CALCULO DEL FLETE GOBIERNO REGIONAL DE ANCASH OBRA : UBICACIÓN : ANCASH - ANTONIO RAYMONDI - LLAMELLIN 1.- DATOS GENERALES A.- POR PESO MATERIALES UNIDAD CANTIDAD PESO TOTAL ALAMBRE NEGRO RECOCIDO # 16 kg 529.69 1.00 529.69 ALAMBRE NEGRO RECOCIDO # 8 kg 151.58 1.00 151.58 CLAVOS PARA MADERA kg 231.20 1.00 231.20 CLAVOS PARA CEMENTO C/C 3" u 2.40 0.02 0.05 POLEA METALICA DE DIAMETRO 3" X 1/2" u 4.00 2.00 8.00 GIGANTOGRAFIA u 1.00 20.00 20.00 GRAPA ACERADA DE 1" kg 0.32 1.00 0.32 GRAPA DE ACERO D=1 1/2'' u 342.00 1.00 342.00 GRAPA DE ACERO D=1/2'' u 500.00 0.80 400.00 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 6,870.89 1.00 6,870.89 COMPUERTA METALICA T/IZAJE (0.20 x 0.30) H=0 u 1.00 30.00 30.00 GUIA LENTA m 41.53 0.02 0.83 CEMENTO PORTLAND TIPO I (42.5 kg) bls 1,947.89 42.50 82,785.33 VALVULA COMPUERTA DE BRONCE 6" u 8.00 15.00 120.00 CONO DE REBOSE 4" u 8.00 12.00 96.00 FULMINANTE COMUN # 6 DE 35 mm pza 61.25 0.50 30.63 DINAMITA 60%-65% kg 10.93 1.00 10.93 YESO EN BOLSAS DE 25 kg bls 76.78 25.00 1,919.50 CANASTILLA DE BRONCE D=3" u 8.00 12.00 96.00 THINER gal 5.02 4.00 20.08 BARRENO OCTOGONAL 7/8"X3 pza 0.18 30.00 5.40 ADITIVO IMPERMEABILIZANTE MORTERO CONCRETO C kg 58.90 1.00 58.90 CABLE DE ACERO D=5/8'' TIPO BOA 6x19 m 262.50 30.00 7,875.00 CABLE DE ACERO D=3/8'' m 577.50 25.00 14,437.50 RIEL DE FIERRO ASME 60 (60 LB/YD) m 24.00 30.00 720.00 ANILLO DE CAUCHO D=200 mm ISO MODELO 3s NEGR u 419.44 1.00 419.44 DRISSA DE NYLON DE 1/4" m 21.00 12.00 252.00 TAPA SANITARIA METALICA 0.70 x 0.70 u 1.00 20.00 20.00 IMPERMEABILIZANTE gal 2.84 4.00 11.36 LIJA u 2.01 0.20 0.40 BOMBA MANUAL PARA PRUEBA DE TUBERIA hm 15.79 20.00 315.80 SILLA DE CAMBIO DE