M E T R A D O METRADO DE ACERO AULAS ALUMNO : DEPARTAMENTO : AYACUCHO PROVINCIA : LA MAR DISTRITO : ANCO LUGAR : OSQOQOCHA ITEM DESCRIPCION CANT. Nº VECES LONG (ml)DIAM. P.U. (Kg/mlSUB TOTAL SUB TOTAL TOTAL UNIDAD 3/4" 5/8" 1/2" 3/8" 1/4" 03.01.04.ZAPATAS, ACERO FY=4200KG/CM2 891.47 Kg Z-1 4.00 15.00 1.68 5/8" 1.552 156.44 156.44 100.80 4.00 15.00 1.68 5/8" 1.552 156.44 156.44 100.80 Z-2 6.00 11.00 1.84 5/8" 1.552 188.47 188.47 121.44 6.00 14.00 1.84 5/8" 1.552 239.88 239.88 154.56 Z-3 4.00 11.00 1.10 5/8" 1.552 75.12 75.12 48.40 4.00 11.00 1.10 5/8" 1.552 75.12 75.12 48.40 Z-4 3.00 7.00 1.84 5/8" 1.552 59.97 59.97 38.64 3.00 7.00 1.84 5/8" 1.552 59.97 59.97 38.64 Z-5 1.00 9.00 1.10 5/8" 1.552 15.36 15.36 9.90 1.00 16.00 1.10 5/8" 1.552 27.32 27.32 17.60 3.01.04.0 VIGAS DE CIMENTACION, ACERO FY=4200KG/CM2 1156.27 Kg Eje 01 VC-01 9.00 6.00 3.50 3/4" 1.552 293.33 293.33 189.00 4.00 6.00 3.50 3/8" 0.993 83.41 83.41 84.00 ### 2.00 1.80 3/8" 0.559 56.35 56.35 100.80 Eje 02 VC-01 6.00 2.00 3.50 3/4" 1.552 65.18 65.18 42.00 4.00 2.00 3.50 3/8" 0.993 27.80 27.80 28.00 ### 2.00 1.80 3/8" 0.559 34.21 34.21 61.20 Eje A VC-01 6.00 2.00 3.35 3/4" 1.552 62.39 62.39 40.20 8.00 2.00 3.35 3/8" 0.993 53.22 53.22 53.60 ### 2.00 1.80 3/8" 0.559 46.29 46.29 82.80 Eje C, E VC-01 6.00 8.00 3.10 3/4" 1.552 230.94 230.94 4.00 8.00 3.10 3/8" 0.993 98.51 98.51 99.20 ### 8.00 1.80 3/8" 0.559 104.64 104.64 187.20

Upload: berly-tovar-vergara

Post on 04-Aug-2015

25 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: METRADOS CONSTRUCCIONES

M E T R A D OMETRADO DE ACERO AULAS

ALUMNO :DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEM DESCRIPCION CANT. Nº VECES LONG (ml) DIAM. P.U. (Kg/ml) SUB TOTAL SUB TOTAL TOTAL UNIDAD 3/4" 5/8" 1/2" 3/8" 1/4" Nº VARILLAS

