Control de Partida

TRANSCRIPT

ENCOFRADO DE VERTICALES

Personas 11 105.60

h día 9.6

Dia de obra 1 2 3 4

hh 105.60 105.60 105.60 105.60

hh acum 105.60 211.20 316.80 422.40

met 135.21 142.43 120.50 101.94

met acum 135.21 277.64 398.14 500.08

Rend. Diario 0.78 0.74 0.88 1.04

Rend. Acum 0.78 0.76 0.80 0.84

Rend. Presup 1.00 1.00 1.00 1.00

Operario 6

Oficial 0

Peon 5

Total 11

Rendimiento 1.00 hh/m2

Jornada 9.60 horas/DIA

Cuadrilla Cantidad

Operario 6 57.60

Oficial 0 0.00

Peon 5 48.00

Total 105.60

Formación de

Cuadrilla

5 6 7 8 9 10 11

105.60 105.60 105.60 105.60 105.60 105.60 105.60

528.00 633.60 739.20 844.80 950.40 1056.00 1161.60

135.21 142.43 120.50 101.94 135.21 142.43 120.50

635.29 777.72 898.22 1000.16 1135.37 1277.80 1398.30

0.78 0.74 0.88 1.04 0.78 0.74 0.88

0.83 0.81 0.82 0.84 0.84 0.83 0.83

1.00 1.00 1.00 1.00 1.00 1.00 1.00

12 13 14 15 16 17 18

105.60 105.60 105.60 105.60 105.60 105.60 105.60

1267.20 1372.80 1478.40 1584.00 1689.60 1795.20 1900.80

101.94 135.21 142.43 120.50 101.94 135.21 142.43

1500.24 1635.45 1777.88 1898.38 2000.32 2135.53 2277.96

1.04 0.78 0.74 0.88 1.04 0.78 0.74

0.84 0.84 0.83 0.83 0.84 0.84 0.83

1.00 1.00 1.00 1.00 1.00 1.00 1.00

19 20 21 22 23 24 25

105.60 105.60 105.60 105.60 105.60 105.60 105.60

2006.40 2112.00 2217.60 2323.20 2428.80 2534.40 2640.00

120.50 101.94 135.21 142.43 120.50 101.94 135.21

2398.46 2500.40 2635.61 2778.04 2898.54 3000.48 3135.69

0.88 1.04 0.78 0.74 0.88 1.04 0.78

0.84 0.84 0.84 0.84 0.84 0.84 0.84

1.00 1.00 1.00 1.00 1.00 1.00 1.00

26 27 28 29 30 31 32

105.60 105.60 105.60 105.60 105.60 105.60 105.60

2745.60 2851.20 2956.80 3062.40 3168.00 3273.60 3379.20

142.43 120.50 101.94 135.21 142.43 120.50 101.94

3278.12 3398.62 3500.56 3635.77 3778.20 3898.70 4000.64

0.74 0.88 1.04 0.78 0.74 0.88 1.04

0.84 0.84 0.84 0.84 0.84 0.84 0.84

1.00 1.00 1.00 1.00 1.00 1.00 1.00

Metrado Partida

33 34 35 36 37 38 39

105.60 105.60 105.60 105.60 105.60 105.60 105.60

3484.80 3590.40 3696.00 3801.60 3907.20 4012.80 4118.40

135.21 142.43 120.50 101.94 135.21 142.43 120.50

4135.85 4278.28 4398.78 4500.72 4635.93 4778.36 4898.86

0.78 0.74 0.88 1.04 0.78 0.74 0.88

0.84 0.84 0.84 0.84 0.84 0.84 0.84

1.00 1.00 1.00 1.00 1.00 1.00 1.00

Dif Rend

Dif HH

Dif Soles

Metrado Partida 5000.8

LAST DAY Amortiguador Amortiguador Amortiguador Amortiguador

40 41 42 43 44

105.60 105.60 105.60 105.60 105.60

4224.00 4329.60 4435.20 4540.80 4646.40

101.94

5000.80 5000.80 5000.80 5000.80 5000.80

1.04

0.84 0.87 0.89 0.91 0.93

1.00 1.00 1.00 1.00 1.00

0.16 0.13 0.11 0.09 0.07 hh/m2

776.80 671.20 565.60 460.00 354.40 hh

S/.