CONTRATISTA - CONSERVADOR : CONSORCIO VIAL JUANJUI Item UND METRADO P.U. TOTAL 01.00 TRABAJOS PRELIMINARES 28,685.45 01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 17,876.02 17,876.02 01.02 TRAZO Y REPLANTEO M2 6,325.00 1.71 10,809.43 02.00 MOVIMIENTO DE TIERRAS - PLATAFORMA DE MONTAJE 19,553.65 02.01 DESBROCE DEL ÁREA DE TRABAJO M2 425.00 0.30 127.43 02.02 CONFORMACIÓN DE PLATAFORMA PARA MONTAJE M3 562.50 34.54 19,426.22 03.00 COSTO AMBIENTAL 3,451.14 03.01 ACONDICIONAMIENTO DE DEPOSITOS DE MATERIAL EXCEDENTE M3 34.04 2.44 83.16 03.02 RESTAURACION DE AREA AFECTADA HA 0.04 8,658.34 367.98 03.03 PROGRAMA DE CONTINGENCIAS MES 1.00 3,000.00 3,000.00 04.00 ESTRUCTURA METALICA 1,081,461.08 04.01 TRANSPORTE A OBRA DE ESTRUCTURA MODULAR INC. SEGURO VJE 4.00 14,100.00 56,400.00 04.02 DESCARGA EN OBRA DE ESTRUCTURA MODULAR TON 97.82 306.57 29,988.06 04.03 CONCRETO FC=280 KG/CM2 (PREMEZCLADO) PARA APOYO DE PUENTE MODULAR M3 13.21 466.28 6,157.16 04.04 ENCOFRADO Y DESENCOFRADO DE APOYO DE PUENTE MODULAR M2 46.97 48.33 2,269.90 04.05 ACERO DE REFUERZO PARA APOYO DE PUENTE MODULAR KG 2,465.03 6.33 15,603.61 04.06 MONTAJE DE ESTRUCTURA MODULAR TON 97.82 4,346.09 425,124.98 04.07 LANZAMIENTO DE ESTRUCTURA MODULAR GLB 1.00 494,460.00 494,460.00 04.08 DESMONTAJE DE NARIZ DE LANZAMIENTO DE LA ESTRUCTURA MODULAR TON 9.27 1,873.20 17,357.37 04.09 TRANSPORTE A ALMACEN DE PVN - NARIZ DE LANZAMIENTO INC. SEGURO VJE 1.00 14,100.00 14,100.00 04.10 TRANSPORTE A ALMACEN DE PVN - ELEMENTOS DESMONTADOS INC. SEGURO VJE 2.00 10,000.00 20,000.00 05.00 MURO DE IMPACTO 2,210.85 05.01 CONCRETO FC=280 KG/CM2 (PREMEZCLADO) PARA MURO DE IMPACTO M3 1.44 466.28 671.44 05.02 ENCOFRADO Y DESENCOFRADO DE MURO DE IMPACTO M2 12.48 48.33 603.16 05.03 ACERO DE REFUERZO PARA MURO DE IMPACTO KG 147.91 6.33 936.25 06.00 LOSA DE APROXIMACION 14,237.30 06.01 DEMOLICION DE ASFALTO PARA LOSA DE APROXIMACION M3 3.51 115.27 404.60 06.02 EXCAVACION EN PLATAFORMA PARA LOSA DE APROXIMACION M3 9.85 26.15 257.65 06.03 CONCRETO FC=280 KG/CM2 (PREMEZCLADO) PARA LOSA DE APROXIMACION M3 13.36 466.28 6,230.60 06.04 CONCRETO F'C=140 KG/CM2 PARA SOLADO DE LOSA DE APROXIMACION M3 2.01 220.85 443.36 06.05 ACERO DE REFUERZO PARA LOSA DE APROXIMACION KG 1,090.22 6.33 6,901.09 07.00 REDUCTOR DE VELOCIDAD 14,441.50 07.01 DEMOLICION DE ASFALTO PARA REDUCTOR DE VELOCIDAD M3 5.63 115.27 648.40 07.02 EXCAVACION EN PLATAFORMA PARA REDUCTOR DE VELOCIDAD M3 9.38 26.15 245.16 07.03 CONCRETO FC=280 KG/CM2 (PREMEZCLADO) PARA REDUCTOR DE VELOCIDAD M3 13.99 466.28 6,524.82 07.04 ENCOFRADO Y DESENCOFRADO DE REDUCTOR DE VELOCIDAD M2 3.73 48.33 180.35 07.05 ACERO DE REFUERZO PARA REDUCTOR DE VELOCIDAD KG 871.94 6.33 5,516.48 07.06 MARCAS EN EL PAVIMENTO DE REDUCTOR DE VELOCIDAD M2 75.00 17.68 1,326.29 08.00 TRANSPORTE 33,946.59 08.01 TRANSPORTE DE MATERIAL DE CANTERA PARA PROTECCION DE ESTRIBOS D<= 1 KM M3K 225.00 2.63 591.64 08.02 TRANSPORTE DE MATERIAL DE CANTERAL PARA PROTECCION DE ESTRIBOS D> 1 KM M3K 22,720.50 1.46 33,267.36 08.03 TRANSPORTE DE EXCEDENTE A DME D<= 1 KM M3K 33.35 2.63 87.59 09.00 ENCAUZAMIENTO Y PROTECCION DE ESTRIBO 20,914.35 PARTIDAS Gestión y Conservación Vial por Niveles de Servicio de la Carretera Emp. PE-18A (Dv. Tingo María) - Aucayacu - Nuevo Progreso - Tocache - Juanjui - Picota - Tarapoto PRESUPUESTO : ATENCION DE EMERGENCIA (COLAPSO DEL PUENTE PUCAYACU - TRASLADO, MONTAJE Y PUESTA EN MARCHA DEL NUEVO PUENTE PUCAYACU PRESUPUESTO EMERGENCIA VIAL N° 007

