King Abdullah Petrolium Studies And Research Center (KAPSARC – Iconic Project) /

Riyadh - KSA

Saudi Landscaping and Contracting Company (SALCO)

SALCO Scope

Hardscape

Landscape

Softscape Irrigation

SALCO Tasks & Milestone based on DSI time schedule

Hardscape (%) Irrigation (%) Softscape (%) Area Handed Over by DSI Area handed over by SALCO

Area 1 65.50 (m2) 23.70 19.70 1-July-13 Jan-13

51.83 (Lm)

Area 2 1.66 9.00 11.33 15 juin-13 August-13

Area 3 7.62 13.50 10.23 July-13 Sep-13

Area 4 0.00 2.50 1.77 30 Juin-13 Sep-13

Area 5 0.00 0.00 0.00 30-Apr-13 ------

Area 6 0.00 1.75 1.27 15-July-13 15-August-13

Area 7 4.46 5.22 4.23 15-Juin-13 30-July-13

Area 8 4.66 21.93 23.10 15-Juin-13 15-October-13

Area 9 16.08 (m2) 22.40 28.34 15 Juin-13 July-13

Area 1048.16 (Lm)

0.56 0.00 0.00 15-Juin-13 30-July-13

* All Starting date for SALCO scope are based on DSI and sub-contractors schedule (MEP, FCC , etc …)* Interface pending issues between MEP & SBM are not yet finished and we still waiting for their response* After installation of the Irrigation System, SALCO needs 35 to 45 days to make the final arrangement of the Controlling System

SALCO Materials

Hardscape

Softscape

On Site Construction

Major Site Construction faced

- LV installation; specially in Zone 9

- Underground Utilities

- Deep Excavation around the podium walls

- Scaffold

General Recommendations

- Prioritize the areas

- Efficient Coordination

- Start to provide access around the Iconic area