  • 5/24/2018 2 Da Parcial de Costos

    1/15

    1.- EXCAVACION DE ZANJAS

    RENDIMIENTO 2.50 m3

    CAPATAZ = 0.10

    OPERARIO = 0.00

    OFICIAL = 0.00

    PEON = 1.00

    CAPATAZ = 0.10 x 8.00 = 0.3200 hh

    OPERARIO = 0.00 x 8.00 = 0.0000 hh

    OFICIAL = 0.00 x 8.00 = 0.0000 hh

    PEON = 1.00 x 8.00 = 3.2000 hh

    2.- SOLADO DE CONCRETO

    RENDIMIENTO 80.00 m2

    CAPATAZ = 0.10

    OPERARIO = 1.00

    OFICIAL = 1.00

    PEON = 4.00

    CAPATAZ = 0.10 x 8.00 = 0.0100 hh

    OPERARIO = 1.00 x 8.00 = 0.1000 hh

    OFICIAL = 1.00 x 8.00 = 0.1000 hh

    PEON = 4.00 x 8.00 = 0.4000 hh

    3.- ACERO EN COLUMNAS

    RENDIMIENTO 300.00 KG

    CAPATAZ = 0.10

    OPERARIO = 1.00

    OFICIAL = 1.00

    PEON = 0.00

    80.00

    2.50

    2.50

    2.50

    2.50

    80.00

    80.00

    80.00

  • 5/24/2018 2 Da Parcial de Costos

    2/15

    CAPATAZ = 0.10 x 8.00 = 0.0030 hh

    OPERARIO = 1.00 x 8.00 = 0.0270 hh

    OFICIAL = 1.00 x 8.00 = 0.0270 hh

    PEON = 0.00 x 8.00 = 0.0000 hh

    4.- CONCRETO EN ZAPATAS

    RENDIMIENTO 25.00 m3

    CAPATAZ = 0.20

    OPERARIO = 2.00

    OFICIAL = 2.00PEON = 4.00

    CAPATAZ = 0.20 x 8.00 = 0.0640 hh

    OPERARIO = 2.00 x 8.00 = 0.6400 hh

    OFICIAL = 2.00 x 8.00 = 0.6400 hh

    PEON = 4.00 x 8.00 = 1.2800 hh

    5.- ENCOFRADO EN COLUMNAS

    RENDIMIENTO 18.00 m2

    CAPATAZ = 0.10

    OPERARIO = 1.00

    OFICIAL = 1.00

    PEON = 2.00

    CAPATAZ = 0.10 x 8.00 = 0.0440 hh

    OPERARIO = 1.00 x 8.00 = 0.4440 hh

    OFICIAL = 1.00 x 8.00 = 0.4440 hh

    18.00

    18.00

    25.00

    25.00

    25.00

    25.00

    300.00

    300.00

    300.00

    300.00

  • 5/24/2018 2 Da Parcial de Costos

    3/15

    PEON = 2.00 x 8.00 = 0.8890 hh

    6.- CONCRETO EN COLUMNAS

    RENDIMIENTO 5.00 m3

    CAPATAZ = 0.20

    OPERARIO = 2.00

    OFICIAL = 2.00

    PEON = 6.00

    CAPATAZ = 0.20 x 8.00 = 0.3200 hh

    OPERARIO = 2.00 x 8.00 = 3.2000 hh

    OFICIAL = 2.00 x 8.00 = 3.2000 hh

    PEON = 6.00 x 8.00 = 9.6000 hh

    18.00

    18.00

    5.00

    5.00

    5.00

    5.00

  • 5/24/2018 2 Da Parcial de Costos

    4/15

    CAPATAZ = 0.3200

    OPERARIO = 0.0000

    OFICIAL = 0.0000

    PEON = 3.2000

    CAPATAZ = 0.0100

    OPERARIO = 0.1000

    OFICIAL = 0.1000

    PEON = 0.4000

  • 5/24/2018 2 Da Parcial de Costos

    5/15

    CAPATAZ = 0.0030

    OPERARIO = 0.0270

    OFICIAL = 0.0270

    PEON = 0.0000

    CAPATAZ = 0.0640

    OPERARIO = 0.6400

    OFICIAL = 0.6400

    PEON = 1.2800

    CAPATAZ = 0.0440

    OPERARIO = 0.4440

    OFICIAL = 0.4440

    PEON = 0.8890