F°G° (0.20x0.25x3/16'') u 8.00 50.00 400.00 CASETA Y ALMACEN glb 1.00 500.00 500.00 CORDEL m 12.34 0.01 0.12 REGLA DE MADERA p2 0.63 12.00 7.56 REGLA GRADUADA I/ACCESOR Y PINTURA u 1.00 12.00 12.00 ROMPE AGUA EXPANDITE SUPERCAST REAGUARD 200m m 88.83 12.00 1,065.96 MADERA TORNILLO p2 1,717.78 12.00 20,613.36 MADERA DE EUCALIPTO p2 294.34 12.00 3,532.08 COMPUERTA METALICA T/CANAL (0.40 x 0.30) H=0 u 1.00 40.00 40.00 MADERA PINO (REGLAS) p2 3.00 12.00 36.00 MADERA DE EUCALIPTO 4" X 5m u 8.00 12.00 96.00 MADERA DE EUCALIPTO 4" X 3m u 10.00 12.00 120.00 MADERA PARA ENCOFRADO p2 1,130.53 12.00 13,566.36 ESTACA DE MADERA EUCALIPTO DE 1"x1"x30 cm u 124.01 0.30 37.20 ESTACAS DE TOPOGRAFIA pza 7.80 0.30 2.34 TRIPLAY DE 19 mm pl 88.55 20.00 1,771.00 PINTURA ESMALTE SINTETICO gal 32.39 4.00 129.56 PINTURA ANTICORROSIVA gal 0.88 4.00 3.52 CALAMINA GALVANIZADA 1.83x0.83x0.30MM pl 18.00 15.00 270.00 CAJA METAL PARA INDICADOR NIVEL u 1.00 1.00 1.00 TUBO FIERRO GALVANIZADO ESTANDAR ISO-I 1" m 7.71 12.00 92.52 TUBO FIERRO GALVANIZADO ESTANDAR ISO-I 1 1/2 m 7.71 12.00 92.52 NIPLE DE FºGº DE 3" u 16.00 1.00 16.00 UNION UNIVERSAL 2" u 2.00 3.00 6.00 UNION UNIVERSAL 3" u 8.00 3.00 24.00 ALAMBRE GALBANIZADO CON PUAS rll 0.32 30.00 9.60 ABRAZADERA HDPE-PVC 160MM u 20.00 50.00 1,000.00 LUBRICANTE gal 4.19 4.00 16.76 UNION SIMPLE u 8.00 2.00 16.00 FLOTADOR DE BRONCE DE 5" u 1.00 1.00 1.00 ABRAZADERA CON PLATINA 6'' x 1/16'' u 250.00 5.00 1,250.00 PERNO CON HUACHA D=3/8''x1 1/2'' u 250.00 3.00 750.00 VALVULA COMPUERTA TIPO MAZZA A-7.5 (C-105) 4 u 12.00 4.00 48.00 AMPLIACION Y MEJORAMIENTO DEL CANAL DE LLULLUCA, DISTRITO DE LLAMELLIN, PROVINCIA DE ANTONIO RAIMONDI, REGION ANCASH PESO UNITARIO

