EVALUACION ECONOMICA Ite m Descripcion Unida d Metrad o P. Uni t. P. Parci al Totale s 01.00 .00 OBRAS PROVISIONALES 01.02 .00 INSTALACION PROVISIONAL DE DEPOSITO P/AGUA 2x1.5x1 MTS (SOGA) UND 1.00 298.8 0 298.80 298.80 02.00 .00 TRABAJOS PRELIMINARES 02.01 .00 LIMPIEZA DE TERRENO MANUAL M2 216.00 1.94 419.90 02.02 .00 TRAZO, NIVEL Y REPLANTEO M2 216.00 0.38 81.65 501.55 03.00 .00 MOVIMIENTO DE TIERRAS 03.01 .00 EXCAVACION DE ZANJAS M3 48.53 19.40 941.68 03.02 .00 NIVELACION INTERIOR Y APISONADO M2 213.59 1.29 274.89 03.03 .00 ELIMINACION MATERIAL EXCEDENTE HASTA 30.00 MT (A MANO USANDO CARRETILLA) M3 58.24 11.52 670.92 03.04 .00 RELLENO Y COMPACTACION EN VEREDAS CON HORMIGON M3 12.00 35.71 428.54 2,316.03 04.00 .00 CONCRETO SIMPLE 04.01 .00 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO- HORMIGON 30% PIEDRA M3 30.36 31.97 970.55 04.02 .00 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS M3 4.00 57.13 228.53 04.03 .00 ENCOFRADO Y DEDESENCOFRADO SOBRECIMIENTO HASTA 0.30 MT M2 46.92 13.32 624.97 04.04 .00 FALSO PISO DE 4" DE CONCRETO 1:8 M2 201.50 4.93 993.80 2,817.85 05.00 .00 CONCRETO ARMADO 05.01 .00 CONCRETO EN ZAPATAS F'C= 140 KG/CM2 M3 6.40 31.97 204.60 05.02 .00 ENCOFRADO Y DESENCOFRADO PARA ZAPATAS M2 25.60 22.53 576.69 05.03 .00 HABILITACION Y COLOCACION DE ACERO PARA ZAPATA KG 56.45 0.57 32.01 05.04 .00 CONCRETO EN COLUMNAS F'C=175 KG/CM2 M3 3.96 89.28 353.55

Upload: fornil

Post on 20-Dec-2015

23 views

Category:

Documents


0 download

DESCRIPTION

Principales partidas para la construccion de pozo de percolacion

TRANSCRIPT

Page 1: Presupuesto Pozo Percolacion

EVALUACION ECONOMICA

Item Descripcion  

Unidad

Metrado

P. Unit.

P. Parcial

Totales

01.00.00 OBRAS PROVISIONALES

01.02.00INSTALACION PROVISIONAL DE DEPOSITO P/AGUA 2x1.5x1 MTS (SOGA)

UND 1.00 298.80 298.80298.80

02.00.00 TRABAJOS PRELIMINARES

02.01.00 LIMPIEZA DE TERRENO MANUAL M2 216.00 1.94 419.90

02.02.00 TRAZO, NIVEL Y REPLANTEO M2 216.00 0.38 81.65 501.55

03.00.00 MOVIMIENTO DE TIERRAS

03.01.00 EXCAVACION DE ZANJAS M3 48.53 19.40 941.68

03.02.00 NIVELACION INTERIOR Y APISONADO M2 213.59 1.29 274.89

03.03.00

ELIMINACION MATERIAL EXCEDENTE HASTA 30.00 MT (A MANO USANDO CARRETILLA)

M3 58.24 11.52 670.92

03.04.00 RELLENO Y COMPACTACION EN VEREDAS CON HORMIGON M3 12.00 35.71 428.54 2,316.03

04.00.00 CONCRETO SIMPLE

04.01.00CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA

M3 30.36 31.97 970.55

04.02.00 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS M3 4.00 57.13 228.53