  • 5/24/2018 2 Da Parcial de Costos

    6/15

    CAPATAZ = 0.3200

    OPERARIO = 3.2000

    OFICIAL = 3.2000

    PEON = 9.6000

  • 5/24/2018 2 Da Parcial de Costos

    7/15

    OBRA : EXAMEN 2013 - II

    PARTIDA: 1.- EXCAVACION DE ZANJAS

    UNIDAD : m3 RENDIMIENTO : COSTO UNITARIO : S/. 48.78

    1.- MATERIALES

    UND. CANT. P. UNIT PARCIAL TOTAL

    0.00

    2.- MANO DE OBRA

    No H-H J-H PARCIAL TOTAL

    HH 0.320 18.00 5.76

    HH 0.000 16.00 0.00

    HH 0.000 15.00 0.00

    HH 3.200 13.00 41.60

    47.36

    3.- EQUIPO

    No H-M A-H PARCIAL TOTAL

    1.42

    0.00

    0.00

    1.42

    .(1) S/. 0.00

    .(2) S/. 47.36

    .(3) S/. 1.42

    S/. 48.78

    OBRA : EXAMEN 2013 - II

    PARTIDA: 2.- SOLADO DE CONCRETO

    UNIDAD : m2 RENDIMIENTO : COSTO UNITARIO : S/. 23.75

    1.- MATERIALES

    UND. CANT. P. UNIT PARCIAL TOTALbolsas 0.28 22.00 6.16

    m2 0.10 50.00 5.00

    11.16

    2.- MANO DE OBRA

    No H-H J-H PARCIAL TOTAL

    HH 0.010 18.00 0.18

    DESCRIPCION

    CAPATAZ

    DESCRIPCION

    CAPATAZ

    OPERARIO

    OFICIAL

    PEON

    ANALISIS DE COSTOS UNITARIOS N 1

    DESCRIPCION

    DESCRIPCION

    HERRAMIENTAS 3% M.O.

    DESCRIPCIONCEMENTO

    HORMIGON

    TOTAL MATERIAL

    TOTAL MANO DE OBRA

    TOTAL EQUIPO

    COSTO UNITARIO

    ANALISIS DE COSTOS UNITARIOS N 2

  • 5/24/2018 2 Da Parcial de Costos

    8/15

    HH 0.100 16.00 1.60

    HH 0.100 15.00 1.50

    HH 0.400 13.00 5.20

    8.48

    3.- EQUIPO

    No H-M A-H PARCIAL TOTAL

    0.251.00 0.10 35.00 3.50

    0.12 3.00 0.36

    4.11

    .(1) S/. 11.16

    .(2) S/. 8.48

    .(3) S/. 4.11

    S/. 23.75

    OBRA : EXAMEN 2013 - II

    PARTIDA: 3.- ACERO EN COLUMNAS

    UNIDAD : KG RENDIMIENTO : COSTO UNITARIO : S/. 7.97

    1.- MATERIALES

    UND. CANT. P. UNIT PARCIAL TOTAL

    BLS 1.07 6.00 6.42

    m3 0.06 7.00 0.42

    6.84

    2.- MANO DE OBRA

    No H-H J-H PARCIAL TOTAL

    HH 0.003 18.00 0.05

    HH 0.027 16.00 0.43

    HH 0.027 15.00 0.41

    HH 0.000 13.00 0.00

    0.89

    3.- EQUIPO

    No H-M A-H PARCIAL TOTAL0.03

    Hm 0.05 4.00 0.21

    0.24

    .(1) S/. 6.84

    .(2) S/. 0.89

    TOTAL MATERIAL

    TOTAL MANO DE OBRA

    CIZALLA

    DESCRIPCIONHERRAMIENTAS 3% M.O.

    DESCRIPCION

    CAPATAZ

    OPERARIO

    OFICIAL

    PEON

    DESCRIPCION

    ACERO

    ALAMBRE

    TOTAL MATERIAL

    TOTAL MANO DE OBRA

    TOTAL EQUIPO

    COSTO UNITARIO

    ANALISIS DE COSTOS UNITARIOS N 3

    MEZCLADORA

    REGLAS DE MADERA

    OPERARIO

    OFICIAL

    PEON

    DESCRIPCION

    HERRAMIENTAS 3% M.O.