03.01.04.02 ZAPATAS, ACERO FY=4200KG/CM2 891.47 Kg

Z-1 4.00 15.00 1.68 5/8" 1.552 156.44 156.44 100.80 11.20

4.00 15.00 1.68 5/8" 1.552 156.44 156.44 100.80 11.20

Z-2 6.00 11.00 1.84 5/8" 1.552 188.47 188.47 121.44 13.49

6.00 14.00 1.84 5/8" 1.552 239.88 239.88 154.56 17.17

Z-3 4.00 11.00 1.10 5/8" 1.552 75.12 75.12 48.40 5.38

4.00 11.00 1.10 5/8" 1.552 75.12 75.12 48.40 5.38

Z-4 3.00 7.00 1.84 5/8" 1.552 59.97 59.97 38.64 4.29

3.00 7.00 1.84 5/8" 1.552 59.97 59.97 38.64 4.29

Z-5 1.00 9.00 1.10 5/8" 1.552 15.36 15.36 9.90 1.10

1.00 16.00 1.10 5/8" 1.552 27.32 27.32 17.60 1.96

03.01.04.05 VIGAS DE CIMENTACION, ACERO FY=4200KG/CM2 1156.27 Kg

Eje 01 VC-01 9.00 6.00 3.50 3/4" 1.552 293.33 293.33 189.00 21.00

4.00 6.00 3.50 3/8" 0.993 83.41 83.41 84.00 9.33

28.00 2.00 1.80 3/8" 0.559 56.35 56.35 100.80 11.20

Eje 02 VC-01 6.00 2.00 3.50 3/4" 1.552 65.18 65.18 42.00 4.67

4.00 2.00 3.50 3/8" 0.993 27.80 27.80 28.00 3.11

17.00 2.00 1.80 3/8" 0.559 34.21 34.21 61.20 6.80

Eje A VC-01 6.00 2.00 3.35 3/4" 1.552 62.39 62.39 40.20 4.47

8.00 2.00 3.35 3/8" 0.993 53.22 53.22 53.60 5.96

23.00 2.00 1.80 3/8" 0.559 46.29 46.29 82.80 9.20

Eje C, E VC-01 6.00 8.00 3.10 3/4" 1.552 230.94 230.94 0.00

4.00 8.00 3.10 3/8" 0.993 98.51 98.51 99.20 11.02

13.00 8.00 1.80 3/8" 0.559 104.64 104.64 187.20 20.80

Page 2: METRADOS CONSTRUCCIONES

M E T R A D OMETRADO DE ACERO AULAS

ALUMNO :DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEM DESCRIPCION CANT. Nº VECES LONG (ml) DIAM. P.U. (Kg/ml) SUB TOTAL SUB TOTAL TOTAL UNIDAD 3/4" 5/8" 1/2" 3/8" 1/4" Nº VARILLAS

Eje G VC-01 12.00 8.00 3.10 3/4" 1.552 461.88 461.88 0.00

2.00 8.00 3.10 3/8" 0.993 49.25 49.25 49.60 5.51

13.00 8.00 1.80 3/8" 0.559 104.64 104.64 187.20 20.80

03.01.04.10 COLUMNAS, ACERO FY=4200KG/CM2 1032.47 Kg

Primer piso

P1 4.00 10.00 4.90 5/8" 1.552 304.19 304.19 196.00 21.78

4.00 6.00 4.90 1/2" 0.993 116.78 116.78 117.60 13.07

Estribos 4.00 27.00 2.10 3/8" 0.559 126.78 126.78 226.80 25.20

4.00 27.00 1.50 3/8" 0.559 90.56 90.56 162.00 18.00

Columna C1 6.00 8.00 2.20 5/8" 0.559 59.03 59.03 0.00

estribos 6.00 14.00 0.23 3/8" 0.250 4.83 4.83 19.32 2.15

Columna C3 2.00 4.00 1.86 5/8" 0.559 8.32 8.32 0.00

estribos 2.00 14.00 0.23 3/8" 0.250 1.61 1.61 6.44 0.72

Columna C5 24.00 6.00 3.98 3/8" 0.559 320.37 320.37 573.12 63.68

estribos 24.00 22.00 0.44 1/4" 0.250 58.08 58.08 232.32 25.81

03.01.04.16 VIGAS, ACERO FY=4200KG/CM2 2872.91 Kg

Primer Piso

Viga de Amarre Eje 1 3.00 2.00 1.64 3/8" 0.559 5.50 5.50 9.84 1.09

3.00 2.00 1.64 1/2" 0.993 9.77 9.77 9.84 1.09

estribos 3.00 32.00 0.44 1/4" 0.250 10.56 10.56 42.24 4.69

Page 3: METRADOS CONSTRUCCIONES

M E T R A D OMETRADO DE ACERO AULAS

ALUMNO :DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEM DESCRIPCION CANT. Nº VECES LONG (ml) DIAM. P.U. (Kg/ml) SUB TOTAL SUB TOTAL TOTAL UNIDAD 3/4" 5/8" 1/2" 3/8" 1/4" Nº VARILLAS

3.00 2.00 3.90 3/8" 0.559 13.08 13.08 23.40 2.60

3.00 2.00 3.90 1/2" 0.993 23.24 23.24 23.40 2.60

estribos 3.00 29.00 0.44 1/4" 0.250 9.57 9.57 38.28 4.25

viga de amarre eje 2 3.00 2.00 3.90 3/8" 0.559 13.08 13.08 23.40 2.60

3.00 2.00 3.90 1/2" 0.993 23.24 23.24 23.40 2.60

estribos 3.00 64.00 0.44 1/4" 0.250 21.12 21.12 84.48 9.39

3.00 2.00 3.90 3/8" 0.559 13.08 13.08 23.40 2.60

3.00 2.00 3.90 1/2" 0.993 23.24 23.24 23.40 2.60

estribos 3.00 62.00 0.44 1/4" 0.250 20.46 20.46 81.84 9.09

solera 2.00 4.00 3.50 1/2" 0.993 27.80 27.80 28.00 3.11

estribos 2.00 32.00 1.50 3/8" 0.559 53.66 53.66 96.00 10.67

V-1 (0.20X0.45) 3.00 1.00 13.00 1/2" 0.993 38.73 38.73 39.00 4.33

3.00 2.00 22.00 5/8" 1.552 204.86 204.86 132.00 14.67

3.00 3.00 20.00 5/8" 1.552 279.36 279.36 180.00 20.00

estribos 8.00 68.00 1.30 3/8" 0.559 395.32 395.32 707.20 78.58

V-2 (0.20X0.45) 9.00 4.00 3.30 5/8" 1.552 184.38 184.38 118.80 13.20

estribos 9.00 52.00 1.50 3/8" 0.559 392.42 392.42 702.00 78.00

V-3 (0.30X0.55) 6.00 2.00 9.00 1/2" 0.993 107.24 107.24 108.00 12.00

6.00 6.00 9.00 3/4" 2.235 724.14 724.14 324.00 36.00

estribos 6.00 52.00 1.60 3/8" 0.559 279.05 279.05 499.20 55.47

03.01.04.19LOSA ALIGERADA, ACERO FY=4200KG/CM2 1726.52 Kg

Primer pisoAcero positivo 27.00 1.00 22.56 1/2" 0.99 604.86 604.86 609.12 67.68

27.00 1.00 8.00 3/8" 0.56 120.74 120.74 216.00 24.00Acero negativo 27.00 1.00 12.44 1/2" 0.99 333.53 333.53 335.88 37.32

