pbl report-1

Upload: valentina-fernandez

Post on 09-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 PBL Report-1

    1/6

    Lugo 1

    INSTITUTO TECNOLGICO Y DE ESTUDIOS SUPERIORES DE MONTERREY

    CAMPUS SANTA FE

    PBL- Report

    Matemticas para ingeniera II Prof.Francisco Prez

    Biaani Cervantes Luna A01015566

    Tania Gonzlez Mata A01018297

    Diana Lugo Pin A01015694

    31 de enero de 2011

    PBL Reporte: Ttulo

    Abstract

    The purpose of this PBL is to evaluate the funcionality of different methods, and to

    evaluate which one of them is the best or has the major productivity in an industrial process. For

    this, we need to evaluate the function for each graphic and therefore obtain the integral to see if a

    process has more productivity than other, in this case, machine A and machine B have different

    cycles and conditions. Another aspect to consider is the way in which the graphics need to be

    ordered and maximize productivity and the method to obtain functions for both graphics.

    Introduction

    Parabola

    A parabola is the set of all points in the

    plane equidistant from a given line (the conic

    section directrix) and a given point not on the line

    (the focus). The focal parameter (i.e., the distance

    between the directrix and focus) is therefore given

    by , where is the distance from the vertex to

    the directrix or focus.

  • 8/7/2019 PBL Report-1

    2/6

    Lugo 2

    Integral

    An integral is a mathematical object that can be interpreted as an area or a generalization

    of area. Integrals, together with derivatives, are the fundamental objects of calculus.

    Problem definition

    The problem to be solved in this workshop consists on finding, first, the formula of a

    parabola given the plot, and second, the areas under the two curves (parabola, line) between

    specific intervals making use of integrals. That way, we will be able to find production rates and

    determine which one of the proposed methods is more effective, or in its case, find another

    method that results in a better production.

    Input data

    This graphic represents the behavior of

    the production vs. time, in the machine A. The

    machines production has a complete cycle of

    eight hours, in which production increases during

    the first four hours, the major production happens

    in the fourth hour, and during the last four hours

    it decreases. This machine can work eight hours

    but must rest two hours.

    This second graphic represents the

    behavior of production vs. time, in the

    machine B. The production is constant and

    it can continue working indefinitely.

    Also we know that in five days

    (120 hrs) the machine can work with three

    cycles:

    y Machine A (8hrs) and machine B

    (2hrs) with twelve repetitions in order to complete the five days.

    y Machine A (4hrs) and machine B (2hrs) with twenty repetitions in order to complete the

    five days.

  • 8/7/2019 PBL Report-1

    3/6

    Lugo 3

    y Machine A (6hrs) and machine B (2hrs) with fifteen repetitions in order to complete the

    five days.

    Assumptions

    We assumed that machine An in x=0 the production was 900 units, in x=4 the maxim

    production was 1900 units and in x=8 the production had turned back to 900 units. Also, we

    assumed that the function in the graphic corresponds with the parabola and it can be determined

    following the equation: .

    We assumed that the function of machine B corresponds to y=800

    Data Analysis

    Byusing the points in the graphic we can determine the equation ofthe parabola in the following way:

    As result we obtained the following equation:

    By plotting the equation, we realized that the equations are likely accurate.

    x y

    0 900

    4 1900

    8 900

  • 8/7/2019 PBL Report-1

    4/6

    Lugo 4

    In order to find the area under the curve for

    obtaining the production units, we have to integrate

    the equations.

    Then, we have to evaluate the functions according with the three cycles. Also, we can

    integrate them determining the range in the graphic.

    y Machine A (8hrs) and machine B (2hrs) with twelve repetitions in order to complete the

    five days.

    y Machine A (4hrs) and machine B (2hrs) with twenty repetitions in order to complete the

    five days.

    y Machine A (6hrs) and machine B (2hrs) with fifteen repetitions in order to complete the

    five days.

    After these procedures we searched others methods in order to achieve a major

    production. We found two different cycles which results in major productions:

  • 8/7/2019 PBL Report-1

    5/6

    Lugo 5

    y The first: we tried to found the cycle by random calculations taking into account that we

    needed to eliminate the decrease in the machine A and we have to obtain a great number

    of repetitions. So, we found this cycle:

    y The second: we realized that the functions intersect themselves in y=1600, in this way

    we can obtain a great production if we start the machine B when machine A decreases to

    y=1600 for avoiding the following decrease of it. By the plotting and by equation

    balancing, we can obtain the x value when y=1600.

    Results

    As we can observe, of the established cycles, the major production was reached by the

    last one, with 172500 units. Because the machine A was stopped before to decrease until

    y=1600. And the greatest cycle that we found was: machine A (7hrs) machine B (2hrs) which

    results in 173388.88 units.

    Conclussions

  • 8/7/2019 PBL Report-1

    6/6

    Lugo 6

    According to the results, we could determine the functions for the graphics assuming it

    was a polinomial funtcion of order 2, and see if the methods applied were lucrative and which

    one was the best, for this, using integrals was the best option to determine the area under the

    curve, to see it graphically and analitically, and comparing the results for each methos in units

    sqaured, at last, we used the hours as intervals for the integral and evaluate how much production

    was created after 120 hours in the cycle.

    Reference

    MathWorld. (2011). Mth. Disponible en: http://mathworld.wolfram.com/Integral.html

    MathWorld. (2011). Mth. Disponible en: http://mathworld.wolfram.com/Parabola.html