Download - PARTIDAS GAVIONES

Transcript

Sheet1ItemItem AlternoDescripcinUnd.MetradoPrecio (S/.)Parcial (S/.)001CONSTRUCCION DE DE GAVIONES BADEN LA IRACA26:24001.01OBRAS PRELIMINARES16:48001.01.01LIMPIEZA DEL TERRENO CON EQUIPO(Retroexcavadora)m200:0055:1212:00001.01.02LIMPIEZA DEL TERRENO MANUALm200:0026:2400:00001.01.03RETIRO DE TUBERIAS HDPEund00:0040:4826:24001.01.04RETIRO DE COSTALES LLENADOS CON TIERRAund00:0050:2436:00001.01.05CORTE Y COMPACTADO MANUAL DE TERRENO PARA GAVIONES e=0.35mm200:0038:2457:36001.01.06SELECCION DE ROCA PARA GAVIONESm300:0045:3604:48001.02CONSTRUCCION DE GAVIONES09:36001.02.01TRAZO Y REPLANTEOm200:0033:3628:48001.02.02EXCAVACION MANUAL PARA GAVIONESm357:3645:3624:00001.02.03ACONDICIONAMIENTO DE GAVIONESund00:0000:0000:00001.02.04ENCOFRADO Y DESENCOFRADO DE GAVIONESm200:0033:3628:48001.02.05TRASLADO DE ROCA D=60mm300:0026:2431:12001.02.06LLENADO DE GAVIONES 1MX1Mm300:0045:3604:48001.02.07CONFORMACION DE BERMAS CON ROCA H=0.6M, B=0.8Mm00:0048:0012:00


Top Related