POOL DE MAQUINARIAS PLANTILLA DE METRADO - CERCO PERIMETRICO ITEM DESCRIPCION UND. DIMENSIONES LARGO ANCHO ALTO 09.01.00 TRABAJOS PRELIMINARES 09.01.01 LIMPIEZA MANUAL DEL PERIMETRO TERRENO M 1.00 171.35 1.00 171.35 1.00 171.35 1.00 171.35 09.01.02 TRAZO Y REPLANTEO M2 1.00 171.35 1.00 1.00 171.35 1.00 1.00 171.35 1.00 1.00 171.35 1.00 09.02.00 MOVIMIENTO DE TIERRAS 09.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS M3 ZAPATA 31.00 0.80 0.80 1.00 CIMIENTO CORRIDO 1.00 57.39 0.40 0.80 ZAPATA 30.00 0.80 0.80 1.00 CIMIENTO CORRIDO 1.00 54.63 0.40 0.80 ZAPATA 30.00 0.80 0.80 1.00 CIMIENTO CORRIDO 1.00 55.42 0.40 0.80 ZAPATA 29.00 0.80 0.80 1.00 CIMIENTO CORRIDO 1.00 42.28 0.40 0.80 09.02.02 ELIMINACION DE MATERIAL EXCEDENTE (D=100 MT) M3 ESPJ. VIENE DE EXCAVACION 143.91 1.25 09.03.00 CONCRETO SIMPLE 09.03.01 CONCRETO 1:10+30%P.G. PARA CIMIENTOS CORRIDOS M3 PERFIL A-B 1.00 57.39 0.40 0.80 -37.00 0.20 0.40 0.80 PERFIL C-D 1.00 54.63 0.40 0.80 -40.00 0.20 0.40 0.80 PERFIL D-E 1.00 55.42 0.40 0.80 -40.00 0.20 0.40 0.80 PERFIL E-F 1.00 42.28 0.40 0.80 -40.00 0.20 0.40 0.80 -2.00 0.30 0.40 0.80 09.03.02 CONCRETO 1:8+25%P.M. PARA SOBRECIMIENTOS M3 1.00 57.39 0.15 0.30 -37.00 0.20 0.15 0.30 1.00 54.63 0.15 0.30 -40.00 0.20 0.15 0.30 1.00 55.42 0.15 0.30 -40.00 0.20 0.15 0.30 1.00 42.28 0.15 0.30 -40.00 0.20 0.15 0.30 -2.00 0.30 0.15 0.30 DISTRITO: ANDAHUAYLAS N° DE VECES

Upload: rechir-oscco

Post on 20-Feb-2016

4 views

Category:

