    TALLERSIMULACION Y ANALISIS

    COMPUTACIONAL

    Ph. D. Felipe CalizayaConsultor Intercade

    2

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    VnetPC es un programa numrico utilizado pararesolver problemas de ventilacin.

    Trabaja en computadores personales.

    Fuente: http://www.mvsengineering.com

    SIMULADORES DE VENTILACION

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    2/17

    2

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    3

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    8

    7

    6

    13

    12

    9

    1

    11

    2

    5

    4

    10

    3

    14

    4

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    PRACTICA 1: INFORMACION ADICIONAL

    600 m (2000 p)600 m

    30 m

    Muro flotante

    Talleres

    Exploracin

    Entrada

    Salida

    ReguladorR

    Frente activo

    Ventilador

    GE Exploracin

    Frentesactivos

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    3/17

    3

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    5

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Dimensiones de las galeras y recortes

    Entradas: Seccin: 14.8 x 13.1 p; K = 50 x E-10

    Salidas: Seccin: 13.1 x 13.1 pies; K = 50 x E-10

    Resistencias para controles de ventilacin

    Muros y puertas: 50 P.U.

    Muro flotante: 10 P.U.

    Ramales con caudales fijos

    Frentes de desarrollo (dos): 60,000 p3/min

    Estaciones de servicio (tres): 30,000 Recorte de exploracin (uno): 30,000

    PRACTICA 1: INFORMACION ADICIONAL

    6

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Figura 2. Curvas del ventilador Spendrup serie 244-147-880

    Caudal del aire (p3/min x 1000)

    Presin

    total(pulg.

    H2

    O)

    Po

    tenciaconsumida(BHP)

    116

    54

    3

    80%

    85%

    75%

    70%6

    5

    4

    32

    1

    21

    10

    9

    8

    7

    6

    5

    4

    3

    2

    1

    0

    0 50 100 150 200 250 300 350 400 450

    200

    400

    600

    800

    500

    CONE VP0

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    4/17

    4

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    7

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    PRACTICA 2: PRACTICAS DE SIMULACION

    Ramal Res, P.U.

    15-29 0.0037

    31-32 0.0037

    Ramal Res, P.U.

    35-35 0.0050

    33-16 0.0050

    Ramal 33-36: ltimo crucero. R = 0.0007 P.U.

    Ramal 29-37: Estacin de diamantina. R = 0.0007 P.U.

    29 30 31 32

    33 34 35 36

    37

    Zona proyectada

    Figura 4

    8

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Solucin

    1. Extienda la red de ventilacin

    2. Alimente al modelo con las nuevas resistenciasEjemplo: Ramal 15-29: R = 0.0037 P.U. (entrada)

    Ramal 33-16: R = 0.0050 P.U. (salida)

    Ramal 15-16: R = 50 P.U. (muro)

    29 30 31 32

    33 34 35 36

    37

    Zona proyectada

    PRACTICA 2: PRACTICAS DE SIMULACION

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    5/17

    5

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    9

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Rampa

    EntradaSalida

    Tajo 2Tajo 1

    LHD 1:

    354 kW

    LHD 2

    243 kW

    Jumbo:

    100 kW

    S-VHC:180 kW

    Mineral

    QT = 88 m3/s

    Ore-pass

    Qo = 21 m3/s Qo = 17 m3/s

    Qo = 15 m3/s

    Frente 1

    VENTILACION DE TAJOS ACTIVOS

    10

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Secuencia de actividades

    SECCION TRANSVERSAL

    Tajo endesarrollo

    Tajo enproduccin

    Tajo con rellenohidrulico

    Nivel de produccin

    Nivel de perforacin

    Extraccin delmineral

    Taladros al piso

    MINA BIG GOSSAN (INDONESIA)

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    6/17

    6

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    11

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Simulation Result

    12

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Simulation Result

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    7/17

    7

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    13

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    14

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    8/17

    8

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    15

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    16

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    9/17

    9

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    17

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    18

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    10/17

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    11/17

    11

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    21

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    22

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    12/17

    12

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    23

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    24

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    13/17

    13

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    25

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    26

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    El nivel ms activo es el nivel de produccin.

