RESUMEN DE MEDICIONES 1 Nro. DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO MONTO TOTAL EJECUTADA ANTERIOR 1 EXCAVACION A MAQUINA M3 300.00 100.00 30,000.00 0.00 2 RELLENO M3 120.00 160.00 19,200.00 0.00 3 CONCRETO M3 60.00 90.00 5,400.00 0.00 4 ACERO KG 160.00 120.00 19,200.00 0.00 5 TUBERIA PIEZA 40.00 100.00 4,000.00 0.00 6 ANTENA PIEZA 90.00 100.00 9,000.00 0.00 7 PIEDRA PICADA M3 120.00 500.00 60,000.00 0.00 146,800.00 RESUMEN DE MEDICIONES 2 Nro. DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO MONTO TOTAL EJECUTADA ANTERIOR 1 EXCAVACION A MAQUINA 300.00 100.00 30,000.00 320.00 2 RELLENO 120.00 160.00 19,200.00 100.00 3 CONCRETO 60.00 90.00 5,400.00 65.00 4 ACERO 160.00 120.00 19,200.00 120.00 5 TUBERIA 40.00 100.00 4,000.00 0.00 6 ANTENA 90.00 100.00 9,000.00 0.00 7 PIEDRA PICADA 120.00 500.00 60,000.00 0.00 146,800.00

Upload: carla-gonzalez

Post on 16-Jan-2016

228 views

Category:

Documents


0 download

DESCRIPTION

construccion valuaciones

TRANSCRIPT

Page 1: Ejercicio de Clase Examen 3

RESUMEN DE MEDICIONES 1

Nro. DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO MONTO TOTAL EJECUTADA ANTERIOR MONTO ANTERIOR

1 EXCAVACION A MAQUINA M3 300.00 100.00 30,000.00 0.00 0.00

2 RELLENO M3 120.00 160.00 19,200.00 0.00 0.00

3 CONCRETO M3 60.00 90.00 5,400.00 0.00 0.00

4 ACERO KG 160.00 120.00 19,200.00 0.00 0.00

5 TUBERIA PIEZA 40.00 100.00 4,000.00 0.00 0.00

6 ANTENA PIEZA 90.00 100.00 9,000.00 0.00 0.00

7 PIEDRA PICADA M3 120.00 500.00 60,000.00 0.00 0.00

146,800.00 0.00

RESUMEN DE MEDICIONES 2Nro. DESCRIPCION UNIDAD CANTIDAD PRECIO UNITARIO MONTO TOTAL EJECUTADA ANTERIOR MONTO ANTERIOR

1 EXCAVACION A MAQUINA 300.00 100.00 30,000.00 320.00 32,000.00

2 RELLENO 120.00 160.00 19,200.00 100.00 16,000.00

3 CONCRETO 60.00 90.00 5,400.00 65.00 5,850.00

4 ACERO 160.00 120.00 19,200.00 120.00 14,400.00

5 TUBERIA 40.00 100.00 4,000.00 0.00 0.00

6 ANTENA 90.00 100.00 9,000.00 0.00 0.00

7 PIEDRA PICADA 120.00 500.00 60,000.00 0.00 0.00

146,800.00 68,250.00

Page 2: Ejercicio de Clase Examen 3

CANT. EJECUTADA MONTO CANT. ACUMULADA MONTO ANTE. CANT. RELACIONADA MONTO A COBRAR CANT. POR RELACIONAR

320.00 32,000.00 320.00 32,000.00 300.00 30,000.00 20.00

100.00 16,000.00 100.00 16,000.00 100.00 16,000.00 0.00

65.00 5,850.00 65.00 5,850.00 60.00 5,400.00 5.00

120.00 14,400.00 120.00 14,400.00 120.00 14,400.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

68,250.00 68,250.00 65,800.00

CANT. EJECUTADA MONTO CANT. EJE. ACUMULADA MONTO ANTE. CANT. RELACIONADA MONTO A COBRAR CANT. POR RELACIONAR

20.00 2,000.00 340.00 34,000.00 0.00 0.00 40.00

25.00 4,000.00 125.00 20,000.00 20.00 3,200.00 5.00

10.00 900.00 75.00 6,750.00 0.00 0.00 15.00

45.00 5,400.00 165.00 19,800.00 40.00 4,800.00 5.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00

