    Strategy adopted for indigenous manufactureExpected date of award 01.01.2011

    Establish Commissioning date Done

    Contractual Deliveries Worked out

    Float Considered

    Transportation time Considered

    Experience of Similar organizations Considered

    Work out Ex Factory Delivery Worked out

  • 7/27/2019 Presentation 211010.ppt

    2/13

    Strategy adopted for indigenous manufacture

    Time schedule for factory built up 10/2012

    Factory operational 12/2012

    Time & sequence of operations Indicated

    Machine schedule Prepared

    Assembly schedule Prepared

    Critical activities Identified

    Mitigation plan Prepared

  • 7/27/2019 Presentation 211010.ppt

    3/13

    Time required for

    synchronization after receipt ofGen 10 Months

    LPT 18 Months

    IPT 14 Months

    HPT 12 Months

    Zero Date Assumed 1.1.2011

    Synchronization time 44 Months

    Synchronization time indicated by Experts, from

    the receipt of major Assemblies

  • 7/27/2019 Presentation 211010.ppt

    4/13

  • 7/27/2019 Presentation 211010.ppt

    5/13

    Set No. 1st 2nd 3rd 4th 5th

    Project NBN1 SP1 NBN2 SP2 NBN3

    Commissioning date Dec-14 Feb-15 Jun-15 Aug-15 Dec-15

    Box up Nov-13 Jan-14 May-14 Jul-14 Nov-14

    Supply at site Jul-13 Sep-13 Jan-14 Mar-14 Jul-14

    Considering float of 3mths. Apr-13 Jun-13 Oct-13 Dec-13 Apr-14

    Turbine -Transportation 2 mths

    Turbine -Ex Factory Feb-13 Apr-13 Aug-13 Oct-13 Feb-14

    HP (Dates indicated by Kamlesh) SEP 13 Nov 13 Mar 14

    IP (Dates indicated by Kamlesh) SEP 13 Nov 13 Mar 14

    LP (Dates indicated by Kamlesh) AUG 13 Oct 13 Feb 14

    Valves

    Pedestal

    Generator -Transportation 4 mths

    Generator -Ex Factory 12-Dec Feb-13 Jun-13 Aug-13 Dec-13

    Stator (Dates indicated by Kamlesh) SEP 13

    Rotor

    Ex Factory deliveries (Date wise) to meet Contractual

    requirements (Assuming NTP as 01.01.2011)

  • 7/27/2019 Presentation 211010.ppt

    6/13

    Set No. 1st 2nd 3rd 4th 5th

    Months

    from

    NTPProject NBN1 SP1 NBN2 SP2 NBN3

    commissioning/

    Synchronization

    Aug-14 Oct-14 Feb-15 May-15 Aug-15 44

    Box up

    Supply at site

    Considering float of 3months,

    Turbine -Transportation 2mths.

    HP Aug-13 Oct-13 Feb-14 Apr-14 Aug-14

    IP Jun-13 Aug-13 Dec-13 Feb-14 Jun-14

    LP Feb-13 Apr-13 Aug-13 Oct-13 Dec-13

    Ex works HP Jun-13 Aug-13 Dec-14 Feb-14 Jun-14 30

    Ex works IP Apr-13 Jun-13 Oct-13 Dec-13 Apr-14 28

    Ex works LP Dec-10 Feb-13 Jun-13 Aug-13 Oct-13 24Generator -Transportation 4

    mths.

    Stator Oct-13 Dec-13 Apr-14 Jun-14 Oct-14

    Rotor Oct-13 Dec-13 Apr-14 Jun-14 Oct-14

    Ex Works Jun-13 Aug-13 Dec-13 Feb-14 Jun-14 30

    Delivery Schedule suggested by Experts

  • 7/27/2019 Presentation 211010.ppt

    7/13

    OUTER CASING

    Get fully machined & hydraulically tested casings. Approved venders

    are available This has also been considered while planning facilities.