Page 4: METRADOS CONSTRUCCIONES

M E T R A D OMETRADO DE ACERO AULAS

ALUMNO :DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEM DESCRIPCION CANT. Nº VECES LONG (ml) DIAM. P.U. (Kg/ml) SUB TOTAL SUB TOTAL TOTAL UNIDAD 3/4" 5/8" 1/2" 3/8" 1/4" Nº VARILLAS

Acero negativo 6.00 1.00 12.44 1/2" 0.99 74.12 74.12 74.64 8.29

Acero positivo 6.00 1.00 22.25 1/2" 0.99 132.57 132.57 133.50 14.83

6.00 1.00 8.00 3/8" 0.56 26.83 26.83 48.00 5.33

Acero temperatura 78.00 1.00 22.25 1/4" 0.25 433.88 433.88 1735.50 192.83

7679.64 595.20 1305.98 1525.78 4269.72 2214.66 1101.26 No DE VARILLAS66.13 145.11 169.53 474.41 246.07 1101.26

Page 5: METRADOS CONSTRUCCIONES

PLANILLA DE METRADOS MODULO DE AULAS

PROYECTO :

DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEMS DESCRIPCIÓN UND N° VECES CANT LARGO ANCHO ALTURA PARCIAL TOTAL01 OBRAS PROVISIONALES

01.01 ALMACEN, OFICINA Y CASETA DE GUARDIANIA MES 3.001.00 3.00 3.00

01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M pza 1.001.00 1.00 1.00

01.03 SERVICIOS HIGIENICOS GLB 1.001.00 1.00 1.00

01.04 AGUA PARA LA CONSTRUCCION GLB 1.001.00 1.00 1.00

02 TRABAJOS PRELIMINARES

02.01 TRANSPORTE DE EQUIPO Y MAQUINARIA GLB 1.001.00 1.00 1.00

02.02 FLETE TERRESTRE TON 113.21INSUMOS A TRANSPORTAR 1.00 113.21 113.21

03 MODULO DE AULAS03.01 ESTRUCTURAS

03.01.01 TRABAJOS PRELIMINARES03.01.01.01 LIMPIEZA DE TERRENO MANUAL M2 220.05

LIMPIEZA PARA MODULO DE AULAS 1.00 1.00 21.68 10.15 220.05

03.01.01.02 TRAZO Y REPLANTEO PRELIMINAR M2 433.60LIMPIEZA PARA MODULO DE AULAS 1.00 1.00 20.00 21.68 433.60

03.01.02 MOVIMIENTO DE TIERRAS

03.01.02.01 NIVELACION DEL TERRENO M2 220.05Corte para Aulas 1.00 1.00 21.68 10.15 220.05

03.01.02.02 EXCAVACION DE ZANJAS Y ZAPATAS M3 104.77Eje A 1.00 1.00 4.40 0.60 1.20 3.17eje C 1.00 1.00 4.40 0.60 1.20 3.17eje E 1.00 1.00 4.40 0.60 1.20 3.17eje G 1.00 1.00 2.80 0.60 1.20 2.02eje 1 1.00 1.00 8.70 0.40 1.20 4.18eje 2 1.00 1.00 8.70 0.40 1.20 4.18Zapata Z1 4.00 1.00 1.80 1.80 1.40 18.14Zapata Z2 6.00 1.00 2.40 1.80 1.40 36.29Zapata Z3 4.00 1.00 1.80 1.80 1.40 18.14Zapata Z4 3.00 1.00 1.20 1.20 1.40 6.05Zapata Z5 1.00 1.00 2.80 1.60 1.40 6.27

03.01.02.03 RELLENO Y COMP. MANUAL- MAT. DE AFIRMADO M3 1.07Bajo el cimiento de eje A 1.00 1.00 9.70 0.22 0.25 0.53Bajo el cimiento de eje B 1.00 1.00 9.70 0.22 0.25 0.53

03.01.02.04 AFIRMADO DE 4" PARA PISOS INTERIORES Y EXTERIORES, COMPACTADO M2 239.43Aula 1 1.00 1.00 8.30 7.20 59.76Aula 2 1.00 1.00 8.30 7.20 59.76Dirección 1.00 1.00 8.30 7.20 59.76Veredas Aulas posterior 1.00 1.00 17.65 1.00 17.65Veredas Aulas anterior 1.00 1.00 19.00 1.50 28.50Veredas laterales 1.00 1.00 14.00 1.00 14.00