Upload: fiorella-corazon-gueivin

Post on 29-Sep-2015

6 views

Category:

Documents


0 download

DESCRIPTION

PUENTE PUCAYACU

TRANSCRIPT

  • CONTRATISTA - CONSERVADOR : CONSORCIO VIAL JUANJUI

    Item UND METRADO P.U. TOTAL

    01.00 TRABAJOS PRELIMINARES 28,685.45

    01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 17,876.02 17,876.02

    01.02 TRAZO Y REPLANTEO M2 6,325.00 1.71 10,809.43

    02.00 MOVIMIENTO DE TIERRAS - PLATAFORMA DE MONTAJE 19,553.65

    02.01 DESBROCE DEL REA DE TRABAJO M2 425.00 0.30 127.43

    02.02 CONFORMACIN DE PLATAFORMA PARA MONTAJE M3 562.50 34.54 19,426.22

    03.00 COSTO AMBIENTAL 3,451.14

    03.01 ACONDICIONAMIENTO DE DEPOSITOS DE MATERIAL EXCEDENTE M3 34.04 2.44 83.16

    03.02 RESTAURACION DE AREA AFECTADA HA 0.04 8,658.34 367.98

    03.03 PROGRAMA DE CONTINGENCIAS MES 1.00 3,000.00 3,000.00

    04.00 ESTRUCTURA METALICA 1,081,461.08

    04.01 TRANSPORTE A OBRA DE ESTRUCTURA MODULAR INC. SEGURO VJE 4.00 14,100.00 56,400.00

    04.02 DESCARGA EN OBRA DE ESTRUCTURA MODULAR TON 97.82 306.57 29,988.06

    04.03 CONCRETO FC=280 KG/CM2 (PREMEZCLADO) PARA APOYO DE PUENTE MODULAR M3 13.21 466.28 6,157.16

    04.04 ENCOFRADO Y DESENCOFRADO DE APOYO DE PUENTE MODULAR M2 46.97 48.33 2,269.90

    04.05 ACERO DE REFUERZO PARA APOYO DE PUENTE MODULAR KG 2,465.03 6.33 15,603.61

    04.06 MONTAJE DE ESTRUCTURA MODULAR TON 97.82 4,346.09 425,124.98

    04.07 LANZAMIENTO DE ESTRUCTURA MODULAR GLB 1.00 494,460.00 494,460.00

    04.08 DESMONTAJE DE NARIZ DE LANZAMIENTO DE LA ESTRUCTURA MODULAR TON 9.27 1,873.20 17,357.37

    04.09 TRANSPORTE A ALMACEN DE PVN - NARIZ DE LANZAMIENTO INC. SEGURO VJE 1.00 14,100.00 14,100.00

    04.10 TRANSPORTE A ALMACEN DE PVN - ELEMENTOS DESMONTADOS INC. SEGURO VJE 2.00 10,000.00 20,000.00

    05.00 MURO DE IMPACTO 2,210.85

    05.01 CONCRETO FC=280 KG/CM2 (PREMEZCLADO) PARA MURO DE IMPACTO M3 1.44 466.28 671.44

    05.02 ENCOFRADO Y DESENCOFRADO DE MURO DE IMPACTO M2 12.48 48.33 603.16

    05.03 ACERO DE REFUERZO PARA MURO DE IMPACTO KG 147.91 6.33 936.25

    06.00 LOSA DE APROXIMACION 14,237.30

    06.01 DEMOLICION DE ASFALTO PARA LOSA DE APROXIMACION M3 3.51 115.27 404.60

    06.02 EXCAVACION EN PLATAFORMA PARA LOSA DE APROXIMACION M3 9.85 26.15 257.65

