CONJUNTO MULTIFAMILIAR SCALA 25
INTERVENTORÍA FINAL DE OBRA
ACTA No. 16 – ACOMETIDA RED ELÉCTRICA
JULIO – SEPTIEMBRE 2010
![Page 2: CONJUNTO MULTIFAMILIAR SCALA 25 INTERVENTORÍA FINAL DE OBRA ACTA No. 16 – ACOMETIDA RED ELÉCTRICA JULIO – SEPTIEMBRE 2010](https://reader035.vdocumento.com/reader035/viewer/2022070416/5665b49a1a28abb57c929392/html5/thumbnails/2.jpg)
IMÁGENES ACTA No. 16 – ACOMETIDA RED ELÉCTRICA
CÁMARA (CRA. 52) ACOMETIDA AL EDIFICIO Y PLAQUETA TAPA
![Page 3: CONJUNTO MULTIFAMILIAR SCALA 25 INTERVENTORÍA FINAL DE OBRA ACTA No. 16 – ACOMETIDA RED ELÉCTRICA JULIO – SEPTIEMBRE 2010](https://reader035.vdocumento.com/reader035/viewer/2022070416/5665b49a1a28abb57c929392/html5/thumbnails/3.jpg)
IMÁGENES ACTA No. 16 – ACOMETIDA RED ELÉCTRICA
ACOMETIDA PRINCIPALBAJADA A SUBESTACIÓN
![Page 4: CONJUNTO MULTIFAMILIAR SCALA 25 INTERVENTORÍA FINAL DE OBRA ACTA No. 16 – ACOMETIDA RED ELÉCTRICA JULIO – SEPTIEMBRE 2010](https://reader035.vdocumento.com/reader035/viewer/2022070416/5665b49a1a28abb57c929392/html5/thumbnails/4.jpg)
IMÁGENES ACTA No. 16 – ACOMETIDA RED ELÉCTRICA
ACOMETIDA EN EL SÓTANO HACIA LA SUBESTACIÓN
![Page 5: CONJUNTO MULTIFAMILIAR SCALA 25 INTERVENTORÍA FINAL DE OBRA ACTA No. 16 – ACOMETIDA RED ELÉCTRICA JULIO – SEPTIEMBRE 2010](https://reader035.vdocumento.com/reader035/viewer/2022070416/5665b49a1a28abb57c929392/html5/thumbnails/5.jpg)
IMÁGENES ACTA No. 16 – ACOMETIDA RED ELÉCTRICA
DETALLES A CARGO DE LA CONSTRUCTORA
LAS NORMAS EXIGEN EL PINTAR LA TOTALIDAD DE LA TUBERÍA EN COLOR NARANJA Y NO SEGMENTADA