03.01.02.05 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. M3 406.03Producto de excavacion esponjamiento 25% 1.25 324.82 406.03

03.01.02.06 ESCARIFICADO Y COMPACTACION CON PLANCHA COMPACT. M2 239.43Aula 1 1.00 1.00 8.30 7.20 59.76Aula 2 1.00 1.00 8.30 7.20 59.76Direccion 1.00 1.00 8.30 7.20 59.76Veredas Aulas posterior 1.00 1.00 17.65 1.00 17.65Veredas Aulas anterior 1.00 1.00 19.00 1.50 28.50Veredas laterales 1.00 1.00 14.00 1.00 14.00

03.01.02.07 ELIMINACION DE MATERIAL EXCEDENTE M3 406.031.00 1 406.03 406.03

Page 6: METRADOS CONSTRUCCIONES

PLANILLA DE METRADOS MODULO DE AULAS

PROYECTO :

DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEMS DESCRIPCIÓN UND N° VECES CANT LARGO ANCHO ALTURA PARCIAL TOTAL03.01.03 CONCRETO SIMPLE

03.01.03.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA M3 7.24Eje A 1.00 1.00 6.70 0.60 0.60 2.41Eje C 1.00 1.00 6.70 0.60 0.60 2.41Eje E 1.00 1.00 6.70 0.60 0.60 2.41Eje G 1.00 1.00 6.70 0.60 0.60 2.41

03.01.03.02 SOBRECIMIENTO CONCRETO 1:8 + 25% P.M. M3 4.81Eje 1 1.00 1.00 12.66 0.24 0.45 1.37Eje 2 1.00 1.00 9.33 0.13 0.45 0.55Eje A 1.00 1.00 6.70 0.24 0.45 0.72Eje C 1.00 1.00 6.70 0.24 0.45 0.72Eje E 1.00 1.00 6.70 0.24 0.45 0.72Eje G 1.00 1.00 6.70 0.24 0.45 0.72

03.01.03.03 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO M2 55.97Eje 1 2.00 1.00 12.66 0.45 11.39Eje 2 2.00 1.00 9.33 0.45 8.40Eje A 2.00 3.00 6.70 0.45 18.09Eje C 2.00 1.00 6.70 0.45 6.03Eje E 2.00 1.00 6.70 0.45 6.03Eje G 2.00 1.00 6.70 0.45 6.03

03.01.03.04 FALSO PISO MEZCLA 1:8 e=4" M2 99.22Aula 1 1.00 1.00 6.92 7.20 49.82Aula 2 1.00 1.00 6.86 7.20 49.39Direccion 1.00 1.00 6.92 7.20 49.82

03.01.03.05 SOLADO PARA ZAPATAS DE 4" MEZCLA 1:12 CEMENTO-HORMIGON M2 51.84Zapata Z1 4.00 1.00 1.80 1.80 12.96Zapata Z2 6.00 1.00 2.40 1.80 25.92Zapata Z3 4.00 1.00 1.80 1.80 12.96Zapata Z4 3.00 1.00 1.20 1.20 4.32Zapata Z5 1.00 1.00 2.80 1.60 4.48

03.01.04 OBRAS DE CONCRETO ARMADO03.01.04.01 ZAPATAS CONCRETO F`C=210 kg/cm2 M3 31.10

Zapata Z1 4.00 1.00 1.80 1.80 0.60 7.78Zapata Z2 6.00 1.00 2.40 1.80 0.60 15.55Zapata Z3 4.00 1.00 1.80 1.80 0.60 7.78Zapata Z4 3.00 1.00 1.20 1.20 0.60 2.59Zapata Z5 1.00 1.00 2.80 1.60 0.60 2.69

03.01.04.02 ZAPATAS, ACERO FY=4200KG/CM2 KG 891.47

03.01.04.03 VIGAS DE CIMENTACION CONCRETO F`C=210 kg/cm2 M3 5.46Eje A - VC-01 1.00 1.00 11.40 0.22 0.60 1.50Eje C - VC -01 1.00 1.00 11.40 0.22 0.60 1.50Eje 1, 3, 5 , - VC-01 1.00 3.00 6.20 0.22 0.60 2.46

03.01.04.04 VIGAS DE CIMENTACION, ENCOFRADO Y DESENCOFRADO M2 49.68Eje A - VC-01 2.00 1.00 11.40 0.60 13.68Eje C - VC -01 2.00 1.00 11.40 0.60 13.68Eje 1, 3, 5 , - VC-01 2.00 3.00 6.20 0.60 22.32

03.01.04.05 VIGAS DE CIMENTACION, ACERO FY=4200KG/CM2 KG 1,156.27

03.01.04.06 COLUMNAS, CONCRETO 175 kg/cm2 (COLUMNETAS) M3 0.95Primer PisoColumna Pc elevacion frontal 1.00 6.00 0.13 0.12 1.40 0.13Columna Pb elevacion frontal 1.00 6.00 0.12 0.20 2.85 0.41Columna Pc elevacion posterior 1.00 8.00 0.13 0.12 1.10 0.14Columna Pb elevacion posterior 1.00 4.00 0.12 0.20 2.85 0.27