    INNER CASING

    Machine Inner casing in JV or Partially machined casing except final

    machining of blade plan Blades may be procured from machine supplier if required. Blading & post blading machining in JV

    ROTOR

    Procure forgings/welded Rotor from Birr

    Blades to be manufactured in JV/ procured from machine supplier, if

    required Blading & post blading machining in JV. Balancing Pit to be expedited /Balancing in Baroda Tunnel/ OR

    Import from BIRR

    ACTION PLAN FOR HP TURBINE

  • 7/27/2019 Presentation 211010.ppt

    8/13

    OUTER CASING

    Get fully machined & hydraulically tested casings. Approved vendors

    are available

    This has also been considered while planning facilities.INNER CASING

    MACHINE CASTINGS IN JV or procure Partially machined casing

    (except final machining of blade plan) Blades to be manufactured in JV or may be procured from machine

    supplier in case capacity is not sufficient Blading & post blading machining in JV

    ROTOR

    Procure forgings/welded Rotor from Birr

    Blades may be manufactured /procured from machine supplier, if

    required Blading & post blading machining in JV Balance in Balancing Pit to be expedited/ or utilize the facility at

    Baroda/ OR IMOPRT FROM BIRR

    ACTION PLAN FOR IP TURBINE

  • 7/27/2019 Presentation 211010.ppt

    9/13

    OUTER CASING

    Fabrication in JVB. In case required, suitable & qualified fabricatorsavailable in India. These can be suitably validated and trained.

    INNER CASINGCASTING from approved sourcesMachining in JVLast stage blades from Alstom. Other blades can be manufactured in

    JVBlading & post blading machining in JV

    ROTOR

    Welded Rotor from BirrFully machined in JVBalancing Pit to be expedited to meet the time lines for 3rd set

    ORFully machined & bladed & balanced rotor from Alstom

    ACTION PLAN FOR LP TURBINE

  • 7/27/2019 Presentation 211010.ppt

    10/13

    STATOR

    Wound Stator to be manufactured in India for 3rd set

    Other components such as end shields, terminal box etc. to be

    manufactured in JV or can be sourced from India

    Assembly & Testing in India

    Testing facilities to be expedited to meet the time lines for 3rd set

    ROTOR

    Forgings to be imported

    Facilities available for Turning & slot milling

    Rotor Coils from Birr Balancing pit to be expedited to meet the time lines for 3rd set

    OR

    In the mean time Import Complete Rotor duly balanced from

    Alstom Birr

    ACTION PLAN FOR GENERATOR

  • 7/27/2019 Presentation 211010.ppt

    11/13

    Civil works to be expedited

    Ordering of machine tools to be expedited

    Expedite factory build up

    Immediate decision for Balancing Tunnel

    LP Rotor & Generator Rotor from Alstom tillfacility for balancing is not visible.

    Finalization of design for Generator test stand

    CRITICAL ACTIVITIES

  • 7/27/2019 Presentation 211010.ppt

    12/13

    3rd , 4th and 5th set can be manufactured with

    following constraints:

    For HP Turbine and IP Turbine, balancing of Rotors is constraint

    in view of uncertainty of Balancing Tunnel. This can either be

    balanced in Baroda Pit or fully bladed and balanced Rotor may be

    imported from Alstom network.

    LP Rotor not possible to be manufactured in JV due to invisibility

    of Balancing Pit. It may be have to be sourced from Alstom

    Generator Rotor not possible to be manufactured in JV due toinvisibility of Balancing Pit. It may be have to be sourced from

    Alstom

    Finalization of design for Generator test stand. This is critical

    CONCLUSION

  • 7/27/2019 Presentation 211010.ppt

    13/13

    Mr. Swamy proposed to import 3rd and 4th

    Turbine from Alstom network :

    To keep provision of slots for expected orders from IPPs

    Alstom today is considering to provide slots for JV which may not

    be provided later

    Bharat Forge expressed that as order from IPP is not certain, lets

    not worry about the slots today and allocate the capacity to NTPC.

    Shall see how to manage when order from IPPs becomes visible.

    Mr Swamy had his own views and conveyed that management

    shall take suitable decision.

    CONCLUSION