12,300.00 80,550.00 8,000.00

Page 3: Ejercicio de Clase Examen 3

MONTO POR RELACIONAR

2,000.00

0.00

450.00

0.00

0.00

0.00

0.00

2,450.00

MONTO POR RELACIONAR

4,000.00

800.00

1,350.00

600.00

0.00

0.00

0.00

6,750.00

Page 4: Ejercicio de Clase Examen 3

VALUACION 1 DE OBRA EJECUTADA

OBRA :FECHA D

CONTRATISTA : MONTO DEL CONTRATO : PERIODO DESDENº DEL CONTRATO:

PARTIDAS UNIDAD CANTIDAD PRECIO MONTO OBRA RELACION ANTERIOR OBRA RELACIONADA EN EL PERIODO

Nº DESCRIPCION UNITARIO TOTAL CANTIDAD BOLIVARES CANTIDAD BOLIVARES1 EXCAVACION A MAQUINA 300.00 100.00 30,000.00 0.00 0.00 300.00 30,000.00

2 RELLENO 120.00 160.00 19,200.00 0.00 0.00 100.00 16,000.00

3 CONCRETO 60.00 90.00 5,400.00 0.00 0.00 60.00 5,400.00

4 ACERO 160.00 120.00 19,200.00 0.00 0.00 120.00 14,400.00

5 TUBERIA 40.00 100.00 4,000.00 0.00 0.00 0.00 0.00

6 ANTENA 90.00 100.00 9,000.00 0.00 0.00 0.00 0.00

7 PIEDRA PICADA 120.00 500.00 60,000.00 0.00 0.00 0.00 0.00

TOTAL 146,800.00 TOTAL 0.00 TOTAL 65,800.00

UNIVERSIDAD RAFAEL URDANETAFACULTAD DE INGENIERIAESCUELA DE ING. CIVILELABORADO POR:

Page 5: Ejercicio de Clase Examen 3

M A

HASTA VALUACION No.1

RELACIONADA HASTA LA FECHA

CANTIDAD BOLIVARES300.00 30,000.00

100.00 16,000.00

60.00 5,400.00

120.00 14,400.00

0.00 0.00

0.00 0.00

0.00 0.00

TOTAL 65,800.00

Page 6: Ejercicio de Clase Examen 3

BALANCE DE OBRAS 1EMPRESA: CONTRATO No. FECHA:OBRA: HOJA No:

PARTIDAS UNIDAD CANTIDAD PRECIO MONTO CANTIDAD ACUMULADA AUMENTOS

Nº CONTRATO ORIGINAL UNITARIO TOTAL CANTIDAD MONTO CANTIDAD MONTO

1 EXCAVACION A MAQUINA 300.00 100.00 30,000.00 320.00 32,000.00 20.00 2,000.00

2 RELLENO 120.00 160.00 19,200.00 100.00 16,000.00 0.00

3 CONCRETO 60.00 90.00 5,400.00 65.00 5,850.00 5.00 450.00

4 ACERO 160.00 120.00 19,200.00 120.00 14,400.00 0.00

5 TUBERIA 40.00 100.00 4,000.00 0.00 0.00 0.00

6 ANTENA 90.00 100.00 9,000.00 0.00 0.00 0.00

7 PIEDRA PICADA 120.00 500.00 60,000.00 0.00 0.00 0.00

TOTAL 146,800.00 TOTAL 68,250.00 TOTAL 2,450.00

Page 7: Ejercicio de Clase Examen 3

DISMINUCIONES OBRAS POR EJECUTAR

CANTIDAD MONTO CANTIDAD MONTO

0.00 0.00

0.00 20.00 3,200.00

0.00 0.00

0.00 40.00 4,800.00

0.00 40.00 4,000.00

25.00 2,500.00 65.00 6,500.00

0.00 120.00 60,000.00

TOTAL 2,500.00 TOTAL 78,500.00 68,250.00

Page 8: Ejercicio de Clase Examen 3

UNIVERSIDAD RAFAEL URDANETAELABORADO POR:

EMPRESA VALUACION Nro. PERIODO FECHA DEL TRAMITE

URU 1 DESDE: HASTA: 7/30/2007

OBRA:

MONTO ORIGINAL DEL CONTRATO: 146,800.00MONTO DEL ANTICIPO 30%: 44,040.00

OBRA RELACIONADA MONTO (Bs) DEDUCCIONES MONTO (Bs)SEGUN CONTRATO 65,800.00 RETENCION DE FIEL CUMP. 10%

SEGUN AUMENTO RETENCION LABORAL 5%

ADICIONALES AMORTIZACION ANTICIPO 25% 16,450.00

RECONSIDERACIONES I.S.L.R 2%

IMPUESTO IVA 9% 5,922.00 OTROS

TOTAL Bs. 71,722.00 TOTAL Bs. 16,450.00

TOTAL A PAGAR POR ESTA LIQUIDACION 55,272.00

BALANCE DE OBRASESTADO DE CUENTA MONTO (Bs) RETENCIONES 5% Y 10% MONTO (Bs)

CONTRATO 146,800.00 LIQUIDACION ANTERIOR 0.00

AUMENTOS 2,450.00 PRESENTE LIQUIDACION 65,800.00

DISMINUCIONES 2,500.00 RETENCION ACUMULADA 0.00

POR EJECUTAR 78,500.00

EXTRAS ANTICIPORECONSIDERACIONES ANTICIPO 44,040.00

OTROS AMORTIZACION ANTERIOR 0.00

TOTAL EJECUTADO 68,250.00 AMORTIZACION PRESENTE 16,450.00

AMORTIZACION ACUM. 16,450.00

SALDO POR AMORTIZAR 27,590.00

BALANCE FINANCIEROCONTRATO ORIGINAL 146,800.00 RESUMEN PORCENTUAL FINANCIEROLIQUID. ANTERIORES % OBRA RELACIONADA 44.82%

LIQUID. PRESENTES 65,800.00 % OBRA POR RELACIONAR 55.18%

LIQUID. TOTALES 65,800.00 % ANTICIPO AMORTIZADO 44.82%

%ANTICIPO POR AMORTIZAR 55.18%

SALDO ACTUAL 81,000.00

SALDO REAL P/ LIQUID. 81,000.00

SALDO DISPONIBLE 81,000.00

LIQUIDACION DE OBRAS 1

Page 9: Ejercicio de Clase Examen 3

VALUACION 2 DE OBRA EJECUTADA

OBRA :

CONTRATISTA : MONTO DEL CONTRATO :Nº DEL CONTRATO:

PARTIDAS UNIDAD CANTIDAD PRECIO MONTO OBRA RELACION ANTERIOR

Nº DESCRIPCION TOTAL CANTIDAD BOLIVARES

1 EXCAVACION A MAQUINA M3 300.00 100.00 30,000.00 300.00 30,000.00

2 RELLENO M3 120.00 160.00 19,200.00 100.00 16,000.00

3 CONCRETO M3 60.00 90.00 5,400.00 60.00 5,400.00

4 ACERO KG 160.00 120.00 19,200.00 120.00 14,400.00

5 TUBERIA PIEZA 40.00 100.00 4,000.00 0.00 0.00

6 ANTENA PIEZA 90.00 100.00 9,000.00 0.00 0.00

7 PIEDRA PICADA M3 120.00 500.00 60,000.00 0.00 0.00

UNIVERSIDAD RAFAEL URDANETAFACULTAD DE INGENIERIAELABORADO POR:

Page 10: Ejercicio de Clase Examen 3

TOTAL 146,800.00 TOTAL 65,800.00

Page 11: Ejercicio de Clase Examen 3

FECHA D M A

PERIODO DESDE HASTA VALUACION No.2

OBRA EJECUTADA EN EL PERIODO EJECUTADO HASTA LA FECHA

CANTIDAD BOLIVARES CANTIDAD BOLIVARES0.00 0.00 300.00 30,000.00

20.00 3,200.00 120.00 19,200.00

0.00 0.00 60.00 5,400.00

40.00 4,800.00 160.00 19,200.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

