Download - Al Qasr Mall presentation
Saudi Diyar consultant
Al Qasr Mall Project
20th Feb. 2012
Al-Qasr Plan
Al Qasr Shopping CentreLead Architect: Albert Speer & PartnersLead Consultant: Saudi DiyarMain Contractor: Saudi Constructioneers
67,500 m² Land Area215,000 m² of BUA76,489.6 m² of Leasable Area368 Shop/Store1756 Parking Capacity
Construction Start: May 2008Expected completion: 31st Jan 2012
Current Status of PackagesPkg 6A: SAUDICO- Structural Works
Work In Place 100%
Forecast Completion Date 17-
Dec-09
Pkg 6B: SAUDICO- Finishes & MEP Works Work In Place
98.8% Forecast Completion Date 15-
Feb-12
Pkg 6C: Al Ojaimi- Substation & Cable Works Work In Place
100% Forecast Completion Date 30-
Oct-11
Project Total of completion all packages: 99.6%
Critical Milestones to Achieve Completion Date
All Construction Works Completed on or before- 15 Feb 2012Energize Transformer Rooms- 30 Oct 2011 ( Done)Telephone Cables and Cabinet- all material delivered & partially installed.Way finding mock up approval : 04.01.12, 45days for installation after
releasing LOI.Balance of the interior design packages in ProcessElectrical Panel Boards Delivery- 100 % delivered.Execution of the STC Contract Agreement- awaiting Signature Finalizing Al Shaya requirementsFinalizing the A/C requirements for the StoresFinalizing The Food Court Requirement (GAS)Epoxy Paint- Ground Floor painting
PROJECT: AL QASR MALL
LIST OF POTENTIAL ADDITIONAL WORKS
SN Description Rough Estimated Cost Duration Remarks
1 Fun Zone (Part A) - Waterproofing Awaiting SCE Cost
2 Drop Off area Awaiting SCE Cost from conceptual drawing provided by SDC
3 Additional Parking Areas (at North East) Awaiting SCE Cost
4 LPG Central Tank & Services 649,982.00 2 months
SR 649,982 - cost from Supplier/contractor (AL ROWAFED Est), Excluding Civil works which still awaiting from SCE
5 Additional HVAC works for Tenant (AL SHAYAH) 6,000,000.00 9 months As proposed by SCE
6 Water and Drainage for 17 shops 590,150.00 10 weeks (2.5 month) As proposed by SCE
7 Additional 4 nos. Panoramic Elevator 12 Months
* includes 1month design period of SDC* SDC awaiting DAAR's instruction to provide the design.
Floor Total(1)
In Process of Handing Over
(2)
Total HO To DAAR-PM (or
skipped)(3)
Handed Over to DAAR-PM with
No Tenant Action
(4)
Handed Over to
Tenant with No Further
Action(5)
Tenant Submitted Fit Out Design
Drawings for DAAR Approval but Did Not Start Fit-
Out Works(6)
Fit-Out Works Started
(7)
Ground Floor 54 2 52 44 2 1 5
First Floor 79 2 77 22 8 0 47
Second Floor 91 1 90 66 4 0 20
Third Floor 140 84 56 38 8 1 9
TOTAL 364 89 275 170 22 2 81
Area of Fit out on board M2 Total Leasable Area M2 Percentage achieved
33793 76489.6 44.18%
THE KEY PRE-OPENING TASKS NEEDED TO BE COMPLETED PRIOR TO THE MALL OPENING
Saudi Diyar consultant
Al Qasr Mall Project
Thank You