PRESUPUESTO ADICIONAL DE OBRA N°01 (CONTRATISTA) ITEM COMPONENTE PRECIO 1 MURO SECO 20,710.11 2 SISTEMA DE DRENAJE SUBTERRANEO 6,332.78 3 CONSTRUCCION DE GADERIAS AV. HEROES SICAINOS 11,785.81 4 CONSTRUCCION DE SARDINEL SUMERGIDO 5,262.04 5 BADEN 1,464.08 6 ALCANTARILLADO PLUVIAL 40,983.15 7 ENSAYOS Y PRUEBAS 5,270.00 8 PAVIMENTACION 10,079.38 COSTO DIRECTO 101,887.35 GASTOS GENERALES 7% 7,132.11 UTILIDAD 3% 3,056.62 SUB TOTAL 112,076.08 IGV 18% 21,294.46 PRESUPUESTO TOTAL 133,370.54 PRESUPUESTO DEDUCTIVO DE OBRA N°01 (CONTRATISTA) ITEM COMPONENTE PRECIO 2 TRABAJOS PRELIMINARES 2,989.11 3 MOVIMIENTO DE TIERRAS 31,484.77 4 PAVIMENTOS FLEXIBLES 53,027.57 5 SARDINEL 10,826.92 6 DRENAJE PLUVIAL 4,422.43 COSTO DIRECTO 102,750.80 GASTOS GENERALES 7% 7,192.56 UTILIDAD 3% 3,082.52 SUB TOTAL 113,025.88 IGV 18% 20,344.66 PRESUPUESTO TOTAL 133,370.54

Upload: rcurasma

Post on 27-Sep-2015

219 views

Category:

Documents


1 download

DESCRIPTION

aDICIONAL DE oBRA

TRANSCRIPT

Hoja1PRESUPUESTO ADICIONAL DE OBRA N01 (CONTRATISTA)

ITEMCOMPONENTEPRECIO1MURO SECO20,710.112SISTEMA DE DRENAJE SUBTERRANEO6,332.783CONSTRUCCION DE GADERIAS AV. HEROES SICAINOS11,785.814CONSTRUCCION DE SARDINEL SUMERGIDO5,262.045BADEN1,464.086ALCANTARILLADO PLUVIAL40,983.157ENSAYOS Y PRUEBAS5,270.008PAVIMENTACION10,079.38

COSTO DIRECTO101,887.35GASTOS GENERALES 7%7,132.11UTILIDAD 3%3,056.62SUB TOTAL112,076.08IGV 18%21,294.46PRESUPUESTO TOTAL133,370.54

PRESUPUESTO DEDUCTIVO DE OBRA N01 (CONTRATISTA)

ITEMCOMPONENTEPRECIO2TRABAJOS PRELIMINARES2,989.113MOVIMIENTO DE TIERRAS31,484.774PAVIMENTOS FLEXIBLES53,027.575SARDINEL10,826.926DRENAJE PLUVIAL4,422.43

COSTO DIRECTO102,750.80GASTOS GENERALES 7%7,192.56UTILIDAD 3%3,082.52SUB TOTAL113,025.88IGV 18%20,344.66PRESUPUESTO TOTAL133,370.54