  • 5/24/2018 2 Da Parcial de Costos

    9/15

    .(3) S/. 0.24

    S/. 7.97

    OBRA : EXAMEN 2013 - II

    PARTIDA: 4.- CONCRETO EN ZAPATASUNIDAD : m3 RENDIMIENTO : COSTO UNITARIO : S/. 284.25

    1.- MATERIALES

    UND. CANT. P. UNIT PARCIAL TOTAL

    kg 8.00 22.00 176.00

    kg 0.57 45.00 25.65

    0.58 48.00 27.84

    229.49

    2.- MANO DE OBRA

    No H-H J-H PARCIAL TOTAL

    HH 0.064 18.00 1.15

    HH 0.640 16.00 10.24

    HH 0.640 15.00 9.60

    HH 1.280 13.00 16.64

    37.63

    3.- EQUIPO

    No H-M A-H PARCIAL TOTAL

    1.13

    Hm 0.32 35.00 11.20

    0.32 15.00 4.80

    17.13

    .(1) S/. 229.49

    .(2) S/. 37.63

    .(3) S/. 17.13

    S/. 284.25

    OBRA : EXAMEN 2013 - II

    PARTIDA: 5.- ENCOFRADO EN COLUMNASUNIDAD : m2 RENDIMIENTO : COSTO UNITARIO : S/. 69.74

    1.- MATERIALES

    UND. CANT. P. UNIT PARCIAL TOTAL

    kg 5.00 8.00 40.00

    kg 0.15 7.00 1.05

    0.30 6.00 1.80

    42.85

    TOTAL MATERIAL

    TOTAL MANO DE OBRA

    TOTAL EQUIPO

    COSTO UNITARIO

    DESCRIPCION

    HERRAMIENTAS 3% M.O.

    MEZCLADORA

    VIBRADOR

    DESCRIPCION

    CAPATAZ

    OPERARIO

    OFICIAL

    PEON

    ANALISIS DE COSTOS UNITARIOS N 4

    DESCRIPCION

    CEMENTO

    ARENA

    PIEDRA

    TOTAL EQUIPO

    COSTO UNITARIO

    ANALISIS DE COSTOS UNITARIOS N 5

    DESCRIPCION

    MADERA

    CLAVOS

    ALAMBRE

  • 5/24/2018 2 Da Parcial de Costos

    10/15

    2.- MANO DE OBRA

    No H-H J-H PARCIAL TOTAL

    HH 0.044 18.00 0.79

    HH 0.444 16.00 7.10

    HH 0.444 15.00 6.66

    HH 0.889 13.00 11.56

    26.11

    3.- EQUIPO

    No H-M A-H PARCIAL TOTAL

    0.78

    0.78

    .(1) S/. 42.85

    .(2) S/. 26.11

    .(3) S/. 0.78

    S/. 69.74

    OBRA : EXAMEN 2013 - II

    PARTIDA: 6.- CONCRETO EN COLUMNAS

    UNIDAD : m RENDIMIENTO : COSTO UNITARIO : S/. 467.71

    1.- MATERIALES

    UND. CANT. P. UNIT PARCIAL TOTAL

    BOLS 8.00 22.00 176.00

    m3 0.58 45.00 26.10

    m3 0.60 48.00 28.80

    230.90

    2.- MANO DE OBRA

    No H-H J-H PARCIAL TOTAL

    HH 0.320 18.00 5.76

    HH 3.200 16.00 51.20

    HH 3.200 15.00 48.00

    HH 9.600 13.00 124.80

    229.76

    3.- EQUIPO

    No H-M A-H PARCIAL TOTAL

    6.89

    Hm 0.08 2.00 0.16

    7.05

    .(1) S/. 230.90

    .(2) S/. 229.76

    DESCRIPCION

    CAPATAZ

    OPERARIO

    OFICIAL

    PEON

    DESCRIPCION

    HERRAMIENTAS 3% M.O.