Page 12: Ejercicio de Clase Examen 3

TOTAL 8,000.00 TOTAL 73,800.00

Page 13: Ejercicio de Clase Examen 3

BALANCE DE OBRAS 2

EMPRESA: CONTRATO No. FECHA:OBRA: HOJA No:

PARTIDAS UNIDAD CANTIDAD PRECIO MONTO OBRA ACUMULADA AUMENTOS

Nº CONTRATO ORIGINAL UNITARIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL

1 EXCAVACION A MAQUINA M3 300.00 100.00 30,000.00 340.00 34,000.00 40.00 4,000.00

2 RELLENO M3 120.00 160.00 19,200.00 125.00 20,000.00 5.00 800.00

3 CONCRETO M3 60.00 90.00 5,400.00 75.00 6,750.00 15.00 1,350.00

4 ACERO KG 160.00 120.00 19,200.00 165.00 19,800.00 5.00 600.00

5 TUBERIA PIEZA 40.00 100.00 4,000.00 0.00 0.00 0.00

6 ANTENA PIEZA 90.00 100.00 9,000.00 0.00 0.00 0.00

7 PIEDRA PICADA M3 120.00 500.00 60,000.00 0.00 0.00 0.00

TOTAL 146,800.00 TOTAL 80,550.00 TOTAL 6,750.00

Page 14: Ejercicio de Clase Examen 3

DISMINUCIONES OBRAS POR EJECUTAR

CANTIDAD TOTAL CANTIDAD TOTAL

0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00

0.00 40.00 4,000.00

68.00 6,800.00 22.00 2,200.00

0.00 120.00 60,000.00

TOTAL 6,800.00 TOTAL 66,200.00 80,550.00

Page 15: Ejercicio de Clase Examen 3

UNIVERSIDAD RAFAEL URDANETAELABORADO POR:

EMPRESA VALUACION Nro. PERIODO FECHA DEL TRAMITE

uru 2 DESDE: HASTA:

OBRA:

MONTO ORIGINAL DEL CONTRATO: 146,800.00MONTO DEL ANTICIPO 30%: 44,040.00

OBRA EJECUTADA MONTO (Bs) DEDUCCIONES MONTO (Bs)SEGUN CONTRATO 8,000.00 RETENCION DE FIEL CUMP. 10%

SEGUN AUMENTO RETENCION LABORAL 5%

ADICIONALES AMORTIZACION ANTICIPO 25% 2,000.00

RECONSIDERACIONES I.S.L.R 2%

IMPUESTO IVA 9% 720.00 OTROS

TOTAL Bs. 8,720.00 TOTAL Bs. 2,000.00

TOTAL A PAGAR POR ESTA LIQUIDACION 6,720.00

BALANCE DE OBRASESTADO DE CUENTA MONTO (Bs) RETENCIONES 5% Y 10% MONTO (Bs)

CONTRATO 146,800.00 LIQUIDACION ANTERIOR 0.00

AUMENTOS 6,750.00 PRESENTE LIQUIDACION 0.00

DISMINUCIONES 6,800.00 RETENCION ACUMULADA 0.00

POR EJECUTAR 66,200.00

EXTRAS ANTICIPORECONSIDERACIONES ANTICIPO 44,040.00

OTROS AMORTIZACION ANTERIOR 16,450.00

TOTAL EJECUTADO 80,550.00 AMORTIZACION PRESENTE 2,000.00

AMORTIZACION ACUM. 18,450.00

SALDO POR AMORTIZAR 25,590.00

BALANCE FINANCIEROCONTRATO ORIGINAL 146,800.00 RESUMEN PORCENTUAL FINANCIEROLIQUID. ANTERIORES 65,800.00 % OBRA RELACIONADA 50.27%

LIQUID. PRESENTES 8,000.00 % OBRA POR RELACIONAR 49.73%

LIQUID. TOTALES 73,800.00 % ANTICIPO AMORTIZADO 50.27%

%ANTICIPO POR AMORTIZAR 49.73%

SALDO ACTUAL 73,000.00

SALDO REAL P/ LIQUID. 73,000.00

SALDO DISPONIBLE 73,000.00

LIQUIDACION DE OBRAS