Page 1: Detalles Pozo Insp1

De + 0.20

Escala: ____________1:20

TUBERIA CON ATRAQUE

FRISO e= 0.02 M.

Escala: ________1:20

CORTE: D-D

0.2597

Escala: _____________1:20

DE INSPECCION CON PROFUNDIDADES > 1.80 M.

(INCLUYE TRASLAPO DE .30 M)

ANCLAJE PARA CONEXION DOMICILIARIA CON YEE VARIABLE ENTRE 10" Y 24"

0.40

.10Ø 10" .10

0.1000

VARIABLE

10" Y 24"

0.1000

1.00

Ø 6"

Ø =10"

0.10

CONCRETO 1:2:3

C O R T E : A - A

A

Escala: _________________________1:20

CONCRETO 1:2:3

Ø 6"

.10

.10

1.1219

0.6034

0.30

0.1000

VARIABLE

0.10

4

5

°

A

0.07

1 O 1/2" L=2.45

(INCLUYE TRASLAPO DE .30 M)

1 O 1/2" L=3.75

(INCLUYE TRASLAPO DE .30 M)

1 O 1/2" L=4.45

(INCLUYE TRASLAPO DE .30 M)

1 O 1/2" L=5.40

Escala: _____________1:20

ANILLO EN CONCRETO REFORZADO PARA POZOS

DE INSPECCION CON PROFUNDIDADES > 1.80 M.

1 O 1/2" L=3.65

20 O 3/8" L=.40 1 O 1/2" L=2.45

Escala: _____________1:20

INSPECCION CON PROFUNDIDADES > 1.80 M.

DETALLE CONO DE REDUCCION PARA POZOS

CODO Ø 6" x 45°

ATRAQUE EN CONCRETO 1:2:3

1.00

0.30 .10

Ø >10"

.10

.10

0.40

.10Ø>10" .10

.10

Ø>10"

.10

VARIABLE

ATRAQUE EN CONCRETO 1:2:3

Escala: _________________________1:20

ANCLAJE PARA CONEXION DOMICILIARIA CON YEE VARIABLE ENTRE 10" Y 24"

De/4

+0.20

De + 0.20

De + 0.40

De + 0.40

De

Di

De + 0.40

Escala: ____________1:20

TUBERIA SIN ATRAQUE

BASE GRANULADA

CONCRETO DE 2.000 P.S.I.

COMPACTADO

RELLENO SELECCIONADO

1.2000

1.7200

SUPERFICIE CON FRISO

SUPERFICIE SIN FRISO

MORTERO 1:2

FRISO e= 0.02 M.

PLANTA POZO

Escala: ________1:20

0.2600

0.60000.6000 0.2597

.10

Ø 6"

.10

CONCRETO f'c= 3000 p.s.i

REFUERZO: A-37

CONCRETO : 3000 psi (f'c=210 K/cm²)

ESPECIFICACIONES

DE LA TUBERIA PREFAFRICADA

RELLENO DE BASE PARA LA INTALACION

MURO DE LADRILLO

CUBIERTA PARA POZOS

20 O 3/8" L=.70

(INCLUYE TRASLAPO DE .30 M)

1 O 1/2" L=3.05

CORTE

Escala: _1:20

ESCALONES 3/4"

0.2600

0.2000

VARIABLE VARIABLE

1.7200

RELLENO CUMUN COMPACTO

LINEA DE EXCAVACION

RASANTE

COTA CLAVE DE LA TUBERIA MAS ALTA

ALTURA MAXIMA FRISO INTERIOR=

DE INSPECCION

DETALLES BASE Y CAÑUELA PARA POZOS

CORTE: A-A

Escala: ________1:20

DE LA TUBERIA PREFAFRICADA

RELLENO DE BASE PARA LA INTALACION

D

DETALLE ESCALERA DE POZOS

0.6000 0.6000

0.2000

0.8038

0.2595 0.6005 0.2600

0.7034

0.6000

0.2000

0.34 APROX.

HUECOS PARA VENTILACION O 3/4"

0.2009

A LA VISTA

SUPERFICIE DEL LADRILLO

3000 p.s.i.