03.01.04.07 COLUMNAS, CONCRETO 210 kg/cm2, (1er. PISO) M3 12.37Primer PisoP1 1.00 4.00 0.80 0.20 4.40 2.82P2 1.00 3.00 0.80 0.22 4.40 2.32PLACA 1 1.00 6.00 1.37 0.20 4.40 7.23

03.01.04.08 COLUMNAS, ENCOFRADO DESENCOFRADO M2 160.90Primer PisoColumna Pc elevacion frontal 2.00 6.00 0.13 1.40 2.18Columna Pb elevacion frontal 2.00 6.00 0.20 2.85 6.84

Page 7: METRADOS CONSTRUCCIONES

PLANILLA DE METRADOS MODULO DE AULAS

PROYECTO :

DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEMS DESCRIPCIÓN UND N° VECES CANT LARGO ANCHO ALTURA PARCIAL TOTALColumna Pc elevacion posterior 2.00 8.00 0.13 1.10 2.29Columna Pb elevacion posterior 2.00 4.00 0.20 2.85 4.56P1 2.00 4.00 1.00 4.40 35.20P2 2.00 3.00 1.02 4.40 26.93PLACA 1 2.00 6.00 1.57 4.40 82.90

03.01.04.09 COLUMNAS, ACERO FY=4200KG/CM2 KG 1,032.47

03.01.04.10 VIGAS, CONCRETO 175 kg/cm2 (VIGUETAS AMARRE) M3 0.55Primer PisoViga de amarre Eje C frontal 1.00 2.00 2.15 0.10 0.12 0.05Viga de amarre Eje C frontal 1.00 2.00 1.10 0.10 0.12 0.03Viga de amarre Eje C - Va frontal 1.00 2.00 1.20 0.20 0.12 0.06Viga de amarre Eje C - Va frontal 1.00 2.00 2.15 0.20 0.12 0.10Viga de amarre Eje A - Va frontal 1.00 4.00 2.15 0.10 0.12 0.10Viga de amarre Eje A - Va frontal 1.00 4.00 2.15 0.20 0.12 0.21

03.01.04.11 VIGAS, CONCRETO 210 kg/cm2, M3 10.70Primer PisoV-1 (0.20X0.45) 1.00 2.00 17.15 0.20 0.45 3.09V-2 (0.22X0.55) 1.00 3.00 8.95 0.22 0.55 3.25V-3 (0.30X0.55) 1.00 2.00 8.95 0.30 0.55 2.95Viga de amarre del volado (0.15X0.55) 1.00 1.00 17.15 0.15 0.55 1.41

03.01.04.12 VIGAS, ENCOFRADO DESENCOFRADO M2 126.99Vigas de amarrePrimer PisoViga de amarre Eje C frontal 2.00 2.00 2.15 0.10 0.86Viga de amarre Eje C frontal 2.00 2.00 1.10 0.10 0.44Viga de amarre Eje C - Va frontal 3.00 2.00 1.20 0.20 1.44Viga de amarre Eje C - Va frontal 3.00 2.00 2.15 0.20 2.58Viga de amarre Eje A - Va frontal 3.00 4.00 2.15 0.10 2.58Viga de amarre Eje A - Va frontal 3.00 4.00 2.15 0.20 5.16Vigas principasles y secundarios primer pisoV-1 (0.20X0.45) 2.00 2.00 17.15 0.55 37.73V-2 (0.22X0.55) 2.00 3.00 8.95 0.55 29.54V-3 (0.30X0.55) 2.00 2.00 8.95 0.70 25.06Viga de amarre del volado (0.15X0.55) 2.00 1.00 17.15 0.63 21.61

03.01.04.13 VIGAS, ACERO FY=4200KG/CM2 KG 2,872.91

03.01.04.14 LOSA ALIGERADA, CONCRETO 210 kg/cm2 M3 16.63Primer PisoPaños extremos 1.00 2.00 7.00 3.97 0.125 6.95Paños intermedios 1.00 2.00 7.00 3.97 0.125 6.95Paños extremos pasadizo 1.00 2.00 1.38 3.97 0.125 1.37Paños intermedios pasadizo 1.00 2.00 1.38 3.97 0.125 1.37

03.01.04.15 LOSA ALIGERADA, ENCOFRADO DESENCOFRADO M2 142.23Primer PisoPaños extremos 1.00 2.00 7.00 3.97 55.58Paños intermedios 1.00 2.00 7.00 3.97 55.58Paños extremos pasadizo 1.00 2.00 1.38 3.97 10.96Paños intermedios pasadizo 1.00 2.00 1.38 3.97 10.96perimetro de la losa lareral 1.00 2.00 7.00 0.20 2.80perimetro de la losa frontal y posterior 1.00 8.00 3.97 0.20 6.35