04.03.00

ENCOFRADO Y DEDESENCOFRADO SOBRECIMIENTO HASTA 0.30 MT

M2 46.92 13.32 624.97

04.04.00 FALSO PISO DE 4" DE CONCRETO 1:8 M2 201.50 4.93 993.80 2,817.85

05.00.00 CONCRETO ARMADO

05.01.00 CONCRETO EN ZAPATAS F'C= 140 KG/CM2 M3 6.40 31.97 204.60

05.02.00ENCOFRADO Y DESENCOFRADO PARA ZAPATAS

M2 25.60 22.53 576.69

05.03.00 HABILITACION Y COLOCACION DE ACERO PARA ZAPATA KG 56.45 0.57 32.01

05.04.00 CONCRETO EN COLUMNAS F'C=175 KG/CM2 M3 3.96 89.28 353.55

05.05.00ENCOFRADO Y DESENCOFRADO PARA COLUMNAS

M2 39.15 10.75 420.71

05.06.00 HABILITACION Y COLOCACION DE ACERO PARA COLUMNA KG 558.44 0.57 316.64

05.07.00 CONCRETO EN VIGAS F'C=175 KG/CM2 M3 2.89 31.97 92.39

05.08.00 ENCOFRADO Y DESENCOFRADO VIGA M2 37.05 8.06 298.77

05.09.00 HABILITACION Y COLOCACION DE ACERO PARA VIGAS KG 326.48 0.57 185.11

05.10.00 CONCRETO EN LOSAS COCINA F'C=175 KG/CM2 M3 0.50 52.25 26.12

05.11.00ENCOFRADO Y DESENCOFRADO PARA LOSAS COCINA

M2 5.00 16.33 81.63

05.12.00HABILITACION Y COLOCACION DE ACERO PARA LOSA DE COCINA

KG 51.73 0.57 29.332,617.55

07.00.00 ESTRUCTURAS DE MADERA Y COBERTURAS

07.01.00 VIGAS DE MADERA TORNILLO DE 4 x 8" P2 237.97 3.85 916.66

Page 2: Presupuesto Pozo Percolacion

07.02.00 CORREAS DE MADERA TORNILLO P2 1,263.00 1.10 1,386.77

07.03.00 COBERTURA C/PLANCHA CORRUG. ASB-CEMENTO 8P M2 253.97 3.32 843.43

07.04.00 CUMBRERA DE ETERNIT UND 30.70 3.99 122.40 3,269.26

08.00.00 MUROS Y TABIQUES

08.01.00 MURO LADRILLO K.K. CABEZA, H=4MTS MEZCLA 1:5 M2 56.49 17.08 964.96

08.02.00 MURO LADIRLLO K.K. SOGA, MEZCLA 1:5 M2 149.29 14.07 2,100.06 3,065.02

09.00.00 REVOQUES ENLUCIDOS Y MOLDURAS

09.01.00 TARRAJEO DEL TIPO RAYADO O PRIMARIO C/MORTERO 1:5 M2 49.40 7.97 393.47

09.02.00 REVOQUE ACABADO VIGA-COLUMNA C/MORT 1:5, E=2CM M2 102.00 14.94 1,523.88

09.03.00 REVOQ. Y ENLUC. DERRA. VANOS, E=1.5CM M 105.30 7.20 758.16 2,675.51

10.00.00 PISOS Y PAVIMENTOS

10.01.00 ACABADO DE PISO C/PASTA 1:2 E=1.5CM COLOR BRUNADO M2 201.50 7.70 1,552.36

10.02.00 SARDINEL DE 15x45 P/VEREDA M 14.00 3.85 53.93

10.03.00 VEREDA DE CONCRETO E=4" 1:10 (BRUÑA Y JUNTA) M2 12.00 10.94 131.33 1,737.62

11.00.00 ZOCALOS Y CONTRAZOCALOS

11.01.00 CONTRAZOCALO CEMENTO S/COLOREAR H = 30 CM M 57.50 6.34 364.32

11.02.00 ZOCALO DE MAYOLICA BLANCA DE 15 X 15 DE 1RA M2 47.40 26.95 1,277.24 1,641.56

14.00.00 VIDRIOS, CRISTALES Y SIMILARES

14.01.00 VIDRIO SEMIDOBLE P2 259.48 1.27 329.28 329.28

