S10 Empresa no registrada Obra CONST. DE PAVIMENTO Y VEREDAS EN LA 1°, 2° Y 3° CUADRA DEL JR. SAN AGUSTIN Y EL PERIME Fórmula PAVIMENTO RIGIDO Cliente MUNICIPALIDAD DISTRITAL DE SAISA Departament AYACUCHO Item Descripción Total 01.01.00 OBRAS PROVISIONALES 3000 01.02.00 OBRAS PRELIMINARES 1554.08 01.03.00 MOVIMIENTO DE TIERRAS 26851.17 01.04.00 PAVIMENTO DE CONCRETO 91827.09 01.05.00 CANALETA PLUVIAL 24227.29 01.06.00 VEREDAS 59781.64 03.00.00 ENSAYOS 04.00.00 FLETE 10825.95 218067.22 COSTO DIRECTO 219,864.58 GASTOS GENERALES ( 8% ) 17,589.17 UTILIDAD ( 6% ) 13191.87 SUB TOTAL 250645.62 IGV 45116.21 TOTAL GENERAL 295761.83 SON : DOSCIENTOS NOVENTINUEVE MIL OCHOCIENTOS SETENTITRES Y 30/100 NUEVOS SOLES

Upload: alejandro-vilcas

Post on 09-Apr-2016

3 views

Category:

Documents


0 download

DESCRIPTION

ejemplo de cronograma

TRANSCRIPT

S10Empresa no registrada

Obra CONST. DE PAVIMENTO Y VEREDAS EN LA 1°, 2° Y 3° CUADRA DEL JR. SAN AGUSTIN Y EL PERIMETRO DE LA PLAZA DE ARMAS DEL DIST. DE SAISA, PROV. DE LUCANAS-AYACUCHO

Fórmula PAVIMENTO RIGIDOCliente MUNICIPALIDAD DISTRITAL DE SAISADepartament AYACUCHO

Item Descripción Total01.01.00 OBRAS PROVISIONALES 300001.02.00 OBRAS PRELIMINARES 1554.0801.03.00 MOVIMIENTO DE TIERRAS 26851.1701.04.00 PAVIMENTO DE CONCRETO 91827.0901.05.00 CANALETA PLUVIAL 24227.2901.06.00 VEREDAS 59781.6403.00.00 ENSAYOS04.00.00 FLETE 10825.95

218067.22COSTO DIRECTO 219,864.58GASTOS GENERALES ( 8% ) 17,589.17UTILIDAD ( 6% ) 13191.87SUB TOTAL 250645.62IGV 45116.21TOTAL GENERAL 295761.83

SON : DOSCIENTOS NOVENTINUEVE MIL OCHOCIENTOS SETENTITRES Y 30/100 NUEVOS SOLES

CONST. DE PAVIMENTO Y VEREDAS EN LA 1°, 2° Y 3° CUADRA DEL JR. SAN AGUSTIN Y EL PERIMETRO DE LA PLAZA DE ARMAS DEL DIST. DE SAISA, PROV. DE LUCANAS-AYACUCHO

CRONOGRAMA DE EJECUCION VALORIZADO

OBRA: CONST. DE PAVTO. Y VEREDAS EN LA 1°, 2° Y3° CUDR. DEL JR. SAN AGUSTIN Y EL PERMT. DE LA PLAZA DE ARMAS DEL DIST. DE SAISA

UBICACIÓN: DEPT. : AYACUCHO DISTRITO : SAISA

PROV. : LUCANAS LUGAR : SAISA

EPOCA DE EJECUCION : ABRIL A DICIEMBRE

Nº DESCRIPCION DE PARTIDAS PRESTO. PRIMER MES SEGUNDO MES TERCER MES

1 PAVIMENTACION DE CALLES

1.1 OBRAS PROVISIONALES 3000 3,000.00

2 OBRAS PRELIMINARES 1554.08 777.04 777.04

3 MOVIMIENTO DE TIERRAS 26851.17 5,370.23 5,370.23 5,370.23 5,370.23 5,370.23

4 PAVIMENTO DE CONCRETO 91827.09 11,478.39 11,478.39 11,478.39 11,478.39 11,478.39 11,478.39 11,478.39 11,478.39

5 CANALETA PLUVIAL 24227.29 4,845.46 4,845.46 4,845.46 4,845.46 4,845.46

6 VEREDAS 59781.64 9,963.61 9,963.61 9,963.61 9,963.61 9,963.61

7 FLETE 10825.95 5,412.98 5,412.98

8 LIMPIEZA Y ENTREGA DE OBRA

COSTO DIRECTO TOTAL 218,067.22 8,412.98 777.04 6,147.27 16,848.62 22,261.60 21,694.08 31,657.68 26,287.45 26,287.45 26,287.45 21,441.99

GASTOS GENERALES 15,264.71 588.91 54.39 430.31 1,179.40 1,558.31 1,518.59 2,216.04 1,840.12 1,840.12 1,840.12 1,500.94

UTILIDAD 10,903.36 420.65 38.85 307.36 842.43 1,113.08 1,084.70 1,582.88 1,314.37 1,314.37 1,314.37 1,072.10

IGV (18%) 43,962.35 1,696.06 156.65 1,239.29 3,396.68 4,487.94 4,373.53 6,382.19 5,299.55 5,299.55 5,299.55 4,322.71

TOTAL GENERAL 288,197.64 11,118.59 1,026.94 8,124.24 22,267.14 29,420.92 28,670.89 41,838.80 34,741.50 34,741.50 34,741.50 28,337.74

PORCENTAJE SEMANAL 100.00% 3.86% 0.36% 2.82% 7.73% 10.21% 9.95% 14.52% 12.05% 12.05% 12.05% 9.83%

CRONOGRAMA DE EJECUCION VALORIZADO

TERCER MES TOTAL

3,000.00

1,554.08

26,851.17

91,827.09

24,227.29

9,963.61 59,781.64

10,825.95

0.00

9,963.61 218,067.22

697.45 15,264.71

498.18 10,903.36

2,008.66 43,962.35

13,167.90 288,197.64

4.57% 100%