03.01.04.16 LOSA ALIGERADA, ACERO FY=4200KG/CM2 KG 1,726.52

03.01.04.17 LOSA ALIGERADA, LADR. HUECO 15x30X30 UND 1,108.51Primer Piso Cant. LadrilloPaños extremos 1.00 2.00 7.00 3.97 8.33 462.98Paños intermedios 1.00 2.00 7.00 3.97 8.33 462.98Paños extremos pasadizo 1.00 2.00 1.38 3.97 8.33 91.27Paños intermedios pasadizo 1.00 2.00 1.38 3.97 8.33 91.27

03.01.05 MUROS Y TABIQUES DE ALBAÑILERIA

03.01.05.01 MURO DE LADRILLO KK TIPO IV CABEZA M:1:1:4 M2 57.92Primer PisoEje 1, 2, 3 1.00 3.00 7.15 2.70 57.92

Page 8: METRADOS CONSTRUCCIONES

PLANILLA DE METRADOS MODULO DE AULAS

PROYECTO :

DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEMS DESCRIPCIÓN UND N° VECES CANT LARGO ANCHO ALTURA PARCIAL TOTAL

03.01.05.02 MURO DE LADRILLO KK TIPO IV SOGA M:1:1:4 M2 18.07Primer PisoEje A 4.00 1.00 2.51 0.80 8.03Eje C 4.00 1.00 2.51 1.00 10.04

03.02 ARQUITECTURA03.02.01 REVOQUES ENLUCIDOS Y MOLDURAS

03.02.01.01 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 151.97Primer PisoEje 1, 2, 3 2.00 3.00 7.15 2.70 115.83Eje A 2.00 4.00 2.51 0.80 16.06Eje C 2.00 4.00 2.51 1.00 20.08

03.02.01.02 TARRAJEO DE COLUMNAS M2 160.90Primer PisoColumna Pc elevacion frontal 2.00 6.00 0.13 1.40 2.18Columna Pb elevacion frontal 2.00 6.00 0.20 2.85 6.84Columna Pc elevacion posterior 2.00 8.00 0.13 1.10 2.29Columna Pb elevacion posterior 2.00 4.00 0.20 2.85 4.56P1 2.00 4.00 1.00 4.40 35.20P2 2.00 3.00 1.02 4.40 26.93PLACA 1 2.00 6.00 1.57 4.40 82.90

03.02.01.03 TARRAJEO DE VIGAS M2 259.07Vigas de amarrePrimer PisoViga de amarre Eje C frontal 2.00 2.00 2.15 0.10 0.86Viga de amarre Eje C frontal 2.00 2.00 1.10 0.10 0.44Viga de amarre Eje C - Va frontal 3.00 2.00 1.20 0.20 1.44Viga de amarre Eje C - Va frontal 3.00 2.00 2.15 0.20 2.58Viga de amarre Eje A - Va frontal 3.00 4.00 2.15 0.10 2.58Viga de amarre Eje A - Va frontal 3.00 4.00 2.15 0.20 5.16Vigas principasles y secundarios primer pisoV-1 (0.20X0.45) 2.00 2.00 17.15 0.55 37.73V-2 (0.22X0.55) 2.00 3.00 8.95 0.55 29.54V-3 (0.30X0.55) 2.00 2.00 8.95 0.70 25.06Viga de amarre del volado (0.15X0.55) 2.00 1.00 17.15 0.63 21.61

03.02.01.04 VESTIDURA DE DERRAMES (1:5) M 132.08Primer PisoPuerta 01 2.00 2.00 2.05 8.20

1.00 2.00 1.10 2.20V1' 2.00 2.00 1.56 6.24

2.00 2.00 0.80 3.20V1 2.00 2.00 1.56 6.24

2.00 2.00 0.80 3.20V2 2.00 4.00 1.56 12.48

2.00 4.00 0.44 3.52V3 2.00 4.00 0.48 3.84

2.00 4.00 0.44 3.52V4 2.00 4.00 0.81 6.48

2.00 4.00 1.39 11.12V5 2.00 4.00 1.33 10.64

2.00 4.00 1.02 8.16V5a 2.00 4.00 1.33 10.64

2.00 4.00 0.43 3.44V6 2.00 4.00 1.33 10.64

2.00 4.00 0.53 4.24V6a 2.00 4.00 1.33 10.64

2.00 4.00 0.43 3.44

03.02.01.05 BRUÑAS SEGUN DETALLE (1 x 1 cm) M 228.48Primer PisoEje A 1.00 1.00 41.63 41.63Eje C 1.00 1.00 41.63 41.63Lateral 2.00 1.00 39.52 79.04interior 2.00 1.00 33.09 66.18

03.02.02 CIELO RASOS03.02.02.01 CIELO RASO CON MEZCLA C:A 1:5 M2 133.07

Primer Piso

Page 9: METRADOS CONSTRUCCIONES

PLANILLA DE METRADOS MODULO DE AULAS

PROYECTO :

DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEMS DESCRIPCIÓN UND N° VECES CANT LARGO ANCHO ALTURA PARCIAL TOTALPaños extremos 1.00 2.00 7.00 3.97 55.58Paños intermedios 1.00 2.00 7.00 3.97 55.58Paños extremos pasadizo 1.00 2.00 1.38 3.97 10.96Paños intermedios pasadizo 1.00 2.00 1.38 3.97 10.96

03.02.03 PISOS Y PAVIMENTOS03.02.03.01 PISO MACHIHEMBRADO DE MADERA M2 112.00

Primer PisoAulas 1.00 2.00 7.00 8.00 112.00

03.02.03.02 PISO DE CEMENTO PULIDO Y BRUÑADO E=2" S/COLOREAR M2 26.22

Pasadizo 1.00 1.00 19.00 1.38 26.22

03.02.03.03 PATIO Y VEREDA CONCRETO 175 kg/cm2 E=4" FROT. Y BRUÑADO M2 37.88Veredas Aulas posterior 1.00 1.00 23.80 1.00 23.80Veredas laterales 1.00 1.00 7.48 1.00 7.48

1.00 1.00 3.80 1.00 3.801.00 1.00 2.80 1.00 2.80

03.02.04 CONTRAZOCALOS03.02.04.01 CONTRAZOCALO S/COLOREAR H=20 cm MEZCLA 1:2 e=1.5 cm M 77.20

Primer PisoEje A y C 1.00 2.00 17.15 34.30Eje 1 y 5 1.00 2.00 7.45 14.90

03.02.04.02 CONTRAZOCALO DE MADERA E=10 CM M 28.00Primer PisoAulas 2.00 2.00 7.00 28.00

03.02.05 CARPINTERIA DE MADERA03.02.05.01 PUERTA CEDRO M2 4.51

Primer PisoPuerta 1 (P1) 1.00 2.00 1.10 2.05 4.51

03.02.05.02 VENTANA CEDRO C/SEG M2 25.91Primer PisoV1' 1.00 2.00 1.56 0.80 2.50V1 1.00 2.00 1.56 0.80 2.50V2 1.00 4.00 1.56 0.44 2.75V3 1.00 4.00 0.48 0.44 0.84V4 1.00 4.00 0.81 1.39 4.50V5 1.00 4.00 1.33 1.02 5.43V5a 1.00 4.00 1.33 0.43 2.29V6 1.00 4.00 1.33 0.53 2.82V6a 1.00 4.00 1.33 0.43 2.29

03.02.05.03 TICERO DE MADERA CEDRO (L=5 m) BARNIZADO UND 2.00Primer PisoEn Aulas 1.00 2.00 2.00

03.02.06 CERRAJERIA03.02.06.01 BISAGRA DE ACERO ALUMINIZADO DE 4" PESADA EN PUERTA PZA 4.00

Primer PisoPuerta 1 2.00 2.00 4.00

03.02.06.02 BISAGRA DE ACERO ALUMINIZADO DE 2.5" PESADA EN PUERTA/VENTANA PZA 4.00Primer PisoEntre puerta 1 y ventana 2 2.00 2.00 4.00

03.02.06.03 CERRADURA DOS GOLPES EN PUERTA PZA 2.00Primer PisoPuerta 1 1.00 2.00 2.00

03.02.06.04 CERROJO "SAPITO" SEGURIDAD BAT.VENTANA PZA 26.00Primer PisoEntre puerta 1 y ventana 2 2.00 4.00 8.00Ventana 1 2.00 9.00 18.00

03.02.06.05 MANIJA DE BRONCE 4" PARA PUERTAS PZA 2.00Primer PisoPuerta 1 1.00 2.00 2.00

03.02.06.06 CERROJO DE 3" ALUMINIZADO PARA PUERTA PZA 2.00Primer Piso

Page 10: METRADOS CONSTRUCCIONES

PLANILLA DE METRADOS MODULO DE AULAS

PROYECTO :

DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEMS DESCRIPCIÓN UND N° VECES CANT LARGO ANCHO ALTURA PARCIAL TOTALPuerta 1 1.00 2.00 2.00

03.02.07 VIDRIOS, CRISTALES Y SIMILARES03.02.07.01 VIDRIOS SEMIDOBLES IMPORTADO P2 278.76

Primer PisoV1' 1.00 2.00 1m2=10.76p2 1.56 0.80 26.86V1 1.00 2.00 1m2=10.76p2 1.56 0.80 26.86V2 1.00 4.00 1m2=10.76p2 1.56 0.44 29.54V3 1.00 4.00 1m2=10.76p2 0.48 0.44 9.09V4 1.00 4.00 1m2=10.76p2 0.81 1.39 48.46V5 1.00 4.00 1m2=10.76p2 1.33 1.02 58.39V5a 1.00 4.00 1m2=10.76p2 1.33 0.43 24.61V6 1.00 4.00 1m2=10.76p2 1.33 0.53 30.34V6a 1.00 4.00 1m2=10.76p2 1.33 0.43 24.61