Upload: vicente-mateo-cerda-villar

Post on 10-Nov-2014

34 views

Category:

Documents


11 download

TRANSCRIPT

Page 1: Calculo de Flete Llama

CALCULO DEL FLETE GOBIERNO REGIONAL DE ANCASH

OBRA :UBICACIÓN : ANCASH - ANTONIO RAYMONDI - LLAMELLIN

1.- DATOS GENERALES

A.- POR PESO

MATERIALES UNIDAD CANTIDAD PESO TOTAL

ALAMBRE NEGRO RECOCIDO # 16 kg 529.69 1.00 529.69 ALAMBRE NEGRO RECOCIDO # 8 kg 151.58 1.00 151.58 CLAVOS PARA MADERA kg 231.20 1.00 231.20 CLAVOS PARA CEMENTO C/C 3" u 2.40 0.02 0.05 POLEA METALICA DE DIAMETRO 3" X 1/2" u 4.00 2.00 8.00 GIGANTOGRAFIA u 1.00 20.00 20.00 GRAPA ACERADA DE 1" kg 0.32 1.00 0.32 GRAPA DE ACERO D=1 1/2'' u 342.00 1.00 342.00 GRAPA DE ACERO D=1/2'' u 500.00 0.80 400.00 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 6,870.89 1.00 6,870.89 COMPUERTA METALICA T/IZAJE (0.20 x 0.30) H=0. u 1.00 30.00 30.00 GUIA LENTA m 41.53 0.02 0.83 CEMENTO PORTLAND TIPO I (42.5 kg) bls 1,947.89 42.50 82,785.33 VALVULA COMPUERTA DE BRONCE 6" u 8.00 15.00 120.00 CONO DE REBOSE 4" u 8.00 12.00 96.00 FULMINANTE COMUN # 6 DE 35 mm pza 61.25 0.50 30.63 DINAMITA 60%-65% kg 10.93 1.00 10.93 YESO EN BOLSAS DE 25 kg bls 76.78 25.00 1,919.50 CANASTILLA DE BRONCE D=3" u 8.00 12.00 96.00 THINER gal 5.02 4.00 20.08 BARRENO OCTOGONAL 7/8"X3 pza 0.18 30.00 5.40 ADITIVO IMPERMEABILIZANTE MORTERO CONCRE kg 58.90 1.00 58.90 CABLE DE ACERO D=5/8'' TIPO BOA 6x19 m 262.50 30.00 7,875.00 CABLE DE ACERO D=3/8'' m 577.50 25.00 14,437.50 RIEL DE FIERRO ASME 60 (60 LB/YD) m 24.00 30.00 720.00 ANILLO DE CAUCHO D=200 mm ISO MODELO 3s N u 419.44 1.00 419.44 DRISSA DE NYLON DE 1/4" m 21.00 12.00 252.00 TAPA SANITARIA METALICA 0.70 x 0.70 u 1.00 20.00 20.00 IMPERMEABILIZANTE gal 2.84 4.00 11.36 LIJA u 2.01 0.20 0.40 BOMBA MANUAL PARA PRUEBA DE TUBERIA hm 15.79 20.00 315.80 SILLA DE CAMBIO DE F°G° (0.20x0.25x3/16'') u 8.00 50.00 400.00 CASETA Y ALMACEN glb 1.00 500.00 500.00 CORDEL m 12.34 0.01 0.12 REGLA DE MADERA p2 0.63 12.00 7.56 REGLA GRADUADA I/ACCESOR Y PINTURA u 1.00 12.00 12.00 ROMPE AGUA EXPANDITE SUPERCAST REAGUAR m 88.83 12.00 1,065.96 MADERA TORNILLO p2 1,717.78 12.00 20,613.36 MADERA DE EUCALIPTO p2 294.34 12.00 3,532.08 COMPUERTA METALICA T/CANAL (0.40 x 0.30) H=0 u 1.00 40.00 40.00 MADERA PINO (REGLAS) p2 3.00 12.00 36.00 MADERA DE EUCALIPTO 4" X 5m u 8.00 12.00 96.00 MADERA DE EUCALIPTO 4" X 3m u 10.00 12.00 120.00 MADERA PARA ENCOFRADO p2 1,130.53 12.00 13,566.36 ESTACA DE MADERA EUCALIPTO DE 1"x1"x30 cm u 124.01 0.30 37.20 ESTACAS DE TOPOGRAFIA pza 7.80 0.30 2.34 TRIPLAY DE 19 mm pl 88.55 20.00 1,771.00 PINTURA ESMALTE SINTETICO gal 32.39 4.00 129.56 PINTURA ANTICORROSIVA gal 0.88 4.00 3.52 CALAMINA GALVANIZADA 1.83x0.83x0.30MM pl 18.00 15.00 270.00 CAJA METAL PARA INDICADOR NIVEL u 1.00 1.00 1.00 TUBO FIERRO GALVANIZADO ESTANDAR ISO-I 1" m 7.71 12.00 92.52 TUBO FIERRO GALVANIZADO ESTANDAR ISO-I 1 1/ m 7.71 12.00 92.52 NIPLE DE FºGº DE 3" u 16.00 1.00 16.00 UNION UNIVERSAL 2" u 2.00 3.00 6.00 UNION UNIVERSAL 3" u 8.00 3.00 24.00 ALAMBRE GALBANIZADO CON PUAS rll 0.32 30.00 9.60 ABRAZADERA HDPE-PVC 160MM u 20.00 50.00 1,000.00 LUBRICANTE gal 4.19 4.00 16.76 UNION SIMPLE u 8.00 2.00 16.00 FLOTADOR DE BRONCE DE 5" u 1.00 1.00 1.00 ABRAZADERA CON PLATINA 6'' x 1/16'' u 250.00 5.00 1,250.00 PERNO CON HUACHA D=3/8''x1 1/2'' u 250.00 3.00 750.00 VALVULA COMPUERTA TIPO MAZZA A-7.5 (C-105) 4 u 12.00 4.00 48.00