    La red muestra cuatro niveles de trabajo:

    Entradas

    Salidas

    Pozo 2

    Pozo 1N. deproduccin

    N. de reduccinN. de extraccin

    RED DE VENTILACION

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    14/17

    14

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    27

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Determinar el tamao del ventilador auxiliar para lassiguientes condiciones:

    Frente

    Qo= 40 k p3/minManga, L = 2000 pD = 42 pulg.

    L2

    La seccin de la galera es 16.4 x 18 pQT

    L1

    K (manga) = 16.2 x E-10R (acoples) = 30,000 P.U. HT = ? Q = ?

    UTILIZACION DEL PROGRAMA DuctSIM

    28

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    R (acoples) = 30,000 P.U.El sistema usa mangas con acoples cada 30 m.

    Resistencia de Acoples, P.U./100 pSOLUCION

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    15/17

    15

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    29

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Ser posible ventilar el frente de trabajo con unventilador de 150 kW?

    Frente5 x 5.5 m

    Ventilador auxiliar

    Ducto flexible, D = 1.2 m L2

    QT

    L3

    L1 = 1000 m

    Qo = 23 m3/s

    3

    DESARROLLO DE TUNELES LARGOS

    30

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Z1 = - 200 m

    td =21 C

    tw =12 C

    Pb = 108 kPa

    Caja (roca)80, 200 kW

    Diesel120, 325

    Cooler200, - 60

    Chancadora350, 160

    Banda350, 110

    L1 = 650 m

    Fuentes artificiales

    Otros datos generales: Rampa 5 x 5.5 m de seccin, L = 650 m

    tw = 32 c

    Ejemplo

    k = 4.8 W/m C

    = 2 m2/h; VRT = 50 C

    2

    3

    Z1 = - 300 mFuentes naturalesq

    Q = 40

    A = 27.5 m2; Per = 21 m

    APLICACION DE ClimSIM

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    16/17

    16

    INTERCADE

    CONSULTANCY & TRAINING

    www.intercade.org

    31

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Ejemplo:El sistema de ventilacin de la mina Santa Fe

    es representado por la siguiente red:

    Figura 1

    4

    2

    5

    3

    1

    Face 2

    6

    8

    9

    10

    7

    Intake Shaft

    50,000 cfm

    70,000 cfm

    APLICACION DE VnetPC- PRO

    32

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    Problema: Determinar la capacidad del ventiladoradecuado para desarrollar los primeros 1500 m delrecorte.

    Chimenea

    D = 4 m

    tw= 20 C

    Qt = 30 p3/s

    L1 = 1000 m

    Ducto d1= 1.2 m

    LT = 4000 m

    L1 = 1500 m

    XS = 5 x 5.5 m

    Ducto d2 = 1,0 min

    L2 = 500 m

    tw

    Qo = 20

    C 50 ppm CO

    p3/s

    28 C

    Recorte

    A

    Recorte

    B

    Ducto d2 = 1.0 mDucto d1 = 1.2 m

    ESQUEMA DEL PROYECTO PACUNI

  • 7/24/2019 248321 Taller Simulacionyanalisis Tallerparte1diap1 33

    17/17

    17

    INTERCADE www.intercade.org

    33

    Ph.D. Felipe Calizaya - [email protected] - Consultor Intercade

    2. Refrigerador: 100, -300

    Zona calurosa (VRT = 50 C

    1

    2

    3

    4

    1. Playa de acopio: 50, 200

    3. Fosa y tubera: 150, 100

    4. Equipos a diesel: 200, 250

    5 6

    5. Chancadora: 350, 150

    6. Banda transportadora:400, 150

    L1 = 1000 m

    L2 = 600 m

    Calor (kW)

    Distancia (m)

    FUENTES DE CALOR