03.02.08 PINTURA03.02.08.01 PINTURA LATEX 2 MANOS EN CIELO RASO M2 133.07

Paños extremos 1.00 2.00 7.00 3.97 55.58Paños intermedios 1.00 2.00 7.00 3.97 55.58Paños extremos pasadizo 1.00 2.00 1.38 3.97 10.96Paños intermedios pasadizo 1.00 2.00 1.38 3.97 10.96

03.02.08.02 PINTURA OLEO 2 MANOS EN MUROS, VIGAS Y COLUMNAS M2 444.26MUROSPrimer PisoEje 1, 2, 3 2.00 3.00 7.15 2.70 115.83Eje A 2.00 4.00 2.51 0.80 16.06Eje C 2.00 4.00 2.51 1.00 20.08

2.00 2.00 1.10 1.00 4.40COLUMNASPrimer PisoColumna Pc elevacion frontal 2.00 6.00 0.13 1.40 2.18Columna Pb elevacion frontal 2.00 6.00 0.20 2.85 6.84Columna Pc elevacion posterior 2.00 8.00 0.13 1.10 2.29Columna Pb elevacion posterior 2.00 4.00 0.20 2.85 4.56P1 2.00 4.00 1.00 4.40 35.20P2 2.00 3.00 1.02 4.40 26.93PLACA 1 2.00 6.00 1.57 4.40 82.90

VIGASVigas de amarrePrimer PisoViga de amarre Eje C frontal 2.00 2.00 2.15 0.10 0.86Viga de amarre Eje C frontal 2.00 2.00 1.10 0.10 0.44Viga de amarre Eje C - Va frontal 3.00 2.00 1.20 0.20 1.44Viga de amarre Eje C - Va frontal 3.00 2.00 2.15 0.20 2.58Viga de amarre Eje A - Va frontal 3.00 4.00 2.15 0.10 2.58Viga de amarre Eje A - Va frontal 3.00 4.00 2.15 0.20 5.16Vigas principasles y secundarios primer pisoV-1 (0.20X0.45) 2.00 2.00 17.15 0.55 37.73V-2 (0.22X0.55) 2.00 3.00 8.95 0.55 29.54V-3 (0.30X0.55) 2.00 2.00 8.95 0.70 25.06Viga de amarre del volado (0.15X0.55) 2.00 1.00 17.15 0.63 21.61

03.02.08.03 PINTURA BARNIZ EN CARP.DE MADERA M2 4.51Primer PisoPuerta 1 (P1) 1.00 2.00 1.10 2.05 4.51

03.02.08.04 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CEMENTO H=20CM M 49.20Primer PisoEje A y C 1.00 2.00 17.15 34.30Eje 1 y 5 1.00 2.00 7.45 14.90

03.02.09 VARIOS03.02.09.01 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1" M 50.00

Veredas Aulas posterior 1.00 1.00 15.00 15.00Veredas Aulas anterior 1.00 1.00 15.00 15.00Veredas laterales 1.00 1.00 10.00 10.00

1.00 1.00 10.00 10.00

03.02.09.02 PIZARRA CEMENTO 5x1.5 SIN TISERO PZA 2.00Primer PisoEn Aulas 1.00 2.00 2.00

03.02.09.03 JUNTA DE DILATACION CON ESPUMA PLASTICA + JEBE MICROPOROSO M 30.80

Page 11: METRADOS CONSTRUCCIONES

PLANILLA DE METRADOS MODULO DE AULAS

PROYECTO :

DEPARTAMENTO : AYACUCHO PROVINCIA : LA MARDISTRITO : ANCO LUGAR : OSQOQOCHA

ITEMS DESCRIPCIÓN UND N° VECES CANT LARGO ANCHO ALTURA PARCIAL TOTALAula posterior 1.00 16.00 1.10 17.60aula frontal 1.00 12.00 1.10 13.20

03.03 INSTALACIONES ELECTRICAS03.03.01 SALIDAS

03.03.01.01 SALIDA DE TECHO (CENTRO DE LUZ) PTO 12.00Primer PisoEn Aulas 1.00 8.00 8.00Pasadizo 1.00 4.00 4.00

03.03.01.02 SALIDA DE TOMACORRIENTE DOBLE CON LINEA DE TIERRA PTO 8.00Primer PisoEn Aulas 1.00 8.00 8.00

03.03.02 TABLEROS Y CUCHILLAS (LLAVES)03.03.02.01 CAJAS DE PASE F°G° 6"X6"X3" UND 1.00

1.00 1.00 1.0003.03.02.02 TAB. AUT. 1-2X50,1-2x20,2-2x15A UND 1.00

1.00 1.00 1.00

03.03.03 ARTEFACTOS03.03.03.01 ART. FLUORESCENTE 3/36W (SIM. E JOSFEL) UND

Primer Piso 8.00En Aulas 1.00 8.00 8.00

03.03.03.02 ART. FLUOR. 2/18W EMPOTRADO MARCO ALUM (DIF. PLAS) UND 4.00Primer PisoPasadizo 1.00 4.00 4.00