DESAGUE LATERALES DE TECHO 100.76 ML 695.45 70,073.54 2.6 CABALLETE DE FIBRO CEMENTO (SOBRE LIMA TESA) 125.23 PL 103.75 12,992.61 2.7 PINTURA DE MANTENIMIENTO EN MADERA TRATADA 822.00 PL 45.72 37,581.84 2.8 SALIDAS ELECTRICAS DE TECHO (INCLUYE MANO DE OBRA) 1.00 P.A 45,750.00 45,750.00 440,376.54 3.0 COLOCACION DE TECHO 3.1 CUBIERTA DE TECHO EN ALUZINC NATURAL CAL. 26 5011.96 P2 72.56 363,667.82 NOTA: NO SE COTIZA ASBESTO DEBIDO A QUE EL USO DEL MISMO ESTA DESCONTINUADO 363,667.82 SUB-TOTAL GENERAL RD$959,314.88 GASTOS INDIRECTOS A).- RESPONSABILIDAD TÉCNICA 10.00% 95,931.49 B).- GASTOS ADMINISTRATIVOS 3.00% 28,779.45 C).- SEGUROS Y FIANZAS 2.50% 23,982.87 D).-TRANSPORTE 1.75% 16,788.01 E)._ITBIS 1.80% 17,267.67 G)._ FONDO DE PENSIONES DE LOS OBREROS DE LA CONSTRUCCION 1.00% 9,593.15 H)._ CODIA 0.10%   SUB-TOTAL GASTOS INDIRECTOS 193,301.95 TOTAL GENERAL…  RD$1,152,616.83

Upload: manonmarianomaria

Post on 07-Oct-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

  • PRESUPUESTO ESTIMADO CUBIERTA DE TECHO ALMACEN, CON ASBESTO

    SABANA DE LA MAR, PROV. SAMANA; REPUBLICA DOMINICANACOD PARTIDAS CANT. UNID P.U SUBTOTAL

    1.0 TRABAJOS PRELIMINARES

    1.1 LIMPIEZA Y ACONDICIONAMIENTO DEL AREA (120' X 40') 5011.96 P2 8.55 42,852.26

    1.2 DESMONTE DE RESTO DE TECHO EXISTENTE (INSERVIBLE) (20' X 40') 5011.96 P2 22.43 112,418.26

    155,270.52

    2.0 CARPINTERIA

    2.1 BASES PARA COLUMNAS DE SOPORTE DE PINO TRATADO (6" X 6" X 10' ) 7.00 UNID 754.28 5,279.96

    2.2 TIJERILLA DE MADERA SOPORTE EN COLUMNA 6" X 6" (PINO TRATADO) 307.43 PL 327.18 100,584.95

    2.3 TIJERILLA DE MADERA (PINO TRATADO) 438.86 PL 212.03 93,051.49

    2.4 CARGADERAS DE MADERA 2" X 4" X 10' 1377.54 PL 54.49 75,062.15

    2.5 CANALETAS DE DESAGUE LATERALES DE TECHO 100.76 ML 695.45 70,073.54

    2.6 CABALLETE DE FIBRO CEMENTO (SOBRE LIMA TESA) 125.23 PL 103.75 12,992.61

    2.7 PINTURA DE MANTENIMIENTO EN MADERA TRATADA 822.00 PL 45.72 37,581.84

    2.8 SALIDAS ELECTRICAS DE TECHO (INCLUYE MANO DE OBRA) 1.00 P.A 45,750.00 45,750.00

    440,376.54

    3.0 COLOCACION DE TECHO

    3.1 CUBIERTA DE TECHO EN ALUZINC NATURAL CAL. 26 5011.96 P2 72.56 363,667.82

    NOTA: NO SE COTIZA ASBESTO DEBIDO A QUE EL USO DEL MISMO ESTA DESCONTINUADO

    363,667.82

    SUB-TOTAL GENERAL RD$959,314.88

    GASTOS INDIRECTOS

    A).- RESPONSABILIDAD TCNICA 10.00% 95,931.49

    B).- GASTOS ADMINISTRATIVOS 3.00% 28,779.45

    C).- SEGUROS Y FIANZAS 2.50% 23,982.87

    D).-TRANSPORTE 1.75% 16,788.01

    E)._ITBIS 1.80% 17,267.67

    G)._ FONDO DE PENSIONES DE LOS OBREROS DE LA CONSTRUCCION 1.00% 9,593.15

    H)._ CODIA 0.10% 959.31

    SUB-TOTAL GASTOS INDIRECTOS 193,301.95

    TOTAL GENERAL RD$1,152,616.83

    Ing. Maria Isabel Manon M. Ing. Jose F. Vasquez T.

    Preparado por: Codia 18444