    06.03 CONCRETO FC=280 KG/CM2 (PREMEZCLADO) PARA LOSA DE APROXIMACION M3 13.36 466.28 6,230.60

    06.04 CONCRETO F'C=140 KG/CM2 PARA SOLADO DE LOSA DE APROXIMACION M3 2.01 220.85 443.36

    06.05 ACERO DE REFUERZO PARA LOSA DE APROXIMACION KG 1,090.22 6.33 6,901.09

    07.00 REDUCTOR DE VELOCIDAD 14,441.50

    07.01 DEMOLICION DE ASFALTO PARA REDUCTOR DE VELOCIDAD M3 5.63 115.27 648.40

    07.02 EXCAVACION EN PLATAFORMA PARA REDUCTOR DE VELOCIDAD M3 9.38 26.15 245.16

    07.03 CONCRETO FC=280 KG/CM2 (PREMEZCLADO) PARA REDUCTOR DE VELOCIDAD M3 13.99 466.28 6,524.82

    07.04 ENCOFRADO Y DESENCOFRADO DE REDUCTOR DE VELOCIDAD M2 3.73 48.33 180.35

    07.05 ACERO DE REFUERZO PARA REDUCTOR DE VELOCIDAD KG 871.94 6.33 5,516.48

    07.06 MARCAS EN EL PAVIMENTO DE REDUCTOR DE VELOCIDAD M2 75.00 17.68 1,326.29

    08.00 TRANSPORTE 33,946.59

    08.01 TRANSPORTE DE MATERIAL DE CANTERA PARA PROTECCION DE ESTRIBOS D 1 KM M3K 22,720.50 1.46 33,267.36

    08.03 TRANSPORTE DE EXCEDENTE A DME D

  • CONTRATISTA - CONSERVADOR : CONSORCIO VIAL JUANJUI

    Item UND METRADO P.U. TOTALPARTIDAS

    Gestin y Conservacin Vial por Niveles de Servicio de la Carretera Emp. PE-18A (Dv. Tingo Mara) - Aucayacu - Nuevo Progreso - Tocache - Juanjui - Picota - Tarapoto

    PRESUPUESTO : ATENCION DE EMERGENCIA (COLAPSO DEL PUENTE PUCAYACU - TRASLADO, MONTAJE Y PUESTA EN MARCHA DEL NUEVO PUENTE PUCAYACU

    PRESUPUESTO EMERGENCIA VIAL N 007

    09.01 ENCAUZAMIENTO DEL CAUCE M3 1,000.00 7.56 7,558.53

    09.02 PROTECCION DE ESTRIBO DEL PUENTE M3 225.00 59.36 13,355.82

    10.00 GASTOS GENERALES FUERA DE LA CONSERVACIN 74,000.00

    10.01 ESPECIALISTA DE PUENTES MES 2.00 18,000.00 36,000.00

    10.02 ESPECIALISTA DE MONTAJE Y LANZAMIENTO MES 2.00 10,000.00 20,000.00

    10.03 ESPECIALISTA DE SEALIZACION, SEGURIDAD OCUPACIONAL Y MEDIO AMBIENTE MES 1.00 6,000.00 6,000.00

    10.04 MAESTRO CALDERERO MONTAJE Y LANZAMIENTO MES 2.00 6,000.00 12,000.00

    11.00 SEALIZACIN INFORMATIVA 2,060.00

    11.01 SEALES PREVENTIVA P-33 UND 2.00 190.00 380.00

    11.02 SEALES REGLAMENTARIA R-30 UND 2.00 190.00 380.00

    11.03 SEALES INFORMATIVA UND 2.00 650.00 1,300.00

    COSTO DIRECTO S/. 1,294,961.90

    UTILIDADES 10.00% 129,496.19

    SUB TOTAL TOTAL S/. 1,424,458.09

    IGV 18.00% 256,402.46

    TOTAL S/. 1,680,860.55