Documents


0 download

DESCRIPTION

metrados

TRANSCRIPT

Page 1: Metrado Cerco Perimetrico

POOL DE MAQUINARIAS

PLANTILLA DE METRADO - CERCO PERIMETRICO

ITEM DESCRIPCION UND.N° DE VECES DIMENSIONES

PARCIAL TOTALLARGO ANCHO ALTO

09.01.00 TRABAJOS PRELIMINARES09.01.01 LIMPIEZA MANUAL DEL PERIMETRO TERRENO M 685.40

1.00 171.35 171.35

1.00 171.35 171.35

1.00 171.35 171.35

1.00 171.35 171.35

09.01.02 TRAZO Y REPLANTEO M2 685.40

1.00 171.35 1.00 171.35

1.00 171.35 1.00 171.35

1.00 171.35 1.00 171.35

1.00 171.35 1.00 171.35

09.02.00 MOVIMIENTO DE TIERRAS09.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS M3 143.91

ZAPATA 31.00 0.80 0.80 1.00 19.84

CIMIENTO CORRIDO 1.00 57.39 0.40 0.80 18.36

ZAPATA 30.00 0.80 0.80 1.00 19.20

CIMIENTO CORRIDO 1.00 54.63 0.40 0.80 17.48

ZAPATA 30.00 0.80 0.80 1.00 19.20

CIMIENTO CORRIDO 1.00 55.42 0.40 0.80 17.73

ZAPATA 29.00 0.80 0.80 1.00 18.56

CIMIENTO CORRIDO 1.00 42.28 0.40 0.80 13.53

09.02.02 ELIMINACION DE MATERIAL EXCEDENTE (D=100 MT) M3 ESPJ. 179.89 VIENE DE EXCAVACION 143.91 1.25 179.89

09.03.00 CONCRETO SIMPLE09.03.01 CONCRETO 1:10+30%P.G. PARA CIMIENTOS CORRIDOS M3 56.87

PERFIL A-B 1.00 57.39 0.40 0.80 18.36

-37.00 0.20 0.40 0.80 -2.37

PERFIL C-D 1.00 54.63 0.40 0.80 17.48

-40.00 0.20 0.40 0.80 -2.56

PERFIL D-E 1.00 55.42 0.40 0.80 17.73

-40.00 0.20 0.40 0.80 -2.56

PERFIL E-F 1.00 42.28 0.40 0.80 13.53

-40.00 0.20 0.40 0.80 -2.56

-2.00 0.30 0.40 0.80 -0.19

09.03.02 CONCRETO 1:8+25%P.M. PARA SOBRECIMIENTOS M3 8.00

1.00 57.39 0.15 0.30 2.58

-37.00 0.20 0.15 0.30 -0.33

1.00 54.63 0.15 0.30 2.46

-40.00 0.20 0.15 0.30 -0.36

1.00 55.42 0.15 0.30 2.49

-40.00 0.20 0.15 0.30 -0.36

1.00 42.28 0.15 0.30 1.90

-40.00 0.20 0.15 0.30 -0.36

-2.00 0.30 0.15 0.30 -0.03

DISTRITO: ANDAHUAYLAS

Page 2: Metrado Cerco Perimetrico

ITEM DESCRIPCION UND.N° DE VECES DIMENSIONES

PARCIAL TOTALLARGO ANCHO ALTO

09.03.03 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO HASTA 0.30 MT M2 CANT. 106.63