    TOTAL MATERIAL

    TOTAL MANO DE OBRA

    TOTAL EQUIPO

    COSTO UNITARIO

    ANALISIS DE COSTOS UNITARIOS N 6

    DESCRIPCION

    CEMENTO

    ARENA

    PIEDRA

    DESCRIPCION

    CAPATAZ

    OPERARIO

    OFICIAL

    PEON

    DESCRIPCION

    HERRAMIENTAS 3% M.O.

    MEZCLADORA

    VIBRADOR

    TOTAL MATERIAL

    TOTAL MANO DE OBRA

  • 5/24/2018 2 Da Parcial de Costos

    11/15

    .(3) S/. 7.05

    S/. 467.71

    TOTAL EQUIPO

    COSTO UNITARIO

  • 5/24/2018 2 Da Parcial de Costos

    12/15

    FORMULA POLINOMICA

    1.000 x 48.000 2.000 x 3.600 3.000 x 525.000

    1.00 MANO DE OBRA

    J .---------> 47.360 x 48.000 + 8.480 x 3.600 + 0.890 x 525.000

    8627.265

    25539.265

    2.00 CEMENTO

    Ce .---------> 0.000 x 48.000 + 6.160 x 3.600 + 0.000 x 525.000

    3533.376

    25539.265

    3.00 HORMIGON, ARENA Y PIEDRA

    Ar .---------> 0.000 x 48.000 + 5.000 x 3.600 + 0.000 x 525.000

    1098.450

    25539.265

    4.00 ACERO, ALAMBRE, CLAVOS, PERNOS

    Ac .---------> 0.000 x 48.000 + 0.000 x 3.600 + 6.840 x 525.000

    3950.100

    25539.265

    5.00 MADERA, TRIPLAY, PROTECTOR ENCOFRADO

    Md .---------> 0.000 x 48.000 + 0.000 x 3.600 + 0.000 x 525.000

    5040.000

    25539.265

    6.00 HERRAMIENTAS

    Hrr .---------> 1.420 x 48.000 + 4.110 x 3.600 + 0.240 x 525.000

    553.724

    25539.265

    7.00 GASTOS GENERALES Y UTILIDAD

    2736.350

    25539.265

    J .---------> = 0.338

    Ce .---------> = 0.138

    .---------> = 0.022

    Ar .---------> = 0.043

    Ac .---------> = 0.155

    GGyU .---------> = 0.107

    Md .---------> = 0.197

    Hrr

    Jo Ceo Aro Aco Mdo

    Jr Cer Arr Acr Mdr K = 0.338 0.043+ + 0.155 0.1970.138 + + + 0.0

  • 5/24/2018 2 Da Parcial de Costos

    13/15

    9.450

    9.450

    9.450

    9.450

    9.450

    9.450

    9.450

  • 5/24/2018 2 Da Parcial de Costos

    14/15

    METRADOS

    48.00 m3

    3.60 m2

    525.00 kg

    10.50 m3

    126.00 m2

    9.45 m3

    PRESUPUESTO

    METRADO C.U PARCIAL

    48.00 x 48.78 = 2341.44

    3.60 x 23.75 = 85.50

    525.00 x 7.97 = 4184.25

    10.50 x 284.25 = 2984.63

    126.00 x 69.74 = 8787.24

    9.45 x 467.71 = 4419.86

    COSTO DIRECTO = 22802.91

    GGyU 12.00% = 2736.35SUB TOTAL = 25539.26

    IGV 18.00% = 4597.07

    SUB TOTAL = 30136.33

    5.- ENCOFRADO EN COLUMNAS

    6.- CONCRETO EN COLUMNAS

    3.- ACERO EN COLUMNAS

    4.- CONCRETO EN ZAPATAS

    1.- EXCAVACION DE ZANJAS

    2.- SOLADO DE CONCRETO

    3.- ACERO EN COLUMNAS

    4.- CONCRETO EN ZAPATAS

    1.- EXCAVACION DE ZANJAS

    2.- SOLADO DE CONCRETO

    5.- ENCOFRADO EN COLUMNAS

    6.- CONCRETO EN COLUMNAS

  • 5/24/2018 2 Da Parcial de Costos

    15/15

    RELACION DE INSUMOS