15.00.00 PINTURA

15.01.00 LATEX INTERIORES M2 280.78 2.63 737.89

15.02.00 PINTURA OLEO BRILLANTE P/MADERA O FIERRO M2 31.61 6.17 194.88

15.03.00 LATEX EXTERIORES M2 24.78 2.87 71.14

15.04.00 PINTURA ANTICORROSIVA M2 24.14 6.17 148.82 1,152.73

16.00.00 APARATOS Y ACCESORIOS SANITARIOS

16.04.00 COLOCACION DE APARATOS Y ACCESORIOS PZA 10.00 26.87 268.74 268.74

17.00.00 INSTALACIONES SANITARIAS

17.01.00 SALIDA DE DESAGUE PTO 13.00 30.82 400.61

17.02.00 RED DE DISTRIBUCION DE DESAGUE DE 2" PVC SAL M 15.00 4.40 66.02

17.03.00 RED DE DISTRIBUCION DE DESAGUE DE 4" PVC SAL M 14.00 4.40 61.61

17.04.00 CAJA DE REGISTRO 0.30 X 0.60 P/DESAGUE UND 1.00 15.41 15.41 543.65

18.00.00 SISTEMA DE AGUA FRIA

18.01.00 SALIDA DE AGUA FRIA PTO 10.00 14.94 149.40

18.02.00 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP M 11.00 6.17 67.82

18.03.00 RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP M 2.00 2.99 5.98

18.04.00 VALVULA CHECK (COMPUERTA) 1/2 PZA 3.00 16.99 50.98

18.05.00 VALVULA CHECK (COMPUERTA) 3/4 PZA 1.00 16.99 16.99

18.06.00RED AGUA POTABLE-CONEXION DE PRINCIP. AL MEDIDOR

UND 1.00 223.20 223.20514.37

Page 3: Presupuesto Pozo Percolacion

19.00.00 INSTALACIONES ELECTRICAS

19.01.00 INSTALAC. ELECT. SALIDA TECHO Y TIJERAL PTO 12.00 11.95 143.42

19.02.00 SALIDA PARA TOMACORRIENTE PTO 9.00 27.36 246.24

19.03.00 CAJA DE PASE Fo. Go. LIV 4" X 4" X 3" UND 3.00 38.52 115.56

19.04.00 TABLERO GENERAL SEGUN PLANO UND 1.00 460.80 460.80

19.05.00 LLAVE INTERRUPTOR DE CUCHILLA DE 2 X 15 AMP. UND 2.00 2.12 4.25

19.06.00 LLAVE INTERRUPTOR DE CUCHILLA DE 2 X 30 AMP. UND 1.00 0.05 0.05

19.07.00 FLUORESCENTE RECTO 1 X 40 W UND 12.00 14.94 179.28 1,149.60

20.00.00 POZO DE PERCOLACION

20.01.00 EXCAVACION DE ZANJAS M3 55.68 19.40 1,080.41

20.02.00CONCRETO EN VIGAS DE CIMENTACION F'C= 175 KG/CM2

M3 2.23 43.66 97.36

20.03.00ENCOFRADO Y DESENCOFRADO VIGA DE CIMENTACION

M2 4.44 19.96 88.63

20.04.00 HABILITACION Y COLOCACION DE ACERO KG 82.11 0.57 46.56

20.05.00 MURO LADRILLO K.K. CABEZA, H=4MTS MEZCLA 1:5 M2 16.26 17.08 277.75

20.06.00 CAJA DE REGISTRO 30x60cm C/T DE CONCRETO UND 1.11 15.41 17.10

20.07.00 ENCOFRADO Y DESENCOFRADO M2 3.78 21.76 82.26

20.08.00 HABILITACION Y COLOCACION DE ACERO KG 53.37 0.57 30.26

20.09.00 FILTRO DE GRAVA M3 7.76 0.86 6.70

20.10.00 TUBERIA DE DISTRIBUCION PVC-SAL 2" UND 3.00 11.16 33.48 1,760.51

TOTAL DEL PRESUPUESTO

26,659.63