PERFIL A-B 1.00 57.39 2.00 0.30 34.43

-37.00 0.20 2.00 0.30 -4.44

PERFIL C-D 1.00 54.63 2.00 0.30 32.78

-40.00 0.20 2.00 0.30 -4.80

PERFIL D-E 1.00 55.42 2.00 0.30 33.25

-40.00 0.20 2.00 0.30 -4.80

PERFIL E-F 1.00 42.28 2.00 0.30 25.37

-40.00 0.20 2.00 0.30 -4.80

-2.00 0.30 2.00 0.30 -0.36

09.04.00 CONCRETO ARMADO09.04.01 ZAPATAS09.04.01.01 CONCRETO EN ZAPATAS FC=210KG/CM2 M3 38.40

PERFIL A-B 31.00 0.80 0.80 0.50 9.92

PERFIL C-D 30.00 0.80 0.80 0.50 9.60

PERFIL D-E 30.00 0.80 0.80 0.50 9.60

PERFIL E-F 29.00 0.80 0.80 0.50 9.28

09.04.01.02 ACERO FY=4200KG/CM2, GRADO 60 PARA ZAPATAS KG Nº Fº KG/CM2 376.32

PERFIL A-B 31.00 0.70 8.00 0.56 97.22

PERFIL C-D 30.00 0.70 8.00 0.56 94.08

PERFIL D-E 30.00 0.70 8.00 0.56 94.08

PERFIL E-F 29.00 0.70 8.00 0.56 90.94

-

09.04.02 COLUMNAS09.04.02.01 CONCRETO EN COLUMNAS FC=210KG/CM2 M3 - 40.98

PERFIL A-B 37.00 0.20 0.25 3.50 6.48

PERFIL C-D 40.00 0.20 0.25 3.50 7.00

PERFIL D-E 40.00 0.20 0.25 3.50 7.00

PERFIL E-F 40.00 0.20 0.25 3.50 7.00

40.00 0.30 0.30 3.75 13.50

09.04.02.02 ACERO FY=4200KG/CM2, GRADP 60 PARA COLUMNAS KG Nº Fº KG/ML 4,933.00

ACERO LONGITUDINAL C1 Ø=1/2" 157.00 4.29 4.00 1.02 2,748.00

C-2 Ø=1/2" 40.00 4.55 4.00 1.02 742.56

ESTRIBOS C1 Ø=1/4" 157.00 1.05 35.00 0.25 1,442.44

C-2 Ø=1/4" 40.00 1.15 38.00 0.25 437.00

09.04.02.03 ENCOFRADO Y DESENCOFRADO DE COLUMNAS M2 687.15

C1 157.00 4.29 0.75 505.15

C-2 40.00 4.55 1.00 182.00

09.04.03 VIGAS09.04.03.01 CONCRETO EN VIGAS FC=210KG/CM2 M3 10.71

PERFIL A-B 1.00 57.39 0.20 0.25 2.87

PERFIL C-D 1.00 54.63 0.20 0.25 2.73

PERFIL D-E 1.00 55.42 0.20 0.25 2.77

PERFIL E-F 1.00 42.28 0.20 0.25 2.11

PUERTA PRINCIPAL 1.00 4.40 0.20 0.25 0.22

09.04.03.02 ACERO FY=4200KG/CM2, GRADO 60 PARA VIGAS KG Nº Fº KG/ML 1,264.58

ACERO LONGITUDINAL C1 Ø=1/2" 1.00 214.12 4.00 1.02 873.61

ESTRIBOS C1 Ø=1/4" 1.00 1,528.82 1.05 0.25 401.31

POR ESPACIO DE COLUMNAS -1.00 39.40 1.05 0.25 -10.34

09.04.03.03 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 105.36

1.00 214.12 0.50 107.06

Page 3: Metrado Cerco Perimetrico

ITEM DESCRIPCION UND.N° DE VECES DIMENSIONES

PARCIAL TOTALLARGO ANCHO ALTO

POR ESPACIO DE COLUMNAS -1.00 17.00 0.10 -1.70

09.05.00 MUROS Y TABIQUES DE ALBAÑILERIA09.05.01 MURO DE SOGA CON MORTERO 1:5 C:A ACABADO CARAVIST M2 479.03

PERFIL A-B 1.00 57.39 2.70 154.95

POR COLUMNA -37.00 0.20 2.70 -19.98

PERFIL C-D 1.00 54.63 2.70 147.50

POR COLUMNA -40.00 0.20 2.70 -21.60

PERFIL D-E 1.00 55.42 2.70 149.63

POR COLUMNA -40.00 0.20 2.70 -21.60

PERFIL E-F 1.00 42.28 2.70 114.16

POR COLUMNA -40.00 0.20 2.70 -21.60

POR COLUMNA -3.00 0.30 2.70 -2.43

09.06.00 TARRAJEO DE SUPERFICIES09.06.01 TARRAJEO DE SUPERF. COLUMNAS Y VIGAS M2 390.50

COLUMNAS C1 157.00 2.70 0.60 254.34

C-2 3.00 2.95 0.90 7.97

VIGAS 1.00 259.78 0.50 129.89

POR ESPACIO DE COLUMNAS -1.00 17.00 0.10 -1.70

09.07.00 CONTRAZOCALOS09.07.01 CONTRAZOCALO DE CEMENTO PULIDO M2 122.29

PERFIL A-B 2.00 57.39 0.30 34.43

PERFIL C-D 2.00 54.63 0.30 32.78

PERFIL D-E 2.00 55.42 0.30 33.25

PERFIL E-F 2.00 42.28 0.30 25.37

POR PUERTAS -4.00 1.20 0.30 -1.44

-2.00 3.50 0.30 -2.10

09.08.00 PINTURA09.09.01 PINTURA DE COLUMNAS Y VIGAS M2 404.49

COLUMNAS C1 105.00 2.70 0.60 170.10

C-2 40.00 2.95 0.90 106.20

VIGAS 1.00 259.78 0.50 129.89

POR ESPACIO DE COLUMNAS -1.00 17.00 0.10 -1.70

09.09.00 CERRAJERIA09.09.01 PUERTA METALICA 1.2 X 2.8 GBL 2.00 2.00 2.00

09.09.02 PUERTA METALICA 3.5 X 2.8 GBL 1.00 1.00 1.00