Obra / Project: "PARAISO AKUMAL RESORT"
Ubicacin / Location: AKUMAL Q. ROO. Fecha / Date: MIERCOLES 11 DE FEBRERO DE 2015
Plano Ref/ Construction Plan: "EDIFICIO J"
CLAVE CONCEPTO UNIDADCANTIDAD
ANTERIOR
CANTIDAD ESTA
SEM. 07ACUMULADO 2014 CANTIDAD TOPE
CANTIDAD
RESTANTE
% DE
AVANCEP.U. IMPORTE SEMANA 06 IMPORTE ACUMULADO 2014
OBSERVACIONES ULTIMA
ESTIMACION
003 CIMENTACION (EDIFICIO J)
5VACONCLCMCONCRETO EN CIMENTACIN, LOSAS, COLUMNAS Y
MUROSM3 442.49 -442.49 0 442.49 442.49 0% $100.00 44,249.00-$ -$ DEDUCTIVA
5VACONCLCMCONCRETO EN CIMENTACIN, LOSAS, COLUMNAS Y
MUROSM3 0.00 442.49 442.49 442.49 0.00 100% $120.00 53,098.80$ 53,098.80$ ADITIVA
5CIMCURVM2 CIMBRA CURVA EN MUROS DE CONCRETO M2 135.86 -135.86 0 135.86 135.86 0% $180.00 24,454.80-$ -$ DEDUCTIVA
5CIMCURVM2 CIMBRA CURVA EN MUROS DE CONCRETO M2 0.00 135.86 135.86 135.86 0.00 100% $210.00 28,530.60$ 28,530.60$ ADITIVA
Subtotal estimacin 12,925.60$ Presupuesto inicial $ -
Deductiva -$ Anticipo $ -
Subtotal 1 12,925.60$ % Anticipo 0.00%
I. V, A. 16 % 2,068.10$ Total acumulado $ 723,737.82
Total factura 14,993.70$ % Pagado presupuesto 0%
Elabor: Ing. Edgardo Castillo Poot Revis: Ing. Efrain Carranza Aprob: Ing. Carlos Ortega Zuiga
PERIODO DEL 06/02/2015 AL 10/02/2015
ESTIMACION DE OBRA
ESTIMACIN No. 34 DE SEMANA 07(DEDUCTIVAS Y ADITIVAS DE CIMBRA Y CONCRETO)
CONTRUCCION DEL HOTEL PARAISO AKUMAL RESORT PERIODO DEL 06 FEBRERO DE 2015 AL 10 DE FEBRERO DE 2015 DE FECHA 11 DE FEBRERO DE 2015
Cantidad con letra: (Son Catorce mil novecientos noventa y tres pesos con 70/100 M.N.)
SALCON GSCH S. A. DE C. V. CONSTRUCTORA KARO S. A. DE C. V. DIRECTOR DEL PROYECTO