ANILLO EN CONCRETO

MORTERO 1:3

TAPA EN H.F.

TIPO PESADO O .65

ESCALONES 3/4"

1.2000

0.2613

0.2000

0.5987 0.5607

0.6803 0.2600

0.5611

Escala: ________1:20

TAPA EN H.F.

1 Cm.

JUNTA MINIMA

.MORTERO 1:2

FRISO INTERIOR 2 Cm

L=1.50 C/.34 aprox.

ESCALON METALICO O 3/4"

0.2600

0.2600 1.2000

MURO DE LADRILLO

MORTERO 1:2

D

A

1 Cm.

JUNTA MINIMA

CONCRETO 1:2:3 f'c= 3000 psi.

De + 0.40

De/2

+0.20

Di

De

ATRAQUE TOTAL

PERO MENOR DE 25%

MAYOR O IGUAL A 20%

0.80

PERO MENOR DE 20%

MAYOR O IGUAL A 15%

1 MODULO C/4.00 MTS.0.80

COMPACTADO

RELLENO SELECCIONADO

BASE GRANULADA

CONCRETO DE 2.000 P.S.I.

27" -- 30"

0.25

0.2005

0.2005

0.2512

m

Ø

a

e

0.2005

0.2005

0.92

3

ATRAQUE TUBERIA

PENDIENTE

MENOR A 9%

MAYOR O IGUAL A 9%

PERO MENOR DE 15%

SIN ATRAQUE

1 MODULO C/6.00 MTS.

ATRAQUE

LINEA DE EXCAVACION

RELLENO CUMUN COMPACTO

RASANTE

DIMENSIONES PARA CABEZAL

1.40

0.95

1.15

0.85

21" -- 27"

0.80

1.10

0.90

1.00

16" -- 20"

0.60

0.90

0.70

0.80

12" -- 14"

0.40

0.70

0.55

0.55

8" -- 10"

0.30

0.60

0.45

0.50

1:2:3

concreto

m

m

e

a

DIAMETRO

A

A

CORTE A-A

PLANTA

ALZADA

Escala: ____________1:20

DETALLE CABEZAL DE DESCARGA

30°

30°

POZOS CON PROFUNDIDAD

MAYOR A 1.80m.

0.2600

0.2000

0.0672

O s/2

CANTIDADES DE OBRA PARA POZOS

0.65

---

---

0.14

10.6

0.28

218

0.42

3.77

0.42

3.77

0.65

0.41

27

---

---

---

---

MENOR IGUAL A 1.80m.

POZOS CON PROFUNDIDADESUNIDADI T E M

Und.

M.

Und.

M.

Kg.

M.

Kg.

M.

M

(0.07 x 0.12 x 0.25)

LADRILLO TOLETE

MORTERO 1:3

CUERPO DEL POZO (1 ML)

(0.07x0.12 x 0.25)

LADRILLO TOLETE

MORTERO 1:3

CONO DE REDUCCION

HIERRO A-37

CONCRETO 1: 2: 3

ANILLO

HIERRO A-37

CONCRETO 1:2:3

PLACA

PARA BASE Y CAÑUELA

CONCRETO 1:2:3

CONTIENE: DIBUJÓ:

1_20ESCALA:

PROYECTO: PLANO No.:

DE:

6SFECHA:

:ARCHIVO

RED DEALCANTARILLADO

JUNIO DE 2015

OBSERVACIONES:

OCV.

13S

ADMINISTRACION MUNICIPALSAN JUAN DE GIRON

HECTOR JOSUE QUINTEROAlcalde 2011-2015

DETALLES DE POZO

DISEÑÓ Y CALCULÓ: REVISÓ Y APROBÓ:Vo.Bo.

CESAR AUGUSTO REYES RODRIGUEZINGENIERO CIVIL. MP.68202167467 STD.

SECRETARIA DE INFRAESTRUCTURA

SAN JUAN DE GIRON

CONSTRUCCION RED DE ALCANTARILLADO SANITARIO

Y PLANTA DE TRATAMIENTO DE AGUAS RESIDUALESBARRIO VILLA DEL SOL