AMPLIACION Y MEJORAMIENTO DEL CANAL DE LLULLUCA, DISTRITO DE LLAMELLIN, PROVINCIA DE ANTONIO RAIMONDI, REGION ANCASH

PESO UNITARIO

Page 2: Calculo de Flete Llama

PESO TOTAL 163,305.287

Page 3: Calculo de Flete Llama

B.- POR VOLUMEN

AGREGADO

DESCRIPCION UNIDAD SIN IGV

ARENA FINA m3 7.08TIERRA CERNIDA m3 185.05PIEDRA CHANCADA DE 3/4" m3 0.42PIEDRA GRANDE DE 12" MAX m3 32.99PIEDRA SELECCIONADA 6" m3 1.23PIEDRA SEMILABRADA m3 2.42ARENA GRUESA m3 121.44PIEDRA ZARANDEADA DE 1/2" m3 64.39PIEDRA ZARANDEADA DE 3/4" m3 55.94

VOLUMEN TOTAL (AGREGADOS) 470.960 DESDE CANTERA LLULLUCAVOLUMEN TOTAL (PIEDRA) 1.230 DE INMEDIACIONES DE LA OBRACAPACIDAD DEL CAMION ( M3 ) 6.000 NUMERO DE VIAJES 78.493 REDONDEO NUMERO DE VIAJES 78.000

EN TUBERIA UNIDAD DE ( 2.20 m. * 3.00 m. ) DE CARROCERIA CON H = 1.50 m.

CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML ml No PESO POR TUBERIAtuberia tubos KG No VIAJES

TUBERIA HDPE ISO-4427 PN-10.0 160MM 262.50 5 53.00 60.00 1.00TUBO PVC D=200 mm -S-13.3-ISO-4435-UF 2,541.33 5 509.00 30.00 6.00

2,803.83NUMERO TOTAL DE VIAJES 7.00REDONDEO 7.00PESO TUBERIA POR UNIDAD 0.00

2.- FLETE TERRESTRE

MATERIALES UNIDAD DE TRANSPORTE AGREGADOSDESDE CANTERA LLULLUCA DESDE CANTERA LLULLUCAUNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTECAPACIDAD DEL CAMION ( M3 ) 6.00 CAPACIDAD DEL CAMION ( M3 ) 6.00COSTO POR VIAJE S/. 1,000.00 COSTO POR VIAJE S/. 1000.00CAPACIDAD DEL CAMION ( KG ) 9,600.00 CAPACIDAD DEL CAMION ( KG ) 9,600.00FLETE POR KG 0.46 166.67

160,000.00

AFECTO IGV SIN IGV FLETE POR PESO =FLETE POR PESO 74,957.13 Peso Total * Flete por PesoFLETE POR VOLUMEN FLETE POR VOLUMEN =

AGREGADOS 78,000.00 No Viajes * Costos por ViajeTUBERIA 7,000.00

COSTO TOTAL FLETE TERR. 82,000.00 78,000.00

AFECTOS SIN IGV

Page 4: Calculo de Flete Llama

3.- FLETE RURALMATERIALES Y AGREGADOS DESDE PUNTO DE DESCARGA - A OBRA

Costo de Transporte por Viaje Costos de Transporte por Viaje / acémilaAcémila S/. 2.00 Arena Gruesa - P. Zaran. 1.74Cemento S/. 2.00 Piedras de la zona 1.00

Cantidad Unidades Capacidad de Número de Flete node Carga Carga Viajes Afecto a IGV

Número Bolsas de Cemento 1,947.89 1 1.00 1,948.00 3,896.00Peso Resto de Materiales 163,305.29 1 50.00 3,266.00 6,532.00Agregados Total en KG. 847,728.00 1 50.00 16,955.00 29,535.61Piedra Total en KG. (de la zona) 1,968.00 1 50.00 39.40 39.40

El traslado de materiales (agregados) desde Llulluca obra 3.0 km promedio.

* COSTO TOTAL DEL FLETE EN ACEMILA S/. 40,000.00* El costo de Flete Rural que se menciona es el 40% del total, lo demas será asumido por la comunidad de Llulluca

RESUMEN FLETE TOTAL

FLETE AFECTO SIN TOTAL DE IGV IGV FLETE

FLETE TERRESTRE 82,000.00 78,000.00 160,000.00

FLETE EN ACEMILA ( RURAL ) 40,000.00 40,000.00

FLETES TOTALES S/. 82,000.00 118,000.00 200,000.00