Download - Volúmenes de Excavación
ESCUELA DE INGENIERA CIVIL
ALUMNA:RUTH J. FLORES AGUILAR
FACULTAD:INGENIERA
CURSO:INGENIERA DE LA CONSTRUCCIN
TEMA:VOLMENES DE EXCAVACIN
PROFESOR:ING. MIGUEL A. ZAMORA CAPELLI
2014CLCULO DE VOLMNES DE EXCAVACIN
ZAPATASEJESLADOShTOTAL
EJE AEJE BEJE CAB
Z - 13151.201.201.409
Z - 22401.501.501.406
ZAPATASLADOShCANTIDADVOLUMEN (M3)
AB
Z - 11.201.201.40918.1
Z - 21.501.501.40618.9
SUB - TOTAL37.0
CIMIENTOS CORRIDOS
SECCIN A-AbhLVOLUMEN (M3)
EJE A0.601.409.207.73.051.751.652.75
EJE C0.601.409.808.23.051.901.952.90
EJE 10.601.405.24.43.052.15
EJE 50.601.405.24.43.052.15
TOTAL24.7
SECCIN B-BbhLVOLUMEN (M3)
EJE 3'0.601.402.291.92.29
EJE B-10.601.401.651.41.65
EJE B-20.601.401.741.51.74
EJE B-30.601.400.450.40.45
TOTAL5.1
SECCIN VC-1bhLVOLUMEN (M3)
EJE B0.601.708.909.12.901.601.652.75
EJE 20.601.704.905.02.902.00
EJE 30.601.704.754.82.752.00
EJE 40.601.704.754.82.752.00
TOTAL23.8
SUB - TOTAL53.6